KUSUM RESIDENCY
by SURESH PADMAN PATIL · Ghansoli Navi Mumbai, Thane
Possession date of KUSUM RESIDENCY: 30 April 2027, moved from 31 March 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048955, and currently active. Its completion date has moved from March 2026 to April 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KUSUM RESIDENCY?
How the possession date of KUSUM RESIDENCY has moved
31 March 2026
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA18032620270)
Reason the builder gave MahaRERA:
“The extension is being sought as certain internal finishing works remain pending due to unforeseen circumstances. The above-mentioned items constitute the balance scope of work required for completion of the project. In view of the same, it…” Read the full reason
“The extension is being sought as certain internal finishing works remain pending due to unforeseen circumstances. The above-mentioned items constitute the balance scope of work required for completion of the project. In view of the same, it is respectfully requested that an extension of time be granted to enable completion of the pending works within the revised timeline.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KUSUM RESIDENCY’s extension records on MahaRERA (P51700048955), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KUSUM RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048955
- Status
- Registered and active
- Builder
- SURESH PADMAN PATIL
- Location
- Ghansoli Navi Mumbai, Thane · 400701
- Project type
- Others
- Registered on
- 24 Jan 2023
- Completion date at registration
- March 2026
- Latest completion date
- April 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KUSUM RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KUSUM RESIDENCY | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- KUSUM RESIDENCY: covers 8 floors
Latest CC order on MahaRERA: dated 24/06/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KUSUM RESIDENCY every month.
KUSUM RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: KUSUM RESIDENCY (8 floors, 21 units)
- Car parking: 22 covered
- Land: 396 sq m (about 0.1 acres) · sanctioned built-up 1,089 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KUSUM RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KUSUM RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KUSUM RESIDENCY
What is the possession date of KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KUSUM RESIDENCY in Ghansoli Navi Mumbai, Thane is 30 April 2027 — 9 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KUSUM RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KUSUM RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2027, already 9 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KUSUM RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The extension is being sought as certain internal finishing works remain pending due to unforeseen circumstances. The above-mentioned items constitute the balance scope of work required for completion of the project. In view of the same, it is respectfully requested that an extension of time be granted to enable completion of the pending works within the revised timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KUSUM RESIDENCY in Ghansoli Navi Mumbai, Thane is P51700048955.
Is KUSUM RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY is registered as P51700048955 and its status is "Registered and active".
What is the construction status of KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KUSUM RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KUSUM RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is KUSUM RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY is registered on MahaRERA as P51700048955, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KUSUM RESIDENCY's possession date changes?
The latest dates are on KUSUM RESIDENCY's MahaRERA page (P51700048955). GharKundli's Kundli Watch sends a free WhatsApp update on KUSUM RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KUSUM RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY has one building filed: KUSUM RESIDENCY with 8 floors and 21 units.
How much parking does KUSUM RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for KUSUM RESIDENCY.
How big is the land of KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY stands on 396 sq m of land (about 0.1 acres), with 1,089 sq m of sanctioned built-up area.
Where can I read reviews of KUSUM RESIDENCY?
Google Maps has reviews of KUSUM RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KUSUM RESIDENCY?
KUSUM RESIDENCY by SURESH PADMAN PATIL is in Ghansoli Navi Mumbai, Thane (pincode 400701), Maharashtra, and is registered on MahaRERA as P51700048955, per GharKundli's check of MahaRERA records.
How many homes are in KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY has 21 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was KUSUM RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KUSUM RESIDENCY was registered on MahaRERA on 24 January 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on KUSUM RESIDENCY?
No court cases are listed for KUSUM RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KUSUM RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURESH PADMAN PATIL.
Check it yourself on MahaRERA
- How to check the possession date of KUSUM RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400701
- Goldcrest Residency - Phase 2
- MAULI KRUPA
- Business Square
- Alliaance Gloria
- Leaf Mount
- VALENCIA
- ALLIAANCE LAGUNA
- ORBIS PHASE 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.