Goldcrest Residency - Phase 2

by SAVITA HOMEMAKERS LLP (Bhairaav) · Ghansoli, ThaneAlso near Kopar Khairne

Possession date of Goldcrest Residency - Phase 2: 31 March 2027, moved from 30 June 2021 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700010579, and currently active. 93 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Goldcrest Residency - Phase 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Goldcrest Residency - Phase 2 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700009982)

    Reason the builder gave MahaRERA:
    “Force Majeure as defined under RERA to mean "a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project". The Govt., looking at the COVID scen…” Read the full reason“Force Majeure as defined under RERA to mean "a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project". The Govt., looking at the COVID scenario across the country since March 2020 have already declared the current pandemic as force majeure adversely affecting development of real estate projects. The ongoing pandemic situation which resulted in reverse migration of the workers to their native places and break in supply chain of the construction material causing an adverse impact on the constr…”
  3. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51700013366)

    Reason the builder gave MahaRERA:
    “Due to space constraint the Reasons for Extension of the Project has been uploaded hereunder. You are requested to kindly go thru the same & accord your consent for Extension of the Project. We sincerely assure your good offices that the Pr…” Read the full reason“Due to space constraint the Reasons for Extension of the Project has been uploaded hereunder. You are requested to kindly go thru the same & accord your consent for Extension of the Project. We sincerely assure your good offices that the Project would be completed along with O.C & all amenities as mentioned well within Dec 2023.”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51700018457)

    Reason the builder gave MahaRERA:
    “Phase II comprise Wing A, B &C of which Wing A&B Part OC has been received on 11th July 2023 and the possession of flats handed over. Further, application for OC for Balance area is currently under process. For obtaining the final OC and co…” Read the full reason“Phase II comprise Wing A, B &C of which Wing A&B Part OC has been received on 11th July 2023 and the possession of flats handed over. Further, application for OC for Balance area is currently under process. For obtaining the final OC and completion of balance amenities in the project, it is deemed necessary to obtain RERA extension so that all approvals can be obtained during the project validity. Impediments/ exigencies faced by the Project Proponent in the past from time to time resulting delay in completion of amenities/construction mentioned hereunder: i. Inclusive Housing Scheme impose…”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700024214)

    Reason the builder gave MahaRERA:
    “Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc ha…” Read the full reason“Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenge…”
  6. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700025812)

    Reason the builder gave MahaRERA:
    “Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc ha…” Read the full reason“Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenge…”
  7. 31 March 2026

    Extended at the builder's request (MahaRERA application EA30062501867)

    Reason the builder gave MahaRERA:
    “Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. An OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc…” Read the full reason“Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. An OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained. Part OC for C Wing is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: (i) Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprec…”
  8. 31 March 2027

    Extended at the builder's request (MahaRERA application EA11052620901)

    Reason the builder gave MahaRERA:
    “Phase II comprises Wings A, B, and C. Full applications for Occupancy Certificate (OC) have been submitted for all three wings. In respect of Wings A and B, Part Occupancy Certificate has been received up to the 26th floor on 11th July 2023…” Read the full reason“Phase II comprises Wings A, B, and C. Full applications for Occupancy Certificate (OC) have been submitted for all three wings. In respect of Wings A and B, Part Occupancy Certificate has been received up to the 26th floor on 11th July 2023. In respect of Wing C, Part Occupancy Certificate has been received up to the 20th floor on 1st July 2025. In order to obtain the Final Occupancy Certificate for the entire Phase II project and to complete the balance amenities, it is just, necessary, and in the interest of justice that an extension of the project registration under RERA be granted. Exig…”

Source: Goldcrest Residency - Phase 2’s extension records on MahaRERA (P51700010579), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Goldcrest Residency - Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 93 complaints and 2 court cases, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700010579
Status
Registered and active
Builder
SAVITA HOMEMAKERS LLP
Location
Ghansoli, Thane · 400701
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
June 2021
Latest completion date
March 2027
Delay so far
69 months
Homes
316
Sold or booked
100%
Towers
3
Complaints on MahaRERA
93
Court cases listed
2
Appeals at the tribunal
33
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Goldcrest Residency - Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Harmony - Wing B100%100%96%94%
Peace - Wing C100%100%97%92%
Pride - Wing A100%100%97%93%

Commencement certificate (CC), as filed on MahaRERA

  • Harmony - Wing B: covers 28 floors
  • Peace - Wing C: covers 28 floors
  • Pride - Wing A: covers 28 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Goldcrest Residency - Phase 2 every month.

Goldcrest Residency - Phase 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Harmony - Wing B (30 floors, 91 units) · Peace - Wing C (30 floors, 134 units) · Pride - Wing A (30 floors, 91 units)
  • Land: 7,025 sq m (about 1.7 acres) · sanctioned built-up 11,138 sq m · recreational space 1,183 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Bhairaav Kothari Realtors (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 12 months); 2 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. 102 complaints on MahaRERA across 2 projects.

Read Google reviews of Goldcrest Residency - Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Goldcrest Residency - Phase 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Goldcrest Residency - Phase 2

What is the possession date of Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Goldcrest Residency - Phase 2 in Ghansoli, Thane is 31 March 2027 — 69 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Goldcrest Residency - Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Goldcrest Residency - Phase 2's builder has filed on MahaRERA, the official one, is 31 March 2027, already 69 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Goldcrest Residency - Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2's builder applied to MahaRERA to extend the completion date 7 times: to 30 June 2022, giving the reason "Force Majeure as defined under RERA to mean "a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project". The Govt., looking at the COVID scenario across the country since March 2020 have already declared the current pandemic as force majeure adversely affecting development of real estate projects. The ongoing pandemic situation which resulted in reverse migration of the workers to their native places and break in supply chain of the construction material causing an adverse impact on the constr…"; to 30 December 2023, giving the reason "Due to space constraint the Reasons for Extension of the Project has been uploaded hereunder. You are requested to kindly go thru the same & accord your consent for Extension of the Project. We sincerely assure your good offices that the Project would be completed along with O.C & all amenities as mentioned well within Dec 2023."; to 30 June 2024, giving the reason "Phase II comprise Wing A, B &C of which Wing A&B Part OC has been received on 11th July 2023 and the possession of flats handed over. Further, application for OC for Balance area is currently under process. For obtaining the final OC and completion of balance amenities in the project, it is deemed necessary to obtain RERA extension so that all approvals can be obtained during the project validity. Impediments/ exigencies faced by the Project Proponent in the past from time to time resulting delay in completion of amenities/construction mentioned hereunder: i. Inclusive Housing Scheme impose…"; to 31 December 2024, giving the reason "Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenge…"; to 30 June 2025, giving the reason "Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenge…"; to 31 March 2026, giving the reason "Phase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. An OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained. Part OC for C Wing is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: (i) Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprec…"; to 31 March 2027, giving the reason "Phase II comprises Wings A, B, and C. Full applications for Occupancy Certificate (OC) have been submitted for all three wings. In respect of Wings A and B, Part Occupancy Certificate has been received up to the 26th floor on 11th July 2023. In respect of Wing C, Part Occupancy Certificate has been received up to the 20th floor on 1st July 2025. In order to obtain the Final Occupancy Certificate for the entire Phase II project and to complete the balance amenities, it is just, necessary, and in the interest of justice that an extension of the project registration under RERA be granted. Exig…".

What is the RERA number of Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Goldcrest Residency - Phase 2 in Ghansoli, Thane is P51700010579.

Is Goldcrest Residency - Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 is registered as P51700010579 and its status is "Registered and active".

What is the construction status of Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Goldcrest Residency - Phase 2 have complaints on MahaRERA?

93 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Goldcrest Residency - Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 is registered on MahaRERA as P51700010579, its completion date has moved 69 months since registration and 93 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Goldcrest Residency - Phase 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: GOLDCREST RESIDENCY - PHASE 1 (P51700012365, possession 30 Dec 2020). Check that your agreement names the registration of your own wing.

How can I get updates if Goldcrest Residency - Phase 2's possession date changes?

The latest dates are on Goldcrest Residency - Phase 2's MahaRERA page (P51700010579). GharKundli's Kundli Watch sends a free WhatsApp update on Goldcrest Residency - Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Goldcrest Residency - Phase 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 has 3 buildings filed: Harmony - Wing B with 30 floors and 91 units; Peace - Wing C with 30 floors and 134 units; Pride - Wing A with 30 floors and 91 units.

How big is the land of Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 stands on 7,025 sq m of land (about 1.7 acres), with 11,138 sq m of sanctioned built-up area and 1,183 sq m of recreational open space.

What is the track record of Goldcrest Residency - Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhairaav Kothari Realtors (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 12 months); 2 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. 102 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Goldcrest Residency - Phase 2?

Google Maps has reviews of Goldcrest Residency - Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 93 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Goldcrest Residency - Phase 2?

Goldcrest Residency - Phase 2 by SAVITA HOMEMAKERS LLP (Bhairaav) is in Ghansoli, Thane (pincode 400701), near Kopar Khairne, Maharashtra, and is registered on MahaRERA as P51700010579, per GharKundli's check of MahaRERA records.

How many homes are in Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 has 316 homes in 3 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Goldcrest Residency - Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Goldcrest Residency - Phase 2 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Goldcrest Residency - Phase 2?

2 court cases are listed for Goldcrest Residency - Phase 2 on MahaRERA, and 33 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Goldcrest Residency - Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAVITA HOMEMAKERS LLP, the company Bhairaav files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in pincode 400701

All 79 projects in Ghansoli (400701) →

Other projects by SAVITA HOMEMAKERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.