Tycoons Square Avenue III Tower D

by Tycoons Avanti Projects LLP · Konkan Vasahat, Thane

Possession date of Tycoons Square Avenue III Tower D: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700035166, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Tycoons Square Avenue III Tower D?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Tycoons Square Avenue III Tower D has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Tycoons Square Avenue III Tower D’s extension records on MahaRERA (P51700035166), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tycoons Square Avenue III Tower D

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints and 6 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700035166
Status
Registered and active
Builder
Tycoons Avanti Projects LLP
Location
Konkan Vasahat, Thane · 421301
Project type
Others
Registered on
10 May 2022
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
184
Towers
1
Complaints on MahaRERA
3
Court cases listed
6
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Tycoons Square Avenue III Tower D, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower D15%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tycoons Square Avenue III Tower D every month.

Tycoons Square Avenue III Tower D: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tower D (36 floors)
  • Land: 1,681 sq m (about 0.4 acres) · sanctioned built-up 11,990 sq m

The builder’s record and reviews

Tycoons Avanti Projects (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 3 past the promised date (typically 29 months late); 3 lapsed. 104 complaints on MahaRERA across 7 projects.

Read Google reviews of Tycoons Square Avenue III Tower D →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tycoons Square Avenue III Tower D: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Tycoons Square Avenue III Tower D

What is the possession date of Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Tycoons Square Avenue III Tower D in Konkan Vasahat, Thane is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Tycoons Square Avenue III Tower D?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tycoons Square Avenue III Tower D's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Tycoons Square Avenue III Tower D in Konkan Vasahat, Thane is P51700035166.

Is Tycoons Square Avenue III Tower D registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D is registered as P51700035166 and its status is "Registered and active".

What is the construction status of Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tower D is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Tycoons Square Avenue III Tower D have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Tycoons Square Avenue III Tower D safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D is registered on MahaRERA as P51700035166, its completion date has not been moved by the builder and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Tycoons Square Avenue III Tower D have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Tycoons Square Avenue I Tower A (P51700029986, possession 30 Jul 2025); Tycoons Square Avenue I Tower B (P51700004794, possession 30 Oct 2027); Tycoons Square Avenue I Tower D (P51700023614, possession 30 Oct 2025); Tycoons Square Avenue III Tower C (P51700004049, possession 30 Jun 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Tycoons Square Avenue III Tower D's possession date changes?

The latest dates are on Tycoons Square Avenue III Tower D's MahaRERA page (P51700035166). GharKundli's Kundli Watch sends a free WhatsApp update on Tycoons Square Avenue III Tower D every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tycoons Square Avenue III Tower D have?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D has one building filed: Tower D with 36 floors.

How big is the land of Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D stands on 1,681 sq m of land (about 0.4 acres), with 11,990 sq m of sanctioned built-up area.

What is the track record of Tycoons Square Avenue III Tower D's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Avanti Projects (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 3 past the promised date (typically 29 months late); 3 lapsed. 104 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Tycoons Square Avenue III Tower D?

Google Maps has reviews of Tycoons Square Avenue III Tower D written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Tycoons Square Avenue III Tower D?

Tycoons Square Avenue III Tower D by Tycoons Avanti Projects LLP is in Konkan Vasahat, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700035166, per GharKundli's check of MahaRERA records.

How many homes are in Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D has 184 homes in 1 tower registered on MahaRERA.

When was Tycoons Square Avenue III Tower D registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Tycoons Square Avenue III Tower D was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Tycoons Square Avenue III Tower D?

6 court cases are listed for Tycoons Square Avenue III Tower D on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Tycoons Square Avenue III Tower D?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Tycoons Avanti Projects LLP, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →