Shreyas Residency
by KASHINATH KALU BHOIR · Sarovar Nagar, Thane 421202Also near Navagaon, Ganesh Nagar, Dombivli West
What’s in the report? →Possession date of Shreyas Residency (MahaRERA P51700050871): 30 June 2027, moved from 31 March 2026 (15 months later). It has 53 homes, 21% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050871, and currently active.
Source: MahaRERA website — records for P51700050871, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shreyas Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shreyas Residency has moved
31 March 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA31032620500)
Reason the builder gave MahaRERA:
“a) Initially, we obtained commencement certificate and sanction plan from KDMC dated 18/04/2022 for Ground Floor + Nine Floors. Now, we are planning to revise to Ground Floor + ______ Floors. b) The area is which project is to be constructe…” Read the full reason
“a) Initially, we obtained commencement certificate and sanction plan from KDMC dated 18/04/2022 for Ground Floor + Nine Floors. Now, we are planning to revise to Ground Floor + ______ Floors. b) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. c) In addition to above, there was severe slow-down in Housing Construction Sector due to which we got delayed to achieve sale/booking target of flats in spite of our best efforts and the project continued with our own funds till th…”
Source: Shreyas Residency’s extension records on MahaRERA (P51700050871), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreyas Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050871
- Status
- Registered and active
- Builder
- KASHINATH KALU BHOIR
- Location
- Sarovar Nagar, Thane · 421202
- Project type
- Residential / Group Housing
- Registered on
- 15 May 2023
- Completion date at registration
- March 2026
- Latest completion date
- June 2027
- Delay so far
- 15 months
- Homes
- 53
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shreyas Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREYAS RESIDENCY | 100% | 100% | 91% | 65% |
Commencement certificate (CC), as filed on MahaRERA
- SHREYAS RESIDENCY: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreyas Residency every 1–2 months.
Shreyas Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREYAS RESIDENCY (10 floors, 53 units)
- Land: 800 sq m (about 0.2 acres) · sanctioned built-up 2,704 sq m
- Land, as filed: S NO 60 H NO 21A & 21B
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreyas Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreyas Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shreyas Residency
What is the possession date of Shreyas Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreyas Residency in Sarovar Nagar, Thane is 30 June 2027 — 15 months later than 31 March 2026, the date given at registration.
The date has already moved 15 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shreyas Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreyas Residency's builder has filed on MahaRERA, the official one, is 30 June 2027, already 15 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shreyas Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "a) Initially, we obtained commencement certificate and sanction plan from KDMC dated 18/04/2022 for Ground Floor + Nine Floors. Now, we are planning to revise to Ground Floor + ______ Floors. b) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. c) In addition to above, there was severe slow-down in Housing Construction Sector due to which we got delayed to achieve sale/booking target of flats in spite of our best efforts and the project continued with our own funds till th…".
What is the RERA number of Shreyas Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreyas Residency in Sarovar Nagar, Thane is P51700050871.
Is Shreyas Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency is registered as P51700050871 and its status is "Registered and active".
What is the current construction status of Shreyas Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREYAS RESIDENCY is 100% done and internal work 91%. GharKundli's full report compares construction progress with the deadline.
Does Shreyas Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shreyas Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency is registered on MahaRERA as P51700050871, its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shreyas Residency?
Shreyas Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shreyas Residency?
For a flat in Shreyas Residency (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shreyas Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shreyas Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreyas Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shreyas Residency's possession date changes?
The latest dates are on Shreyas Residency's MahaRERA page (P51700050871). GharKundli's Kundli Watch sends a free WhatsApp update on Shreyas Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreyas Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency has one building filed: SHREYAS RESIDENCY with 10 floors and 53 units.
How big is the land of Shreyas Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency stands on 800 sq m of land (about 0.2 acres), with 2,704 sq m of sanctioned built-up area.
What are the reviews of Shreyas Residency?
Google Maps has reviews of Shreyas Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shreyas Residency?
Shreyas Residency by KASHINATH KALU BHOIR is in Sarovar Nagar, Thane, pincode 421202 (near Navagaon, Ganesh Nagar, Dombivli West), Maharashtra, and is registered on MahaRERA as P51700050871, per GharKundli's check of MahaRERA records. Its land is filed as S NO 60 H NO 21A & 21B. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).
How many flats are in Shreyas Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency has 53 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was Shreyas Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreyas Residency was registered on MahaRERA on 15 May 2023. GharKundli did not find a title report on the land on file there.
Does Shreyas Residency have any legal issues or court cases?
No court cases are listed for Shreyas Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shreyas Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KASHINATH KALU BHOIR.
Check it yourself on MahaRERA
- How to check the possession date of Shreyas Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.