by SACVIR REALTORS LLP · Near Sheth Zuri, Laxmi Nagar, Thane 400601Also near Panchpakhadi, Thane West, MajiwadaRegistered on MahaRERA as “KAPIL CONTINENTAL”

What’s in the report? →

Possession date of Sacvir Kapil Continental (MahaRERA P51700045703): 31 December 2029, moved from 11 April 2025 (56 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700045703, and currently active.

Source: MahaRERA website — records for P51700045703, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sacvir Kapil Continental?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sacvir Kapil Continental has moved

  1. 11 April 2025

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA31122519208)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to the project timeline being impacted by modifications in the permissible FSI (Floor Space Index) regulations, which…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to the project timeline being impacted by modifications in the permissible FSI (Floor Space Index) regulations, which required necessary revisions in the project plans and approvals from the competent authority. As these changes were beyond the control of the promoter, additional time was required to incorporate the revised FSI norms, obtain approvals, and align construction activities accordingly. Hence, the extension is being sought to ensure full compliance with regu…”

Source: Sacvir Kapil Continental’s extension records on MahaRERA (P51700045703), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sacvir Kapil Continental

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700045703
Status
Registered and active
Builder
SACVIR REALTORS LLP
Location
Near Sheth Zuri, Laxmi Nagar, Thane · 400601
Project type
Commercial
Registered on
6 Jun 2022
Completion date at registration
April 2025
Latest completion date
December 2029
Delay so far
56 months
Homes
0
Sold or booked
29%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sacvir Kapil Continental, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAPIL CONTINENTAL60%30%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • KAPIL CONTINENTAL: covers 14 (2 Basements + Ground + 5 Podium + 6 Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sacvir Kapil Continental every 1–2 months.

Sacvir Kapil Continental: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sacvir Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA.

Read Google reviews of Sacvir Kapil Continental →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sacvir Kapil Continental: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sacvir Kapil Continental

What is the possession date of Sacvir Kapil Continental?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sacvir Kapil Continental in Near Sheth Zuri, Laxmi Nagar, Thane is 31 December 2029 — 56 months later than 11 April 2025, the date given at registration.

The date has already moved 56 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sacvir Kapil Continental?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sacvir Kapil Continental's builder has filed on MahaRERA, the official one, is 31 December 2029, already 56 months later than the 11 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sacvir Kapil Continental extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to the project timeline being impacted by modifications in the permissible FSI (Floor Space Index) regulations, which required necessary revisions in the project plans and approvals from the competent authority. As these changes were beyond the control of the promoter, additional time was required to incorporate the revised FSI norms, obtain approvals, and align construction activities accordingly. Hence, the extension is being sought to ensure full compliance with regu…".

What is the RERA number of Sacvir Kapil Continental?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sacvir Kapil Continental in Near Sheth Zuri, Laxmi Nagar, Thane is P51700045703.

Is Sacvir Kapil Continental registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental is registered as P51700045703 and its status is "Registered and active".

What is the current construction status of Sacvir Kapil Continental? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KAPIL CONTINENTAL is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sacvir Kapil Continental have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sacvir Kapil Continental safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental is registered on MahaRERA as P51700045703, its completion date has moved 56 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sacvir Kapil Continental?

Sacvir Kapil Continental is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sacvir Kapil Continental?

For a flat in Sacvir Kapil Continental (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sacvir Kapil Continental received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental is still under construction, with 31 December 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Sacvir Kapil Continental uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sacvir Kapil Continental was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sacvir Kapil Continental's possession date changes?

The latest dates are on Sacvir Kapil Continental's MahaRERA page (P51700045703). GharKundli's Kundli Watch sends a free WhatsApp update on Sacvir Kapil Continental every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sacvir Kapil Continental have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental has one building filed: KAPIL CONTINENTAL with 9 floors and 24 units.

How big is the land of Sacvir Kapil Continental?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental stands on 450 sq m of land (about 0.1 acres), with 2,005 sq m of sanctioned built-up area.

What is the track record of Sacvir Kapil Continental's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 1 past the promised date (typically 19 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sacvir Kapil Continental?

Google Maps has reviews of Sacvir Kapil Continental written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sacvir Kapil Continental?

Sacvir Kapil Continental by SACVIR REALTORS LLP is in Near Sheth Zuri, Laxmi Nagar, Thane, pincode 400601 (near Panchpakhadi, Thane West, Majiwada), Maharashtra, and is registered on MahaRERA as P51700045703, per GharKundli's check of MahaRERA records. Its land is filed as 87/3/3 & 88/1/C. GharKundli lists all 178 MahaRERA projects in Thane (400601).

How many flats are in Sacvir Kapil Continental, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental has 0 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.

When was Sacvir Kapil Continental registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sacvir Kapil Continental was registered on MahaRERA on 6 June 2022. GharKundli did not find a title report on the land on file there.

Does Sacvir Kapil Continental have any legal issues or court cases?

No court cases are listed for Sacvir Kapil Continental on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sacvir Kapil Continental?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SACVIR REALTORS LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Thane

All 178 projects in Thane (400601) →

Other projects by SACVIR REALTORS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.