NB Aarambh Residency
by NB ASSOCIATES PRIVATE LIMITED · Near Sai Baba Temple, Thane 421605Also near Titwala, Kalyan, Manda
What’s in the report? →Possession date of NB Aarambh Residency (MahaRERA P51700046135): 31 May 2026, moved from 31 May 2024 (24 months later), and it has already passed. It has 18 homes, 72% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700046135. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700046135, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2026) has passed.
What do you want to know about NB Aarambh Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of NB Aarambh Residency has moved
31 May 2024
Completion date given when the project was registered
31 May 2025
Extended at the builder's request (MahaRERA application EXT51700024292)
31 May 2026
Extended at the builder's request (MahaRERA application EA30052501373)
Reason the builder gave MahaRERA: “Earlier our project was g+3 floor now we have changed the plan to g+7.to complete the same we require more time so i request you to grant us extension of one year”
Source: NB Aarambh Residency’s extension records on MahaRERA (P51700046135), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NB Aarambh Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700046135
- Status
- Lapsed (registration period ended)
- Builder
- NB ASSOCIATES PRIVATE LIMITED
- Location
- Near Sai Baba Temple, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 20 Jun 2022
- Completion date at registration
- May 2024
- Latest completion date
- May 2026
- Delay so far
- 24 months
- Homes
- 18
- Sold or booked
- 72%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NB Aarambh Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NB AARAMBH RESIDENCY | 100% | 100% | 60% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- NB AARAMBH RESIDENCY: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NB Aarambh Residency every 1–2 months.
NB Aarambh Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: NB AARAMBH RESIDENCY (5 floors, 26 units)
- Land: 718 sq m (about 0.2 acres) · sanctioned built-up 1,137 sq m
- Boundaries filed include: SAI BABA TEMPLE
- Land, as filed: 31/32
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NB Aarambh Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NB Aarambh Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about NB Aarambh Residency
What is the possession date of NB Aarambh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NB Aarambh Residency in Near Sai Baba Temple, Thane is 31 May 2026 — 24 months later than 31 May 2024, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for NB Aarambh Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NB Aarambh Residency's builder has filed on MahaRERA, the official one, is 31 May 2026, already 24 months later than the 31 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NB Aarambh Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2025; to 31 May 2026, giving the reason "Earlier our project was g+3 floor now we have changed the plan to g+7.to complete the same we require more time so i request you to grant us extension of one year".
What is the RERA number of NB Aarambh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NB Aarambh Residency in Near Sai Baba Temple, Thane is P51700046135.
Is NB Aarambh Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency is registered as P51700046135 and its status is "Lapsed (registration period ended)".
What is the current construction status of NB Aarambh Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NB AARAMBH RESIDENCY is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does NB Aarambh Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is NB Aarambh Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency is registered on MahaRERA as P51700046135, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in NB Aarambh Residency?
NB Aarambh Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in NB Aarambh Residency?
For a flat in NB Aarambh Residency (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has NB Aarambh Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 May 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for NB Aarambh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 May 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has NB Aarambh Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for NB Aarambh Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if NB Aarambh Residency's possession date changes?
The latest dates are on NB Aarambh Residency's MahaRERA page (P51700046135). GharKundli's Kundli Watch sends a free WhatsApp update on NB Aarambh Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NB Aarambh Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency has one building filed: NB AARAMBH RESIDENCY with 5 floors and 26 units.
How big is the land of NB Aarambh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency stands on 718 sq m of land (about 0.2 acres), with 1,137 sq m of sanctioned built-up area.
What are the reviews of NB Aarambh Residency?
Google Maps has reviews of NB Aarambh Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of NB Aarambh Residency?
NB Aarambh Residency by NB ASSOCIATES PRIVATE LIMITED is in Near Sai Baba Temple, Thane, pincode 421605 (near Titwala, Kalyan, Manda), Maharashtra, and is registered on MahaRERA as P51700046135, per GharKundli's check of MahaRERA records. Its boundaries filed there include SAI BABA TEMPLE. Its land is filed as 31/32. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in NB Aarambh Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency has 18 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.
When was NB Aarambh Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NB Aarambh Residency was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Does NB Aarambh Residency have any legal issues or court cases?
No court cases are listed for NB Aarambh Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of NB Aarambh Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NB ASSOCIATES PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of NB Aarambh Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.