Alishan Park 3
by Aliakbar Yusuf Zojwalla · Near Chhatri Bunglow, Thane 421301
What’s in the report? →Possession date of Alishan Park 3 (MahaRERA P51700046147): 30 September 2027, moved from 31 December 2025 (17 months later). It has 48 homes, 69% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700046147, and currently active. Its completion date has moved from December 2025 to September 2027: 17 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700046147, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Alishan Park 3?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Alishan Park 3 has moved
31 December 2025
Completion date given when the project was registered
31 May 2027
Extended at the builder's request (MahaRERA application EA28052621129)
Reason the builder gave MahaRERA:
“The project construction has been substantially completed and the application for Occupancy Certificate (OC) has already been submitted to the Planning Authority. The delay in obtaining the OC is purely administrative and beyond the Promote…” Read the full reason
“The project construction has been substantially completed and the application for Occupancy Certificate (OC) has already been submitted to the Planning Authority. The delay in obtaining the OC is purely administrative and beyond the Promoter’s control, despite all necessary compliances and follow-ups being completed. Since possession cannot be legally handed over without the OC, the extension is sought only to maintain MahaRERA compliance until the certificate is received. No prejudice will be caused to the allottees, as the physical work of the project is complete and no new construction o…”30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Alishan Park 3’s extension records on MahaRERA (P51700046147), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Alishan Park 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700046147
- Status
- Registered and active
- Builder
- Aliakbar Yusuf Zojwalla
- Location
- Near Chhatri Bunglow, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 20 Jun 2022
- Completion date at registration
- December 2025
- Latest completion date
- September 2027
- Delay so far
- 17 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 69%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Alishan Park 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Alishan Park 3 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Alishan Park 3: covers 48 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alishan Park 3 every 1–2 months.
Alishan Park 3: buildings, flats and land, as filed on MahaRERA
- Buildings: Alishan Park 3 (9 floors, 48 units)
- Car parking: 20 covered
- Land: 1,790 sq m (about 0.4 acres) · sanctioned built-up 3,872 sq m · recreational space 149 sq m
- Boundaries filed include: Sai Venkatesh Complex, Sidhhi Complex, Alishan Park 2
- Land, as filed: 14/3 16/6
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Alishan Park 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Alishan Park 3: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Alishan Park 3
What is the possession date of Alishan Park 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Alishan Park 3 in Near Chhatri Bunglow, Thane is 30 September 2027 — 17 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 17 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Alishan Park 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Alishan Park 3's builder has filed on MahaRERA, the official one, is 30 September 2027, already 17 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Alishan Park 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3's builder applied to MahaRERA to extend the completion date once: to 31 May 2027, giving the reason "The project construction has been substantially completed and the application for Occupancy Certificate (OC) has already been submitted to the Planning Authority. The delay in obtaining the OC is purely administrative and beyond the Promoter’s control, despite all necessary compliances and follow-ups being completed. Since possession cannot be legally handed over without the OC, the extension is sought only to maintain MahaRERA compliance until the certificate is received. No prejudice will be caused to the allottees, as the physical work of the project is complete and no new construction o…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Alishan Park 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Alishan Park 3 in Near Chhatri Bunglow, Thane is P51700046147.
Is Alishan Park 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 is registered as P51700046147 and its status is "Registered and active".
What is the current construction status of Alishan Park 3? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Alishan Park 3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Alishan Park 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Alishan Park 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 is registered on MahaRERA as P51700046147, its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Alishan Park 3?
Alishan Park 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Alishan Park 3?
For a flat in Alishan Park 3 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Alishan Park 3 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 is still under construction, with 30 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Alishan Park 3 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Alishan Park 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Alishan Park 3's possession date changes?
The latest dates are on Alishan Park 3's MahaRERA page (P51700046147). GharKundli's Kundli Watch sends a free WhatsApp update on Alishan Park 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Alishan Park 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 has one building filed: Alishan Park 3 with 9 floors and 48 units.
How much parking does Alishan Park 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered car parking spaces for Alishan Park 3.
How big is the land of Alishan Park 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 stands on 1,790 sq m of land (about 0.4 acres), with 3,872 sq m of sanctioned built-up area and 149 sq m of recreational open space.
What are the reviews of Alishan Park 3?
Google Maps has reviews of Alishan Park 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Alishan Park 3?
Alishan Park 3 by Aliakbar Yusuf Zojwalla is in Near Chhatri Bunglow, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700046147, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sai Venkatesh Complex, Sidhhi Complex, Alishan Park 2. Its land is filed as 14/3 16/6. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Alishan Park 3, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 has 48 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.
When was Alishan Park 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Alishan Park 3 was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Does Alishan Park 3 have any legal issues or court cases?
No court cases are listed for Alishan Park 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Alishan Park 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aliakbar Yusuf Zojwalla.
Check it yourself on MahaRERA
- How to check the possession date of Alishan Park 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.