What’s in the report? →Possession date of Panvelkar Bhoomi Building No 5,6,7,8,9 (MahaRERA P51700050061): 30 April 2028, moved from 31 December 2025 (24 months later). It has 160 homes, 19% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050061, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700050061, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Panvelkar Bhoomi Building No 5,6,7,8,9?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Panvelkar Bhoomi Building No 5,6,7,8,9 has moved
31 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA25112518434)
Reason the builder gave MahaRERA:
“We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700050061.The date of completion of project Panvelkar Bhoomi (Building No. 5,6,7,8,9)" developed by M/s Panvelkar Bhooml currently is 31st December, 20…” Read the full reason
“We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700050061.The date of completion of project Panvelkar Bhoomi (Building No. 5,6,7,8,9)" developed by M/s Panvelkar Bhooml currently is 31st December, 2025. We would like to bring to your notice that the project comprises of five buildings namely Building No. 5,6, 7,8 & 9. Out of these buildings, only two buildings work has been started due to sluggish market demand and bookings were also taken in those two buildings only. For other buildings i.e. Building No. 6, 7, and 8, no work has been started & no bo…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Panvelkar Bhoomi Building No 5,6,7,8,9’s extension records on MahaRERA (P51700050061), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Panvelkar Bhoomi Building No 5,6,7,8,9
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050061
- Status
- Registered and active
- Builder
- PANVELKAR BHOOMI
- Location
- Taluka Ambernath, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 13 Mar 2023
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 160
- Sold or booked
- 19%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Panvelkar Bhoomi Building No 5,6,7,8,9, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 5 BLOSSOM | 100% | 50% | 12% | 0% |
| BUILDING NO 6 CLOVER | 0% | 0% | 0% | 0% |
| BUILDING NO 7 DAFFODIL | 0% | 0% | 0% | 0% |
| BUILDING NO 8 FLORA | 0% | 0% | 0% | 0% |
| BUILDING NO 9 LOTUS | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 5 BLOSSOM: covers 7 floors
- BUILDING NO 6 CLOVER: covers 7 floors
- BUILDING NO 7 DAFFODIL: covers 7 floors
- BUILDING NO 8 FLORA: covers 7 floors
- BUILDING NO 9 LOTUS: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Panvelkar Bhoomi Building No 5,6,7,8,9 every 1–2 months.
Panvelkar Bhoomi Building No 5,6,7,8,9: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 5 BLOSSOM (7 floors, 32 units) · BUILDING NO 6 CLOVER (7 floors, 32 units) · BUILDING NO 7 DAFFODIL (7 floors, 32 units) · BUILDING NO 8 FLORA (7 floors, 32 units) · BUILDING NO 9 LOTUS (7 floors, 32 units)
- Land: 4,751 sq m (about 1.2 acres) · sanctioned built-up 4,751 sq m
- Land, as filed: S NO 27 H NO 3/7,S NO 32/1
- Map: Get directions
The builder’s record and reviews
Panvelkar Infrastructures (a group of 8 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 12 finished, 9 within the promised date and 3 needed more time (typically 12 months); 6 still being built, 3 past the promised date (typically 34 months late); 7 lapsed. 7 complaints on MahaRERA across 4 projects.
Read Google reviews of Panvelkar Bhoomi Building No 5,6,7,8,9 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Panvelkar Bhoomi Building No 5,6,7,8,9: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Panvelkar Bhoomi Building No 5,6,7,8,9
What is the possession date of Panvelkar Bhoomi Building No 5,6,7,8,9?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Panvelkar Bhoomi Building No 5,6,7,8,9 in Taluka Ambernath, Thane is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Panvelkar Bhoomi Building No 5,6,7,8,9?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Panvelkar Bhoomi Building No 5,6,7,8,9's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Panvelkar Bhoomi Building No 5,6,7,8,9 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700050061.The date of completion of project Panvelkar Bhoomi (Building No. 5,6,7,8,9)" developed by M/s Panvelkar Bhooml currently is 31st December, 2025. We would like to bring to your notice that the project comprises of five buildings namely Building No. 5,6, 7,8 & 9. Out of these buildings, only two buildings work has been started due to sluggish market demand and bookings were also taken in those two buildings only. For other buildings i.e. Building No. 6, 7, and 8, no work has been started & no bo…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Panvelkar Bhoomi Building No 5,6,7,8,9?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Panvelkar Bhoomi Building No 5,6,7,8,9 in Taluka Ambernath, Thane is P51700050061.
Is Panvelkar Bhoomi Building No 5,6,7,8,9 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 is registered as P51700050061 and its status is "Registered and active".
What is the current construction status of Panvelkar Bhoomi Building No 5,6,7,8,9? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Panvelkar Bhoomi Building No 5,6,7,8,9 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Panvelkar Bhoomi Building No 5,6,7,8,9 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 is registered on MahaRERA as P51700050061, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Panvelkar Bhoomi Building No 5,6,7,8,9?
Panvelkar Bhoomi Building No 5,6,7,8,9 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Panvelkar Bhoomi Building No 5,6,7,8,9?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Panvelkar Bhoomi Building No 5,6,7,8,9: gharkundli.com/tools/property-cost-calculator
Has Panvelkar Bhoomi Building No 5,6,7,8,9 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Panvelkar Bhoomi Building No 5,6,7,8,9 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Panvelkar Bhoomi Building No 5,6,7,8,9 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Panvelkar Bhoomi Building No 5,6,7,8,9's possession date changes?
The latest dates are on Panvelkar Bhoomi Building No 5,6,7,8,9's MahaRERA page (P51700050061). GharKundli's Kundli Watch sends a free WhatsApp update on Panvelkar Bhoomi Building No 5,6,7,8,9 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Panvelkar Bhoomi Building No 5,6,7,8,9 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 has 5 buildings filed: BUILDING NO 5 BLOSSOM with 7 floors and 32 units; BUILDING NO 6 CLOVER with 7 floors and 32 units; BUILDING NO 7 DAFFODIL with 7 floors and 32 units; BUILDING NO 8 FLORA with 7 floors and 32 units; BUILDING NO 9 LOTUS with 7 floors and 32 units.
How big is the land of Panvelkar Bhoomi Building No 5,6,7,8,9?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 stands on 4,751 sq m of land (about 1.2 acres), with 4,751 sq m of sanctioned built-up area.
What is the track record of Panvelkar Bhoomi Building No 5,6,7,8,9's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Infrastructures (a group of 8 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 12 finished, 9 within the promised date and 3 needed more time (typically 12 months); 6 still being built, 3 past the promised date (typically 34 months late); 7 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Panvelkar Bhoomi Building No 5,6,7,8,9?
Google Maps has reviews of Panvelkar Bhoomi Building No 5,6,7,8,9 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Panvelkar Bhoomi Building No 5,6,7,8,9?
Panvelkar Bhoomi Building No 5,6,7,8,9 by PANVELKAR BHOOMI is in Taluka Ambernath, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700050061, per GharKundli's check of MahaRERA records. Its land is filed as S NO 27 H NO 3/7,S NO 32/1. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Panvelkar Bhoomi Building No 5,6,7,8,9, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 has 160 homes in 5 towers registered on MahaRERA, and 19% of them are sold or booked.
When was Panvelkar Bhoomi Building No 5,6,7,8,9 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Bhoomi Building No 5,6,7,8,9 was registered on MahaRERA on 13 March 2023. GharKundli did not find a title report on the land on file there.
Does Panvelkar Bhoomi Building No 5,6,7,8,9 have any legal issues or court cases?
No court cases are listed for Panvelkar Bhoomi Building No 5,6,7,8,9 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Panvelkar Bhoomi Building No 5,6,7,8,9?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PANVELKAR BHOOMI.
Check it yourself on MahaRERA
- How to check the possession date of Panvelkar Bhoomi Building No 5,6,7,8,9
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Ambarnath
- Sarveshwar Co-op HSG Soc
- Nature Vista Building - 1
- Midtown B and C Wing
- Mery Villa CHSL
- Sai Universe
- Dattatray Residency
- Mahadev Heights
- Chadha Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.