by VIJAY PRABHAKAR PATIL · Titwala East, Thane 421605Also near Manda

What’s in the report? →

Possession date of Ganpati Prasanna (MahaRERA P51700048517): 30 April 2027, moved from 31 December 2025 (12 months later). It has 42 homes, 76% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700048517, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700048517, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ganpati Prasanna?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ganpati Prasanna has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA14112518331)

    Reason the builder gave MahaRERA:
    “Dear Sir/Madam, I, Vijay Prabhakar Patil , ("Prop of Tushar Enterprises"), and I am writing you with regards to our application for extension of time till 31ST December, 2026; 1. As you are aware that the company is engaged in the construct…” Read the full reason“Dear Sir/Madam, I, Vijay Prabhakar Patil , ("Prop of Tushar Enterprises"), and I am writing you with regards to our application for extension of time till 31ST December, 2026; 1. As you are aware that the company is engaged in the constructing a real estate project at Titwala Tal-Kalyan, Maharashtra on its plot of land comprising of 1 Building Wings having 7 floors.” [hereinafter collectively referred to as "the Proiect"). 2. I say that I obtained the Rera registration number P51700048517 for Project GANAPATI PRASANNA at Titwala Tal-Kalyan, Thane. 3. I say that my project is 70% complete as…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ganpati Prasanna’s extension records on MahaRERA (P51700048517), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ganpati Prasanna

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700048517
Status
Registered and active
Builder
VIJAY PRABHAKAR PATIL
Location
Titwala East, Thane · 421605
Project type
Others
Registered on
3 Jan 2023
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
76%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ganpati Prasanna, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GANPATI PRASANNA100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • GANPATI PRASANNA: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ganpati Prasanna every 1–2 months.

Ganpati Prasanna: buildings, flats and land, as filed on MahaRERA

  • Buildings: GANPATI PRASANNA (8 floors, 45 units)
  • Car parking: 21 covered
  • Land: 800 sq m (about 0.2 acres) · sanctioned built-up 2,458 sq m
  • Land, as filed: SURVEY NO 214 HISSA NO 7B AND 7C
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Ganpati Prasanna →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ganpati Prasanna: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ganpati Prasanna

What is the possession date of Ganpati Prasanna?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ganpati Prasanna in Titwala East, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ganpati Prasanna?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ganpati Prasanna's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ganpati Prasanna extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Dear Sir/Madam, I, Vijay Prabhakar Patil , ("Prop of Tushar Enterprises"), and I am writing you with regards to our application for extension of time till 31ST December, 2026; 1. As you are aware that the company is engaged in the constructing a real estate project at Titwala Tal-Kalyan, Maharashtra on its plot of land comprising of 1 Building Wings having 7 floors.” [hereinafter collectively referred to as "the Proiect"). 2. I say that I obtained the Rera registration number P51700048517 for Project GANAPATI PRASANNA at Titwala Tal-Kalyan, Thane. 3. I say that my project is 70% complete as…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ganpati Prasanna?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ganpati Prasanna in Titwala East, Thane is P51700048517.

Is Ganpati Prasanna registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna is registered as P51700048517 and its status is "Registered and active".

What is the current construction status of Ganpati Prasanna? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GANPATI PRASANNA is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Ganpati Prasanna have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ganpati Prasanna safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna is registered on MahaRERA as P51700048517, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ganpati Prasanna?

Ganpati Prasanna is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ganpati Prasanna?

For a flat in Ganpati Prasanna (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ganpati Prasanna received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ganpati Prasanna uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ganpati Prasanna was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ganpati Prasanna's possession date changes?

The latest dates are on Ganpati Prasanna's MahaRERA page (P51700048517). GharKundli's Kundli Watch sends a free WhatsApp update on Ganpati Prasanna every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ganpati Prasanna have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna has one building filed: GANPATI PRASANNA with 8 floors and 45 units.

How much parking does Ganpati Prasanna have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 21 covered car parking spaces for Ganpati Prasanna.

How big is the land of Ganpati Prasanna?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna stands on 800 sq m of land (about 0.2 acres), with 2,458 sq m of sanctioned built-up area.

What are the reviews of Ganpati Prasanna?

Google Maps has reviews of Ganpati Prasanna written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ganpati Prasanna?

Ganpati Prasanna by VIJAY PRABHAKAR PATIL is in Titwala East, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700048517, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 214 HISSA NO 7B AND 7C. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Ganpati Prasanna, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna has 42 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.

When was Ganpati Prasanna registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganpati Prasanna was registered on MahaRERA on 3 January 2023. GharKundli did not find a title report on the land on file there.

Does Ganpati Prasanna have any legal issues or court cases?

No court cases are listed for Ganpati Prasanna on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ganpati Prasanna?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIJAY PRABHAKAR PATIL.

All projects with possession due in 2027 in Thane →

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.