by Mega Creative LLP · Manda Titwala, Thane 421605Also near Kalyan, Titwala East

What’s in the report? →

Possession date of Mega Pearl (MahaRERA P51700046279): 30 April 2027. It has 172 homes, 86% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700046279, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700046279, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mega Pearl?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mega Pearl has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mega Pearl’s extension records on MahaRERA (P51700046279), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mega Pearl

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700046279
Status
Registered and active
Builder
Mega Creative LLP
Location
Manda Titwala, Thane · 421605
Project type
Others
Registered on
20 Jun 2022
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
172
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mega Pearl, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEGA PEARL100%84%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mega Pearl every 1–2 months.

Mega Pearl: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mega Pearl →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mega Pearl: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mega Pearl

What is the possession date of Mega Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mega Pearl in Manda Titwala, Thane is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Mega Pearl?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mega Pearl's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Mega Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mega Pearl in Manda Titwala, Thane is P51700046279.

Is Mega Pearl registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl is registered as P51700046279 and its status is "Registered and active".

What is the current construction status of Mega Pearl? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MEGA PEARL is 84% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Mega Pearl have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mega Pearl safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl is registered on MahaRERA as P51700046279, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mega Pearl?

Mega Pearl is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mega Pearl?

For a flat in Mega Pearl (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mega Pearl received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Mega Pearl uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mega Pearl was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mega Pearl's possession date changes?

The latest dates are on Mega Pearl's MahaRERA page (P51700046279). GharKundli's Kundli Watch sends a free WhatsApp update on Mega Pearl every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mega Pearl have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl has one building filed: MEGA PEARL with 19 floors.

How big is the land of Mega Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl stands on 3,000 sq m of land (about 0.7 acres), with 6,639 sq m of sanctioned built-up area.

What are the reviews of Mega Pearl?

Google Maps has reviews of Mega Pearl written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mega Pearl?

Mega Pearl by Mega Creative LLP is in Manda Titwala, Thane, pincode 421605 (near Kalyan, Titwala East), Maharashtra, and is registered on MahaRERA as P51700046279, per GharKundli's check of MahaRERA records. Its boundaries filed there include Titwala Ganpati Mandir Road. Its land is filed as S No 50 H No 1/B/2. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Mega Pearl, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl has 172 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Mega Pearl registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mega Pearl was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.

Does Mega Pearl have any legal issues or court cases?

No court cases are listed for Mega Pearl on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Mega Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mega Creative LLP.

All projects with possession due in 2027 in Thane →

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →