Avdhut
by S.K. HOMES BUILDER & DEVELOPERS (JAY) · Rambaug, Kalyan, Thane 421301
What’s in the report? →Possession date of Avdhut (MahaRERA P51700048095): 30 April 2027, moved from 31 December 2025 (12 months later). It has 48 homes, 86% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048095, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700048095, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Avdhut?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Avdhut has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA18032620274)
Reason the builder gave MahaRERA: “As per attachment”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Avdhut’s extension records on MahaRERA (P51700048095), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Avdhut
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048095
- Status
- Registered and active
- Builder
- S.K. HOMES BUILDER & DEVELOPERS
- Location
- Rambaug, Kalyan, Thane · 421301
- Project type
- Others
- Registered on
- 8 Dec 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 86%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Avdhut, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AVDHUT | 100% | 100% | 75% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- AVDHUT: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avdhut every 1–2 months.
Avdhut: buildings, flats and land, as filed on MahaRERA
- Buildings: AVDHUT (8 floors, 56 units)
- Car parking: 28 covered
- Land: 1,187 sq m (about 0.3 acres) · sanctioned built-up 3,914 sq m
- Land, as filed: CTS NO 2955A/2, CTS NO 2955A/3
- Map: Get directions
The builder’s record and reviews
S K Homes Builder & Developers (a group of 6 linked companies) has 8 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months); 5 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Avdhut →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Avdhut: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Avdhut
What is the possession date of Avdhut?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avdhut in Rambaug, Kalyan, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Avdhut?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Avdhut's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Avdhut extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "As per attachment". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Avdhut?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avdhut in Rambaug, Kalyan, Thane is P51700048095.
Is Avdhut registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut is registered as P51700048095 and its status is "Registered and active".
What is the current construction status of Avdhut? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AVDHUT is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does Avdhut have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Avdhut safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut is registered on MahaRERA as P51700048095, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Avdhut?
Avdhut is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Avdhut?
For a flat in Avdhut (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Avdhut received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Avdhut uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Avdhut was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Avdhut's possession date changes?
The latest dates are on Avdhut's MahaRERA page (P51700048095). GharKundli's Kundli Watch sends a free WhatsApp update on Avdhut every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Avdhut have?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut has one building filed: AVDHUT with 8 floors and 56 units.
How much parking does Avdhut have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered car parking spaces for Avdhut.
How big is the land of Avdhut?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut stands on 1,187 sq m of land (about 0.3 acres), with 3,914 sq m of sanctioned built-up area.
What is the track record of Avdhut's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), S K Homes Builder & Developers (a group of 6 linked companies) has 8 projects on MahaRERA since 2020, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months); 5 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Avdhut?
Google Maps has reviews of Avdhut written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Avdhut?
Avdhut by S.K. HOMES BUILDER & DEVELOPERS (JAY) is in Rambaug, Kalyan, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700048095, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 2955A/2, CTS NO 2955A/3. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Avdhut, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut has 48 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.
When was Avdhut registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avdhut was registered on MahaRERA on 8 December 2022. GharKundli did not find a title report on the land on file there.
Does Avdhut have any legal issues or court cases?
No court cases are listed for Avdhut on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Avdhut?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S.K. HOMES BUILDER & DEVELOPERS, the company JAY files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Avdhut
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Other projects by S.K. HOMES BUILDER & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.