Gajanan Ramdarshan Residency
by SHREE SAI GAJANAN DEVELOPERS · Titwala, Thane 421605Also near MandaRegistered on MahaRERA as “RAMDARSHAN RESIDENCY”
What’s in the report? →Possession date of Gajanan Ramdarshan Residency (MahaRERA P51700050529): 1 June 2027, moved from 2 February 2026 (12 months later). It has 35 homes, 51% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050529, and currently active. Its completion date has moved from February 2026 to June 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700050529, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Gajanan Ramdarshan Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gajanan Ramdarshan Residency has moved
2 February 2026
Completion date given when the project was registered
1 February 2027
Extended at the builder's request (MahaRERA application EA02022619680)
Reason the builder gave MahaRERA:
“Due to financial constraints, supply chain disruptions and same was effecting booking since last 8-9 months which were beyond our reasonable control. Despite these challenges, we assure the Authority that all possible efforts are being made…” Read the full reason
“Due to financial constraints, supply chain disruptions and same was effecting booking since last 8-9 months which were beyond our reasonable control. Despite these challenges, we assure the Authority that all possible efforts are being made to expedite construction and complete the project within the extended period sought”1 June 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Gajanan Ramdarshan Residency’s extension records on MahaRERA (P51700050529), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gajanan Ramdarshan Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050529
- Status
- Registered and active
- Builder
- SHREE SAI GAJANAN DEVELOPERS
- Location
- Titwala, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 21 Apr 2023
- Completion date at registration
- February 2026
- Latest completion date
- June 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 35
- Sold or booked
- 51%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Gajanan Ramdarshan Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAMDARSHAN RESIDENCY | 100% | 100% | 85% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- RAMDARSHAN RESIDENCY: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gajanan Ramdarshan Residency every 1–2 months.
Gajanan Ramdarshan Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: RAMDARSHAN RESIDENCY (8 floors, 43 units)
- Car parking: 20 open
- Land: 520 sq m (about 0.1 acres) · sanctioned built-up 2,139 sq m
- Land, as filed: SURVEY NO. 5, HISSA NO. 3/A, PLOT NO.2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Aaradhana Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 28 months late). No complaints on MahaRERA.
Read Google reviews of Gajanan Ramdarshan Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gajanan Ramdarshan Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gajanan Ramdarshan Residency
What is the possession date of Gajanan Ramdarshan Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gajanan Ramdarshan Residency in Titwala, Thane is 1 June 2027 — 12 months later than 2 February 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gajanan Ramdarshan Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gajanan Ramdarshan Residency's builder has filed on MahaRERA, the official one, is 1 June 2027, already 12 months later than the 2 February 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gajanan Ramdarshan Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency's builder applied to MahaRERA to extend the completion date once: to 1 February 2027, giving the reason "Due to financial constraints, supply chain disruptions and same was effecting booking since last 8-9 months which were beyond our reasonable control. Despite these challenges, we assure the Authority that all possible efforts are being made to expedite construction and complete the project within the extended period sought". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Gajanan Ramdarshan Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gajanan Ramdarshan Residency in Titwala, Thane is P51700050529.
Is Gajanan Ramdarshan Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency is registered as P51700050529 and its status is "Registered and active".
What is the current construction status of Gajanan Ramdarshan Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAMDARSHAN RESIDENCY is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does Gajanan Ramdarshan Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Gajanan Ramdarshan Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency is registered on MahaRERA as P51700050529, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gajanan Ramdarshan Residency?
Gajanan Ramdarshan Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gajanan Ramdarshan Residency?
For a flat in Gajanan Ramdarshan Residency (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Gajanan Ramdarshan Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency is still under construction, with 1 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Gajanan Ramdarshan Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gajanan Ramdarshan Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gajanan Ramdarshan Residency's possession date changes?
The latest dates are on Gajanan Ramdarshan Residency's MahaRERA page (P51700050529). GharKundli's Kundli Watch sends a free WhatsApp update on Gajanan Ramdarshan Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gajanan Ramdarshan Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency has one building filed: RAMDARSHAN RESIDENCY with 8 floors and 43 units.
How much parking does Gajanan Ramdarshan Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 open car parking spaces for Gajanan Ramdarshan Residency.
How big is the land of Gajanan Ramdarshan Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency stands on 520 sq m of land (about 0.1 acres), with 2,139 sq m of sanctioned built-up area.
What is the track record of Gajanan Ramdarshan Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aaradhana Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 28 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Gajanan Ramdarshan Residency?
Google Maps has reviews of Gajanan Ramdarshan Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gajanan Ramdarshan Residency?
Gajanan Ramdarshan Residency by SHREE SAI GAJANAN DEVELOPERS is in Titwala, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700050529, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 5, HISSA NO. 3/A, PLOT NO.2. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in Gajanan Ramdarshan Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency has 35 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.
When was Gajanan Ramdarshan Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Ramdarshan Residency was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Does Gajanan Ramdarshan Residency have any legal issues or court cases?
No court cases are listed for Gajanan Ramdarshan Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Gajanan Ramdarshan Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SAI GAJANAN DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Gajanan Ramdarshan Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Titwala (421605)
- Charms City Phase II
- Ganpati Heights
- Marathe Tower
- Pitambare Tower
- Shree Gajanan Plaza
- Sai Vrindavan
- Mangalmurti Heights
- Sarnobat Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.