Faisal Balaji Heights
by Faisal Constructions · Ambernath, Thane 421501Registered on MahaRERA as “Balaji Heights”
What’s in the report? →Possession date of Faisal Balaji Heights (MahaRERA P51700048885): 31 December 2025, moved from 30 June 2025 (6 months later), and it has already passed. It has 60 homes, 85% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048885. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700048885, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Faisal Balaji Heights?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Faisal Balaji Heights has moved
30 June 2025
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EA30062501880)
Reason the builder gave MahaRERA:
“While registering we had declared the date of completion of this project as 30/06/2025. We wish to inform you that due to unavailability of PWD NOC for Lift, we are not able to apply for Occupation Certificate and it may take us 45 to 60 da…” Read the full reason
“While registering we had declared the date of completion of this project as 30/06/2025. We wish to inform you that due to unavailability of PWD NOC for Lift, we are not able to apply for Occupation Certificate and it may take us 45 to 60 days for obtaining the PWD NOC and for Occupation Certificate from Ambernath Municipal Council. Therefore, we humbly request your goodself to allow us to extend the date of completion of the said Project by 6 months and permit us to revise the completion date from the current 30/06/2025 to 31/12/2025. We submit here that we shall take all steps necessary to…”
Source: Faisal Balaji Heights’s extension records on MahaRERA (P51700048885), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Faisal Balaji Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048885
- Status
- Lapsed (registration period ended)
- Builder
- Faisal Constructions
- Location
- Ambernath, Thane · 421501
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2023
- Completion date at registration
- June 2025
- Latest completion date
- December 2025
- Delay so far
- 6 months
- Homes
- 60
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Faisal Balaji Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Balaji Heights | 100% | 100% | 95% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Faisal Balaji Heights every 1–2 months.
Faisal Balaji Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Balaji Heights (7 floors)
- Land: 1,339 sq m (about 0.3 acres) · sanctioned built-up 3,995 sq m
- Land, as filed: Survey No 165, Hissa No 2, CTS No.47
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Faisal Balaji Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Faisal Balaji Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Faisal Balaji Heights
What is the possession date of Faisal Balaji Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Faisal Balaji Heights in Ambernath, Thane is 31 December 2025 — 6 months later than 30 June 2025, the date given at registration. That date has already passed.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Faisal Balaji Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Faisal Balaji Heights's builder has filed on MahaRERA, the official one, is 31 December 2025, already 6 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Faisal Balaji Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "While registering we had declared the date of completion of this project as 30/06/2025. We wish to inform you that due to unavailability of PWD NOC for Lift, we are not able to apply for Occupation Certificate and it may take us 45 to 60 days for obtaining the PWD NOC and for Occupation Certificate from Ambernath Municipal Council. Therefore, we humbly request your goodself to allow us to extend the date of completion of the said Project by 6 months and permit us to revise the completion date from the current 30/06/2025 to 31/12/2025. We submit here that we shall take all steps necessary to…".
What is the RERA number of Faisal Balaji Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Faisal Balaji Heights in Ambernath, Thane is P51700048885.
Is Faisal Balaji Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights is registered as P51700048885 and its status is "Lapsed (registration period ended)".
What is the current construction status of Faisal Balaji Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Balaji Heights is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Faisal Balaji Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Faisal Balaji Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights is registered on MahaRERA as P51700048885, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Faisal Balaji Heights?
Faisal Balaji Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Faisal Balaji Heights?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Faisal Balaji Heights: gharkundli.com/tools/property-cost-calculator
Has Faisal Balaji Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Faisal Balaji Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Faisal Balaji Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Faisal Balaji Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Faisal Balaji Heights's possession date changes?
The latest dates are on Faisal Balaji Heights's MahaRERA page (P51700048885). GharKundli's Kundli Watch sends a free WhatsApp update on Faisal Balaji Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Faisal Balaji Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights has one building filed: Balaji Heights with 7 floors.
How big is the land of Faisal Balaji Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights stands on 1,339 sq m of land (about 0.3 acres), with 3,995 sq m of sanctioned built-up area.
What are the reviews of Faisal Balaji Heights?
Google Maps has reviews of Faisal Balaji Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Faisal Balaji Heights?
Faisal Balaji Heights by Faisal Constructions is in Ambernath, Thane, pincode 421501, Maharashtra, and is registered on MahaRERA as P51700048885, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 165, Hissa No 2, CTS No.47. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Faisal Balaji Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights has 60 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was Faisal Balaji Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Faisal Balaji Heights was registered on MahaRERA on 24 January 2023. GharKundli did not find a title report on the land on file there.
Does Faisal Balaji Heights have any legal issues or court cases?
No court cases are listed for Faisal Balaji Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Faisal Balaji Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Faisal Constructions, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Faisal Balaji Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ambernath (421501)
- Paritosh Co Operative Housing Society Limited
- New Neelgagan CHS
- Next Crown Landmark
- Mahadev Heights
- Chadha Residency
- Panvelkar Daffodils-Plot No. 11,12,13
- Neelkanth Royale Palms - F Wing Phase II
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
Other projects by Faisal Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.