Rustagi Rusttagi Aarambha Phase- I
by RUSTAGI ESTATES PRIVATE LIMITED · Titwala, Thane 421605Also near MandaRegistered on MahaRERA as “RUSTTAGI AARAMBHA PHASE- I”
What’s in the report? →Possession date of Rustagi Rusttagi Aarambha Phase- I (MahaRERA P51700034204): 31 July 2026, moved from 22 February 2024 (25 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700034204. Status: Lapsed (registration period ended). Its completion date has moved from February 2024 to July 2026: 25 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700034204, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Rustagi Rusttagi Aarambha Phase- I?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rustagi Rusttagi Aarambha Phase- I has moved
22 February 2024
Completion date given when the project was registered
21 February 2025
Extended at the builder's request (MahaRERA application EXT51700019345)
Reason the builder gave MahaRERA:
“the Project got delayed due to various reasons including labour problem after COVID-19 impact because workers had gone to their native place. Apart of labour issues, there were changes in DP Rules and approval thereunder. Approval took lots…” Read the full reason
“the Project got delayed due to various reasons including labour problem after COVID-19 impact because workers had gone to their native place. Apart of labour issues, there were changes in DP Rules and approval thereunder. Approval took lots of time in getting the revised plans amended and approved from the planning authority. We had to do correction in specification of the project having three phases in this same layout to meet the customers requirements. Thereafter approaching allottees to get their consent for changes in the specification in the project under section 14(2) of RERA. We now…”31 March 2026
Extended at the builder's request (MahaRERA application EA04072501948)
Reason the builder gave MahaRERA:
“The project is in its final stage of completion, with most construction and finishing works already completed. The delay in obtaining the Occupancy Certificate is due to ongoing documentation compliances and approvals from relevant authorit…” Read the full reason
“The project is in its final stage of completion, with most construction and finishing works already completed. The delay in obtaining the Occupancy Certificate is due to ongoing documentation compliances and approvals from relevant authorities. Additionally, this phase is interconnected with another under-development phase, requiring coordinated completion of certain utilities and services. OC is expected in the coming months of 2025 only.”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Rustagi Rusttagi Aarambha Phase- I’s extension records on MahaRERA (P51700034204), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rustagi Rusttagi Aarambha Phase- I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Rusttagi Aarambha 2.0P51700076932 · possession 30 Mar 2027
- RUSTTAGI AARAMBHA PHASE-IIP51700034078 · possession 22 Feb 2026
- RUSTTAGI AARAMBHA PHASE-IIIP51700033998 · possession 22 Feb 2027
- MahaRERA registration
- P51700034204
- Status
- Lapsed (registration period ended)
- Builder
- RUSTAGI ESTATES PRIVATE LIMITED
- Location
- Titwala, Thane · 421605
- Project type
- Commercial
- Registered on
- 25 Mar 2022
- Completion date at registration
- February 2024
- Latest completion date
- July 2026
- Delay so far
- 25 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 72%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Rustagi Rusttagi Aarambha Phase- I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 | 100% | 100% | 100% | 100% |
| BUILDING NO 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1: covers 0 floors
- BUILDING NO 2: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rustagi Rusttagi Aarambha Phase- I every 1–2 months.
Rustagi Rusttagi Aarambha Phase- I: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1 (2 floors) · BUILDING NO 2 (2 floors, 18 units)
- Car parking: 5 open
- Land: 2,290 sq m (about 0.6 acres) · sanctioned built-up 250 sq m
- Map: Get directions
The builder’s record and reviews
Rustagi Estates has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Rustagi Rusttagi Aarambha Phase- I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rustagi Rusttagi Aarambha Phase- I: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rustagi Rusttagi Aarambha Phase- I
What is the possession date of Rustagi Rusttagi Aarambha Phase- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rustagi Rusttagi Aarambha Phase- I in Titwala, Thane is 31 July 2026 — 25 months later than 22 February 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 25 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Rustagi Rusttagi Aarambha Phase- I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rustagi Rusttagi Aarambha Phase- I's builder has filed on MahaRERA, the official one, is 31 July 2026, already 25 months later than the 22 February 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rustagi Rusttagi Aarambha Phase- I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I's builder applied to MahaRERA to extend the completion date 2 times: to 21 February 2025, giving the reason "the Project got delayed due to various reasons including labour problem after COVID-19 impact because workers had gone to their native place. Apart of labour issues, there were changes in DP Rules and approval thereunder. Approval took lots of time in getting the revised plans amended and approved from the planning authority. We had to do correction in specification of the project having three phases in this same layout to meet the customers requirements. Thereafter approaching allottees to get their consent for changes in the specification in the project under section 14(2) of RERA. We now…"; to 31 March 2026, giving the reason "The project is in its final stage of completion, with most construction and finishing works already completed. The delay in obtaining the Occupancy Certificate is due to ongoing documentation compliances and approvals from relevant authorities. Additionally, this phase is interconnected with another under-development phase, requiring coordinated completion of certain utilities and services. OC is expected in the coming months of 2025 only.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Rustagi Rusttagi Aarambha Phase- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rustagi Rusttagi Aarambha Phase- I in Titwala, Thane is P51700034204.
Is Rustagi Rusttagi Aarambha Phase- I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I is registered as P51700034204 and its status is "Lapsed (registration period ended)".
What is the current construction status of Rustagi Rusttagi Aarambha Phase- I? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Rustagi Rusttagi Aarambha Phase- I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Rustagi Rusttagi Aarambha Phase- I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I is registered on MahaRERA as P51700034204, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rustagi Rusttagi Aarambha Phase- I?
Rustagi Rusttagi Aarambha Phase- I isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rustagi Rusttagi Aarambha Phase- I?
For a flat in Rustagi Rusttagi Aarambha Phase- I (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Rustagi Rusttagi Aarambha Phase- I received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Rustagi Rusttagi Aarambha Phase- I?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Rustagi Rusttagi Aarambha Phase- I uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rustagi Rusttagi Aarambha Phase- I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Rustagi Rusttagi Aarambha Phase- I have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Rusttagi Aarambha 2.0 (P51700076932, possession 30 Mar 2027); RUSTTAGI AARAMBHA PHASE-II (P51700034078, possession 22 Feb 2026); RUSTTAGI AARAMBHA PHASE-III (P51700033998, possession 22 Feb 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Rustagi Rusttagi Aarambha Phase- I's possession date changes?
The latest dates are on Rustagi Rusttagi Aarambha Phase- I's MahaRERA page (P51700034204). GharKundli's Kundli Watch sends a free WhatsApp update on Rustagi Rusttagi Aarambha Phase- I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rustagi Rusttagi Aarambha Phase- I have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I has 2 buildings filed: BUILDING NO 1 with 2 floors; BUILDING NO 2 with 2 floors and 18 units.
How much parking does Rustagi Rusttagi Aarambha Phase- I have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 open car parking spaces for Rustagi Rusttagi Aarambha Phase- I.
How big is the land of Rustagi Rusttagi Aarambha Phase- I?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I stands on 2,290 sq m of land (about 0.6 acres), with 250 sq m of sanctioned built-up area.
What is the track record of Rustagi Rusttagi Aarambha Phase- I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Estates has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Rustagi Rusttagi Aarambha Phase- I?
Google Maps has reviews of Rustagi Rusttagi Aarambha Phase- I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rustagi Rusttagi Aarambha Phase- I?
Rustagi Rusttagi Aarambha Phase- I by RUSTAGI ESTATES PRIVATE LIMITED is in Titwala, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700034204, per GharKundli's check of MahaRERA records. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in Rustagi Rusttagi Aarambha Phase- I, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I has 0 homes in 2 towers registered on MahaRERA, and 72% of them are sold or booked.
When was Rustagi Rusttagi Aarambha Phase- I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rustagi Rusttagi Aarambha Phase- I was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.
Does Rustagi Rusttagi Aarambha Phase- I have any legal issues or court cases?
No court cases are listed for Rustagi Rusttagi Aarambha Phase- I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Rustagi Rusttagi Aarambha Phase- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUSTAGI ESTATES PRIVATE LIMITED, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rustagi Rusttagi Aarambha Phase- I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Titwala (421605)
- Charms City Phase II
- Ganpati Heights
- Marathe Tower
- Pitambare Tower
- Shree Gajanan Plaza
- Sai Vrindavan
- Mangalmurti Heights
- Sarnobat Residency
Other projects by RUSTAGI ESTATES PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.