Serenity Maple Paradise

by SERENITY INFRA · Kharegaon Kalwa, Thane 400605Also near Village - Parsik, Majiwade Thane WestRegistered on MahaRERA as “MAPLE PARADISE”

What’s in the report? →

Possession date of Serenity Maple Paradise (MahaRERA P51700047693): 31 March 2025, moved from 31 October 2024 (5 months later), and it has already passed. It has 84 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700047693. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700047693, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2025) has passed.

What do you want to know about Serenity Maple Paradise?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Serenity Maple Paradise has moved

  1. 31 October 2024

    Completion date given when the project was registered

  2. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51700025672)

    Reason the builder gave MahaRERA:
    “The construction of building is completed and application for Occupation Certificate is Pending for receiving the required No objection Certificate from various concern department. We intend to do the application for the occupation Certific…” Read the full reason“The construction of building is completed and application for Occupation Certificate is Pending for receiving the required No objection Certificate from various concern department. We intend to do the application for the occupation Certificate to the Thane Municipal Corporation with in next 15 days. i.e. on or before 15 January 2025. We except the occupation certificate/ Completion certificate will be issued by TMC on or before 31/03/2025. Therefore we request you to grant us an extension of Project completion till the date 31/03/2025.”

Source: Serenity Maple Paradise’s extension records on MahaRERA (P51700047693), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Serenity Maple Paradise

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700047693
Status
Lapsed (registration period ended)
Builder
SERENITY INFRA
Location
Kharegaon Kalwa, Thane · 400605
Project type
Residential / Group Housing
Registered on
21 Nov 2022
Completion date at registration
October 2024
Latest completion date
March 2025
Delay so far
5 months
Homes
84
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Serenity Maple Paradise, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAPLE PARADISE50%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Serenity Maple Paradise every 1–2 months.

Serenity Maple Paradise: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Serenity Maple Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Serenity Maple Paradise: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Serenity Maple Paradise

What is the possession date of Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Serenity Maple Paradise in Kharegaon Kalwa, Thane is 31 March 2025 — 5 months later than 31 October 2024, the date given at registration. That date has already passed.

The date has already moved 5 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Serenity Maple Paradise?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Serenity Maple Paradise's builder has filed on MahaRERA, the official one, is 31 March 2025, already 5 months later than the 31 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Serenity Maple Paradise extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise's builder applied to MahaRERA to extend the completion date once: to 31 March 2025, giving the reason "The construction of building is completed and application for Occupation Certificate is Pending for receiving the required No objection Certificate from various concern department. We intend to do the application for the occupation Certificate to the Thane Municipal Corporation with in next 15 days. i.e. on or before 15 January 2025. We except the occupation certificate/ Completion certificate will be issued by TMC on or before 31/03/2025. Therefore we request you to grant us an extension of Project completion till the date 31/03/2025.".

What is the RERA number of Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Serenity Maple Paradise in Kharegaon Kalwa, Thane is P51700047693.

Is Serenity Maple Paradise registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise is registered as P51700047693 and its status is "Lapsed (registration period ended)".

What is the current construction status of Serenity Maple Paradise? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MAPLE PARADISE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Serenity Maple Paradise have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Serenity Maple Paradise safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise is registered on MahaRERA as P51700047693, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Serenity Maple Paradise?

Serenity Maple Paradise isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Serenity Maple Paradise?

For a flat in Serenity Maple Paradise (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Serenity Maple Paradise received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Serenity Maple Paradise uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Serenity Maple Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Serenity Maple Paradise's possession date changes?

The latest dates are on Serenity Maple Paradise's MahaRERA page (P51700047693). GharKundli's Kundli Watch sends a free WhatsApp update on Serenity Maple Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Serenity Maple Paradise have?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise has one building filed: MAPLE PARADISE with 19 floors.

How big is the land of Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise stands on 3,090 sq m of land (about 0.8 acres), with 6,454 sq m of sanctioned built-up area.

What are the reviews of Serenity Maple Paradise?

Google Maps has reviews of Serenity Maple Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Serenity Maple Paradise?

Serenity Maple Paradise by SERENITY INFRA is in Kharegaon Kalwa, Thane, pincode 400605 (near Village - Parsik, Majiwade Thane West), Maharashtra, and is registered on MahaRERA as P51700047693, per GharKundli's check of MahaRERA records. Its boundaries filed there include RESIDENTIAL SOCIETY. Its land is filed as 54 HISSA NO2. GharKundli lists all 58 MahaRERA projects in Kalwa (400605).

How many flats are in Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise has 84 homes in 1 tower registered on MahaRERA.

When was Serenity Maple Paradise registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Serenity Maple Paradise was registered on MahaRERA on 21 November 2022. GharKundli did not find a title report on the land on file there.

Does Serenity Maple Paradise have any legal issues or court cases?

No court cases are listed for Serenity Maple Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Serenity Maple Paradise?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SERENITY INFRA.

Other projects in Kalwa (400605)

All 58 projects in Kalwa (400605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.