Neelpadma Seva Smruti

by Neelpadma Associates · Ayre, Thane 421201Also near Dombivli East, Ramnagar, Ram NagarRegistered on MahaRERA as “Seva Smruti”

What’s in the report? →

Possession date of Neelpadma Seva Smruti (MahaRERA P51700045235): 30 September 2026, moved from 31 May 2024 (24 months later), and it has already passed. It has 28 homes, 78% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700045235. Status: Lapsed (registration period ended). Its completion date has moved from May 2024 to September 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700045235, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about Neelpadma Seva Smruti?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Neelpadma Seva Smruti has moved

  1. 31 May 2024

    Completion date given when the project was registered

  2. 31 May 2025

    Extended at the builder's request (MahaRERA application EXT51700024296)

    Reason the builder gave MahaRERA: “Due to financial and technical issue there is delay in completing the project.”
  3. 31 May 2026

    Extended at the builder's request (MahaRERA application EA15102518128)

    Reason the builder gave MahaRERA:
    “I, Anant Narayan Karve, Partner of Neelpadma Associates, the Promoter of the project Seva Smruti bearing MahaRERA Registration No. P51700045235, situated at Dombivli, Maharashtra, hereby declare that: 1.The project could not be completed wi…” Read the full reason“I, Anant Narayan Karve, Partner of Neelpadma Associates, the Promoter of the project Seva Smruti bearing MahaRERA Registration No. P51700045235, situated at Dombivli, Maharashtra, hereby declare that: 1.The project could not be completed within the earlier declared completion period due to 1) a significant number of buyers have delayed the payment schedules as per their respective agreements. This shortfall in cash flow has indirectly impacted the procurement of raw materials and timely payment to contractors, thereby affecting overall construction progress. 2) Several contractors and suppl…”
  4. 30 September 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Neelpadma Seva Smruti’s extension records on MahaRERA (P51700045235), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Neelpadma Seva Smruti

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700045235
Status
Lapsed (registration period ended)
Builder
Neelpadma Associates
Location
Ayre, Thane · 421201
Project type
Residential / Group Housing
Registered on
10 May 2022
Completion date at registration
May 2024
Latest completion date
September 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
78%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Neelpadma Seva Smruti, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Seva Smruti100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • Seva Smruti: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neelpadma Seva Smruti every 1–2 months.

Neelpadma Seva Smruti: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA.

Read Google reviews of Neelpadma Seva Smruti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Neelpadma Seva Smruti: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Neelpadma Seva Smruti

What is the possession date of Neelpadma Seva Smruti?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neelpadma Seva Smruti in Ayre, Thane is 30 September 2026 — 24 months later than 31 May 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Neelpadma Seva Smruti?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Neelpadma Seva Smruti's builder has filed on MahaRERA, the official one, is 30 September 2026, already 24 months later than the 31 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Neelpadma Seva Smruti extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2025, giving the reason "Due to financial and technical issue there is delay in completing the project."; to 31 May 2026, giving the reason "I, Anant Narayan Karve, Partner of Neelpadma Associates, the Promoter of the project Seva Smruti bearing MahaRERA Registration No. P51700045235, situated at Dombivli, Maharashtra, hereby declare that: 1.The project could not be completed within the earlier declared completion period due to 1) a significant number of buyers have delayed the payment schedules as per their respective agreements. This shortfall in cash flow has indirectly impacted the procurement of raw materials and timely payment to contractors, thereby affecting overall construction progress. 2) Several contractors and suppl…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Neelpadma Seva Smruti?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neelpadma Seva Smruti in Ayre, Thane is P51700045235.

Is Neelpadma Seva Smruti registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti is registered as P51700045235 and its status is "Lapsed (registration period ended)".

What is the current construction status of Neelpadma Seva Smruti? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Seva Smruti is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Neelpadma Seva Smruti have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Neelpadma Seva Smruti safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti is registered on MahaRERA as P51700045235, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Neelpadma Seva Smruti?

Neelpadma Seva Smruti isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Neelpadma Seva Smruti?

For a flat in Neelpadma Seva Smruti (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Neelpadma Seva Smruti received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Neelpadma Seva Smruti?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Neelpadma Seva Smruti uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Neelpadma Seva Smruti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Neelpadma Seva Smruti's possession date changes?

The latest dates are on Neelpadma Seva Smruti's MahaRERA page (P51700045235). GharKundli's Kundli Watch sends a free WhatsApp update on Neelpadma Seva Smruti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Neelpadma Seva Smruti have?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti has one building filed: Seva Smruti with 9 floors and 35 units.

How big is the land of Neelpadma Seva Smruti?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti stands on 558 sq m of land (about 0.1 acres), with 2,160 sq m of sanctioned built-up area.

What is the track record of Neelpadma Seva Smruti's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Associates (a group of 8 linked companies) has 12 projects on MahaRERA since 2019, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 18 months late); 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Neelpadma Seva Smruti?

Google Maps has reviews of Neelpadma Seva Smruti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Neelpadma Seva Smruti?

Neelpadma Seva Smruti by Neelpadma Associates is in Ayre, Thane, pincode 421201 (near Dombivli East, Ramnagar, Ram Nagar), Maharashtra, and is registered on MahaRERA as P51700045235, per GharKundli's check of MahaRERA records. Its land is filed as C.T.S.NO 1150 TO 1151. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Neelpadma Seva Smruti, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti has 28 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was Neelpadma Seva Smruti registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Neelpadma Seva Smruti was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.

Does Neelpadma Seva Smruti have any legal issues or court cases?

No court cases are listed for Neelpadma Seva Smruti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Neelpadma Seva Smruti?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Neelpadma Associates, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Kalyan

All 408 projects in Tilaknagar (421201) →

Other projects by Neelpadma Associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.