Pradhan Mantri Awas Yojana - Urban
by KULGAON BADLAPUR MUNICIPAL COUNCIL · Badlapur East, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of Pradhan Mantri Awas Yojana - Urban (MahaRERA P51700048693): 30 April 2028, moved from 31 December 2024 (36 months later). It has 2,298 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048693, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700048693, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Pradhan Mantri Awas Yojana - Urban?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pradhan Mantri Awas Yojana - Urban has moved
31 December 2024
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51700028444)
Reason the builder gave MahaRERA:
“1. Project is 15 % completed 2. There are no sold units in the project; hence, the consent of allottees is not required for the extension. 3. Revised Form B uploaded in other tab No.1 and in main Application. 4 PERT Chart for the remaining…” Read the full reason
“1. Project is 15 % completed 2. There are no sold units in the project; hence, the consent of allottees is not required for the extension. 3. Revised Form B uploaded in other tab No.1 and in main Application. 4 PERT Chart for the remaining completion work is uploaded in Other Tab No. 2 and also in Other Technical Tab of Main Application. 5. QPR till date are updated. 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 3 6. Due to unavoidable circumstances project has been delay and it will be completed by 31/12/2027”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Pradhan Mantri Awas Yojana - Urban’s extension records on MahaRERA (P51700048693), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pradhan Mantri Awas Yojana - Urban
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048693
- Status
- Registered and active
- Builder
- KULGAON BADLAPUR MUNICIPAL COUNCIL
- Location
- Badlapur East, Thane · 421503
- Project type
- Others
- Registered on
- 12 Jan 2023
- Completion date at registration
- December 2024
- Latest completion date
- April 2028
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 2,298
- Sold or booked
- 0%
- Towers
- 8
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Pradhan Mantri Awas Yojana - Urban, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| T1 - TOWER 1 | 0% | 0% | 0% | 0% |
| T2 TOWER 2 | 0% | 0% | 0% | 0% |
| T3 TOWER 3 | 100% | 7% | 0% | 0% |
| T4 TOWER 4 | 100% | 55% | 18% | 0% |
| T5 TOWER 5 | 100% | 8% | 0% | 0% |
| T6 TOWER 6 | 100% | 0% | 0% | 0% |
| T7 TOWER 7 | 0% | 0% | 0% | 0% |
| T8 TOWER 8 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- T1 - TOWER 1: covers 14 floors
- T2 TOWER 2: covers 14 floors
- T3 TOWER 3: covers 14 floors
- T4 TOWER 4: covers 14 floors
- T5 TOWER 5: covers 14 floors
- T6 TOWER 6: covers 14 floors
- T7 TOWER 7: covers 14 floors
- T8 TOWER 8: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pradhan Mantri Awas Yojana - Urban every 1–2 months.
Pradhan Mantri Awas Yojana - Urban: buildings, flats and land, as filed on MahaRERA
- Buildings: T1 - TOWER 1 (14 floors, 309 units) · T2 TOWER 2 (14 floors, 309 units) · T3 TOWER 3 (14 floors, 312 units) · T4 TOWER 4 (14 floors, 311 units) · T5 TOWER 5 (14 floors, 312 units) · T6 TOWER 6 (14 floors, 311 units) · T7 TOWER 7 (14 floors, 243 units) · T8 TOWER 8 (14 floors, 245 units)
- Land: 51,310 sq m (about 12.7 acres) · sanctioned built-up 94,251 sq m · recreational space 5,494 sq m
- Land, as filed: PLOT NO 98/A, 98/B AND 99
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Pradhan Mantri Awas Yojana - Urban →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pradhan Mantri Awas Yojana - Urban: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pradhan Mantri Awas Yojana - Urban
What is the possession date of Pradhan Mantri Awas Yojana - Urban?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pradhan Mantri Awas Yojana - Urban in Badlapur East, Thane is 30 April 2028 — 36 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Pradhan Mantri Awas Yojana - Urban?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pradhan Mantri Awas Yojana - Urban's builder has filed on MahaRERA, the official one, is 30 April 2028, already 36 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pradhan Mantri Awas Yojana - Urban extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "1. Project is 15 % completed 2. There are no sold units in the project; hence, the consent of allottees is not required for the extension. 3. Revised Form B uploaded in other tab No.1 and in main Application. 4 PERT Chart for the remaining completion work is uploaded in Other Tab No. 2 and also in Other Technical Tab of Main Application. 5. QPR till date are updated. 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 3 6. Due to unavoidable circumstances project has been delay and it will be completed by 31/12/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Pradhan Mantri Awas Yojana - Urban?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pradhan Mantri Awas Yojana - Urban in Badlapur East, Thane is P51700048693.
Is Pradhan Mantri Awas Yojana - Urban registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban is registered as P51700048693 and its status is "Registered and active".
What is the current construction status of Pradhan Mantri Awas Yojana - Urban? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 55% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does Pradhan Mantri Awas Yojana - Urban have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Pradhan Mantri Awas Yojana - Urban safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban is registered on MahaRERA as P51700048693, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pradhan Mantri Awas Yojana - Urban?
Pradhan Mantri Awas Yojana - Urban is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pradhan Mantri Awas Yojana - Urban?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Pradhan Mantri Awas Yojana - Urban: gharkundli.com/tools/property-cost-calculator
Has Pradhan Mantri Awas Yojana - Urban received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Pradhan Mantri Awas Yojana - Urban uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pradhan Mantri Awas Yojana - Urban was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Pradhan Mantri Awas Yojana - Urban's possession date changes?
The latest dates are on Pradhan Mantri Awas Yojana - Urban's MahaRERA page (P51700048693). GharKundli's Kundli Watch sends a free WhatsApp update on Pradhan Mantri Awas Yojana - Urban every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pradhan Mantri Awas Yojana - Urban have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban has 8 buildings filed: T1 - TOWER 1 with 14 floors and 309 units; T2 TOWER 2 with 14 floors and 309 units; T3 TOWER 3 with 14 floors and 312 units; T4 TOWER 4 with 14 floors and 311 units; T5 TOWER 5 with 14 floors and 312 units; T6 TOWER 6 with 14 floors and 311 units; and 2 more.
How big is the land of Pradhan Mantri Awas Yojana - Urban?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban stands on 51,310 sq m of land (about 12.7 acres), with 94,251 sq m of sanctioned built-up area and 5,494 sq m of recreational open space.
What are the reviews of Pradhan Mantri Awas Yojana - Urban?
Google Maps has reviews of Pradhan Mantri Awas Yojana - Urban written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pradhan Mantri Awas Yojana - Urban?
Pradhan Mantri Awas Yojana - Urban by KULGAON BADLAPUR MUNICIPAL COUNCIL is in Badlapur East, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700048693, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 98/A, 98/B AND 99. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Pradhan Mantri Awas Yojana - Urban, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban has 2,298 homes in 8 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Pradhan Mantri Awas Yojana - Urban registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pradhan Mantri Awas Yojana - Urban was registered on MahaRERA on 12 January 2023. GharKundli did not find a title report on the land on file there.
Does Pradhan Mantri Awas Yojana - Urban have any legal issues or court cases?
No court cases are listed for Pradhan Mantri Awas Yojana - Urban on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Pradhan Mantri Awas Yojana - Urban?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KULGAON BADLAPUR MUNICIPAL COUNCIL.
Check it yourself on MahaRERA
- How to check the possession date of Pradhan Mantri Awas Yojana - Urban
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Prabhu Darshan Co-operative Housing Society Limited
- Dattatray Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.