by KRISHNA BUILDCON · Badlapur East, Thane 421503Also near Kulgaon

What’s in the report? →

Possession: Krishna Darshan (MahaRERA P51700049959) is marked completed on MahaRERA. It has 34 homes, 71% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049959. Status: Completed. Its completion date has moved from December 2025 to October 2026: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700049959, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Krishna Darshan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Krishna Darshan has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA24012619574)

    Reason the builder gave MahaRERA: “DELAY IN CONSTRUCTION WORKS AND APPLIED FOR EXTENSION FOR 6 MONTHS ONLY”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Krishna Darshan’s extension records on MahaRERA (P51700049959), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Krishna Darshan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049959
Status
Completed
Builder
KRISHNA BUILDCON
Location
Badlapur East, Thane · 421503
Project type
Residential / Group Housing
Registered on
6 Mar 2023
Completion date at registration
December 2025
Latest completion date
October 2026
Delay so far
6 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
71%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Krishna Darshan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KRISHNA DARSHAN100%100%100%60%

Commencement certificate (CC), as filed on MahaRERA

  • KRISHNA DARSHAN: covers 7 floors

Latest CC order on MahaRERA: dated 22/08/2022.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krishna Darshan every 1–2 months.

Krishna Darshan: buildings, flats and land, as filed on MahaRERA

  • Buildings: KRISHNA DARSHAN (8 floors, 34 units)
  • Car parking: 12 covered, 12 open
  • Land: 517 sq m (about 0.1 acres) · sanctioned built-up 1,671 sq m
  • Land, as filed: SURVEY NO. 148, HISSA NO. 20/A, PLOT NO. 7 & SURVEY NO. 148, HISSA NO. 20/A, PLOT NO. 8
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Krishna Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krishna Darshan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Krishna Darshan

What is the possession date of Krishna Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krishna Darshan in Badlapur East, Thane is 30 October 2026 — 6 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Krishna Darshan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krishna Darshan's builder has filed on MahaRERA, the official one, is 30 October 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Krishna Darshan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "DELAY IN CONSTRUCTION WORKS AND APPLIED FOR EXTENSION FOR 6 MONTHS ONLY". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Krishna Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krishna Darshan in Badlapur East, Thane is P51700049959.

Is Krishna Darshan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan is registered as P51700049959 and its status is "Completed".

What is the current construction status of Krishna Darshan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan's status on MahaRERA is "Completed". As filed by the builder, slab work on KRISHNA DARSHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Krishna Darshan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Krishna Darshan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan is registered on MahaRERA as P51700049959, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Krishna Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Krishna Darshan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Krishna Darshan: gharkundli.com/tools/property-cost-calculator

Has Krishna Darshan received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Krishna Darshan completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan is marked completed on MahaRERA, and the completion date filed there is 30 October 2026. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Krishna Darshan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Krishna Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Krishna Darshan's possession date changes?

The latest dates are on Krishna Darshan's MahaRERA page (P51700049959). GharKundli's Kundli Watch sends a free WhatsApp update on Krishna Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krishna Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan has one building filed: KRISHNA DARSHAN with 8 floors and 34 units.

How much parking does Krishna Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered and 12 open car parking spaces for Krishna Darshan.

How big is the land of Krishna Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan stands on 517 sq m of land (about 0.1 acres), with 1,671 sq m of sanctioned built-up area.

What are the reviews of Krishna Darshan?

Google Maps has reviews of Krishna Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Krishna Darshan?

Krishna Darshan by KRISHNA BUILDCON is in Badlapur East, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700049959, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 148, HISSA NO. 20/A, PLOT NO. 7 & SURVEY NO. 148, HISSA NO. 20/A, PLOT NO. 8. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Krishna Darshan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan has 34 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was Krishna Darshan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Darshan was registered on MahaRERA on 6 March 2023. GharKundli did not find a title report on the land on file there.

Does Krishna Darshan have any legal issues or court cases?

No court cases are listed for Krishna Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Krishna Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KRISHNA BUILDCON, which has 7 other projects registered on MahaRERA.

Other projects in Kulgaon (421503)

All 938 projects in Kulgaon (421503) →

Other projects by KRISHNA BUILDCON

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.