Possession date of DILKAP CENTRE: 30 October 2027, moved from 30 October 2023 (44 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900011709, and currently active. Its completion date has moved from October 2023 to October 2027: 44 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DILKAP CENTRE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DILKAP CENTRE has moved

  1. 30 October 2023

    Completion date given when the project was registered

  2. 31 May 2025

    Extended at the builder's request (MahaRERA application EXT51900018847)

    Reason the builder gave MahaRERA:
    “CFO FINAL PLAN HAS BEEN SANCTIONED. DELAY IN DUE DILIGENCE FROM BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO SCRUTINY DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC…” Read the full reason“CFO FINAL PLAN HAS BEEN SANCTIONED. DELAY IN DUE DILIGENCE FROM BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO SCRUTINY DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC HAS BEEN PROLONGING TO CLEAR & FINALISE.”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA11092502561)

    Reason the builder gave MahaRERA:
    “I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900011709.As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 30.06.2027. The order is…” Read the full reason“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900011709.As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 30.06.2027. The order is uploaded in Other Tab for your reference”
  4. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DILKAP CENTRE’s extension records on MahaRERA (P51900011709), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DILKAP CENTRE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900011709
Status
Registered and active
Builder
GORKAP PROPERTIES & INVESTMENTS PVT. LTD
Location
Cuffe Parade, Mumbai · 400070
Project type
Commercial
Registered on
31 Aug 2017
Completion date at registration
October 2023
Latest completion date
October 2027
Delay so far
44 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
72%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
1
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of DILKAP CENTRE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DILKAP CENTRE95%100%96%40%

Commencement certificate (CC), as filed on MahaRERA

  • DILKAP CENTRE: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DILKAP CENTRE every month.

DILKAP CENTRE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops101 – 75852
Office Space394 – 3,77242
  • Buildings: DILKAP CENTRE (10 floors, 94 units)
  • Land: 3,786 sq m (about 0.9 acres) · sanctioned built-up 6,632 sq m · recreational space 723 sq m
  • Boundaries filed include: AKRUTI ORCHID PARK, PVT ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects.

Read Google reviews of DILKAP CENTRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DILKAP CENTRE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DILKAP CENTRE

What is the possession date of DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DILKAP CENTRE in Cuffe Parade, Mumbai is 30 October 2027 — 44 months later than 30 October 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DILKAP CENTRE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DILKAP CENTRE's builder has filed on MahaRERA, the official one, is 30 October 2027, already 44 months later than the 30 October 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DILKAP CENTRE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2025, giving the reason "CFO FINAL PLAN HAS BEEN SANCTIONED. DELAY IN DUE DILIGENCE FROM BMC AND CONCERNED AUTHORITIES. OUR FILE HAS BEEN SENT TO SCRUTINY DEPARTMENT OF BMC TO GET THE CLEAR SANCTIONS FOR FINAL APPROVAL WHICH IS STILL TAKING GREAT DEAL OF TIME. BMC HAS BEEN PROLONGING TO CLEAR & FINALISE."; to 30 June 2027, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900011709.As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 30.06.2027. The order is uploaded in Other Tab for your reference". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DILKAP CENTRE in Cuffe Parade, Mumbai is P51900011709.

Is DILKAP CENTRE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE is registered as P51900011709 and its status is "Registered and active".

What is the construction status of DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DILKAP CENTRE is 100% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.

Does DILKAP CENTRE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DILKAP CENTRE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE is registered on MahaRERA as P51900011709, its completion date has moved 44 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DILKAP CENTRE's possession date changes?

The latest dates are on DILKAP CENTRE's MahaRERA page (P51900011709). GharKundli's Kundli Watch sends a free WhatsApp update on DILKAP CENTRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DILKAP CENTRE have?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE has one building filed: DILKAP CENTRE with 10 floors and 94 units.

How big is the land of DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE stands on 3,786 sq m of land (about 0.9 acres), with 6,632 sq m of sanctioned built-up area and 723 sq m of recreational open space.

What is the track record of DILKAP CENTRE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Gorkap Properties & Investments (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 50 months); 3 still being built, 3 past the promised date (typically 24 months late). 13 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DILKAP CENTRE?

Google Maps has reviews of DILKAP CENTRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DILKAP CENTRE?

DILKAP CENTRE by GORKAP PROPERTIES & INVESTMENTS PVT. LTD is in Cuffe Parade, Mumbai (pincode 400070), near Kurla West, Parel, Byculla, Maharashtra, and is registered on MahaRERA as P51900011709, per GharKundli's check of MahaRERA records. Its boundaries filed there include AKRUTI ORCHID PARK, PVT ROAD.

How many homes are in DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE has 0 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was DILKAP CENTRE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DILKAP CENTRE was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on DILKAP CENTRE?

No court cases are listed for DILKAP CENTRE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of DILKAP CENTRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GORKAP PROPERTIES & INVESTMENTS PVT. LTD, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Mumbai City

All 92 projects in Kurla West (400070) →

Other projects by GORKAP PROPERTIES & INVESTMENTS PVT. LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.