ASHAPURA GALAXY
by ASHAPURA ESTATES · Vadavali Gaon, Thane
Possession date of ASHAPURA GALAXY: 31 July 2027, moved from 30 June 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700045776, and currently active. Its completion date has moved from June 2026 to July 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ASHAPURA GALAXY?
How the possession date of ASHAPURA GALAXY has moved
30 June 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA26062621570)
Reason the builder gave MahaRERA: “Due to Slow sale of under Construction Unit”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ASHAPURA GALAXY’s extension records on MahaRERA (P51700045776), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ASHAPURA GALAXY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700045776
- Status
- Registered and active
- Builder
- ASHAPURA ESTATES
- Location
- Vadavali Gaon, Thane · 421102
- Project type
- Others
- Registered on
- 9 Jun 2022
- Completion date at registration
- June 2026
- Latest completion date
- July 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 189
- Sold or booked
- 61%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ASHAPURA GALAXY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A-1 | 100% | 100% | 100% | 100% |
| A-2 | 100% | 100% | 100% | 0% |
| B-1 | 100% | 100% | 70% | 0% |
| C-1 | 70% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A-1: covers 12 floors
- A-2: covers 12 floors
- B-1: covers 12 floors
- C-1: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ASHAPURA GALAXY every month.
ASHAPURA GALAXY: buildings, flats and land, as filed on MahaRERA
- Buildings: A-1 (14 floors, 71 units) · A-2 (14 floors, 71 units) · B-1 (14 floors, 47 units) · C-1 (4 floors, 33 units)
- Land: 3,857 sq m (about 1.0 acres) · sanctioned built-up 13,494 sq m · recreational space 386 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ASHAPURA GALAXY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ASHAPURA GALAXY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ASHAPURA GALAXY
What is the possession date of ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASHAPURA GALAXY in Vadavali Gaon, Thane is 31 July 2027 — 9 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ASHAPURA GALAXY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ASHAPURA GALAXY's builder has filed on MahaRERA, the official one, is 31 July 2027, already 9 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ASHAPURA GALAXY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Due to Slow sale of under Construction Unit". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ASHAPURA GALAXY in Vadavali Gaon, Thane is P51700045776.
Is ASHAPURA GALAXY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY is registered as P51700045776 and its status is "Registered and active".
What is the construction status of ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does ASHAPURA GALAXY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ASHAPURA GALAXY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY is registered on MahaRERA as P51700045776, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ASHAPURA GALAXY's possession date changes?
The latest dates are on ASHAPURA GALAXY's MahaRERA page (P51700045776). GharKundli's Kundli Watch sends a free WhatsApp update on ASHAPURA GALAXY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ASHAPURA GALAXY have?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY has 4 buildings filed: A-1 with 14 floors and 71 units; A-2 with 14 floors and 71 units; B-1 with 14 floors and 47 units; C-1 with 4 floors and 33 units.
How big is the land of ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY stands on 3,857 sq m of land (about 1.0 acres), with 13,494 sq m of sanctioned built-up area and 386 sq m of recreational open space.
Where can I read reviews of ASHAPURA GALAXY?
Google Maps has reviews of ASHAPURA GALAXY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ASHAPURA GALAXY?
ASHAPURA GALAXY by ASHAPURA ESTATES is in Vadavali Gaon, Thane (pincode 421102), Maharashtra, and is registered on MahaRERA as P51700045776, per GharKundli's check of MahaRERA records.
How many homes are in ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY has 189 homes in 4 towers registered on MahaRERA, and 61% of them are sold or booked.
When was ASHAPURA GALAXY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHAPURA GALAXY was registered on MahaRERA on 9 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on ASHAPURA GALAXY?
No court cases are listed for ASHAPURA GALAXY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ASHAPURA GALAXY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASHAPURA ESTATES.
Check it yourself on MahaRERA
- How to check the possession date of ASHAPURA GALAXY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Royal Hills
- MAJESTY HEIGHTS
- Mangeshi Dhara
- VIDHI IMPRESSION
- OM TRIMURTI DARSHAN
- Balaji Govind
- SWAMI ELITE
- RAM JANKI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.