NANDANVAN HOMES-BUILDING B

by SHREE KRUPA BUILDERS · Parsik Nagar Near Reliance Market, ThaneAlso near Kalwa

Possession date of NANDANVAN HOMES-BUILDING B: 31 July 2027, moved from 27 February 2026 (13 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700028028, and currently active. Its completion date has moved from February 2026 to July 2027: 13 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NANDANVAN HOMES-BUILDING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NANDANVAN HOMES-BUILDING B has moved

  1. 27 February 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA18052621005)

    Reason the builder gave MahaRERA: “The delay is on account of slow sale and recovery of sale proceeds. The other factors are explained in Self Explanatory Letter”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NANDANVAN HOMES-BUILDING B’s extension records on MahaRERA (P51700028028), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NANDANVAN HOMES-BUILDING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700028028
Status
Registered and active
Builder
SHREE KRUPA BUILDERS
Location
Parsik Nagar Near Reliance Market, Thane · 400605
Project type
Others
Registered on
26 Jan 2021
Completion date at registration
February 2026
Latest completion date
July 2027
Delay so far
13 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
188
Sold or booked
69%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of NANDANVAN HOMES-BUILDING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING B100%70%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING B: covers 25 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NANDANVAN HOMES-BUILDING B every month.

NANDANVAN HOMES-BUILDING B: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shree Krupa Builders has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.

Read Google reviews of NANDANVAN HOMES-BUILDING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NANDANVAN HOMES-BUILDING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NANDANVAN HOMES-BUILDING B

What is the possession date of NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NANDANVAN HOMES-BUILDING B in Parsik Nagar Near Reliance Market, Thane is 31 July 2027 — 13 months later than 27 February 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NANDANVAN HOMES-BUILDING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NANDANVAN HOMES-BUILDING B's builder has filed on MahaRERA, the official one, is 31 July 2027, already 13 months later than the 27 February 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NANDANVAN HOMES-BUILDING B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The delay is on account of slow sale and recovery of sale proceeds. The other factors are explained in Self Explanatory Letter". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NANDANVAN HOMES-BUILDING B in Parsik Nagar Near Reliance Market, Thane is P51700028028.

Is NANDANVAN HOMES-BUILDING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B is registered as P51700028028 and its status is "Registered and active".

What is the construction status of NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING B is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does NANDANVAN HOMES-BUILDING B have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NANDANVAN HOMES-BUILDING B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B is registered on MahaRERA as P51700028028, its completion date has moved 13 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does NANDANVAN HOMES-BUILDING B have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: NANDANVAN HOMES BUILDING E (P51700079549, possession 27 Apr 2031); NANDANVAN HOMES-C1 (P51700013525, possession 30 Jun 2018). Check that your agreement names the registration of your own wing.

How can I get updates if NANDANVAN HOMES-BUILDING B's possession date changes?

The latest dates are on NANDANVAN HOMES-BUILDING B's MahaRERA page (P51700028028). GharKundli's Kundli Watch sends a free WhatsApp update on NANDANVAN HOMES-BUILDING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NANDANVAN HOMES-BUILDING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B has one building filed: BUILDING B with 27 floors and 208 units.

How much parking does NANDANVAN HOMES-BUILDING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 46 covered car parking spaces for NANDANVAN HOMES-BUILDING B.

How big is the land of NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B stands on 20,480 sq m of land (about 5.1 acres), with 3,237 sq m of sanctioned built-up area.

What is the track record of NANDANVAN HOMES-BUILDING B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Builders has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NANDANVAN HOMES-BUILDING B?

Google Maps has reviews of NANDANVAN HOMES-BUILDING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NANDANVAN HOMES-BUILDING B?

NANDANVAN HOMES-BUILDING B by SHREE KRUPA BUILDERS is in Parsik Nagar Near Reliance Market, Thane (pincode 400605), near Kalwa, Maharashtra, and is registered on MahaRERA as P51700028028, per GharKundli's check of MahaRERA records.

How many homes are in NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B has 188 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.

When was NANDANVAN HOMES-BUILDING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN HOMES-BUILDING B was registered on MahaRERA on 26 January 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on NANDANVAN HOMES-BUILDING B?

No court cases are listed for NANDANVAN HOMES-BUILDING B on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of NANDANVAN HOMES-BUILDING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE KRUPA BUILDERS, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 58 projects in Kalwa (400605) →

Other projects by SHREE KRUPA BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.