Morya Kasturi Home Tower
by SHREE MORYA ASSOCIATES · Titwala, Thane 421605Also near MandaRegistered on MahaRERA as “KASTURI HOME TOWER”
What’s in the report? →Possession date of Morya Kasturi Home Tower (MahaRERA P51700051947): 30 April 2027, moved from 8 September 2025 (15 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051947, and currently active. Its completion date has moved from September 2025 to April 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700051947, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Morya Kasturi Home Tower?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Morya Kasturi Home Tower has moved
8 September 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA21072502122)
Reason the builder gave MahaRERA: “Updation in Sanctioned Plan, thereby increasing the sacntioned floor to 7”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Morya Kasturi Home Tower’s extension records on MahaRERA (P51700051947), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Morya Kasturi Home Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051947
- Status
- Registered and active
- Builder
- SHREE MORYA ASSOCIATES
- Location
- Titwala, Thane · 421605
- Project type
- Others
- Registered on
- 13 Jul 2023
- Completion date at registration
- September 2025
- Latest completion date
- April 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Morya Kasturi Home Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kasturi Home Tower | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Kasturi Home Tower: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Morya Kasturi Home Tower every 1–2 months.
Morya Kasturi Home Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: Kasturi Home Tower (8 floors, 1 units)
- Car parking: 1 covered
- Land: 528 sq m (about 0.1 acres) · sanctioned built-up 1,809 sq m
- Boundaries filed include: 6 METER LAYOUT ROAD, 5 METER LAYOUT ROAD
- Land, as filed: PLOT No.- 4,5,6, Survey No.- 223/2/M,223/2/N,223/2/R
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Morya Kasturi Home Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Morya Kasturi Home Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Morya Kasturi Home Tower
What is the possession date of Morya Kasturi Home Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Morya Kasturi Home Tower in Titwala, Thane is 30 April 2027 — 15 months later than 8 September 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 15 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Morya Kasturi Home Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Morya Kasturi Home Tower's builder has filed on MahaRERA, the official one, is 30 April 2027, already 15 months later than the 8 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Morya Kasturi Home Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Updation in Sanctioned Plan, thereby increasing the sacntioned floor to 7". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Morya Kasturi Home Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Morya Kasturi Home Tower in Titwala, Thane is P51700051947.
Is Morya Kasturi Home Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower is registered as P51700051947 and its status is "Registered and active".
What is the current construction status of Morya Kasturi Home Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kasturi Home Tower is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Morya Kasturi Home Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Morya Kasturi Home Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower is registered on MahaRERA as P51700051947, its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Morya Kasturi Home Tower?
Morya Kasturi Home Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Morya Kasturi Home Tower?
For a flat in Morya Kasturi Home Tower (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Morya Kasturi Home Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Morya Kasturi Home Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Morya Kasturi Home Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Morya Kasturi Home Tower's possession date changes?
The latest dates are on Morya Kasturi Home Tower's MahaRERA page (P51700051947). GharKundli's Kundli Watch sends a free WhatsApp update on Morya Kasturi Home Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Morya Kasturi Home Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower has one building filed: Kasturi Home Tower with 8 floors and 1 units.
How much parking does Morya Kasturi Home Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Morya Kasturi Home Tower.
How big is the land of Morya Kasturi Home Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower stands on 528 sq m of land (about 0.1 acres), with 1,809 sq m of sanctioned built-up area.
What are the reviews of Morya Kasturi Home Tower?
Google Maps has reviews of Morya Kasturi Home Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Morya Kasturi Home Tower?
Morya Kasturi Home Tower by SHREE MORYA ASSOCIATES is in Titwala, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700051947, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6 METER LAYOUT ROAD, 5 METER LAYOUT ROAD. Its land is filed as PLOT No.- 4,5,6, Survey No.- 223/2/M,223/2/N,223/2/R. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in Morya Kasturi Home Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower has 0 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Morya Kasturi Home Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Kasturi Home Tower was registered on MahaRERA on 13 July 2023. GharKundli did not find a title report on the land on file there.
Does Morya Kasturi Home Tower have any legal issues or court cases?
No court cases are listed for Morya Kasturi Home Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Morya Kasturi Home Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE MORYA ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of Morya Kasturi Home Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Titwala (421605)
- Charms City Phase II
- Ganpati Heights
- Marathe Tower
- Pitambare Tower
- Shree Gajanan Plaza
- Sai Vrindavan
- Mangalmurti Heights
- Sarnobat Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.