Possession date of Shree Krupa Co Op Housing Society (MahaRERA P51700051756): 30 January 2027. It has 26 homes, 59% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700051756, and currently active. Its completion date is now January 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700051756, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shree Krupa Co Op Housing Society?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shree Krupa Co Op Housing Society has moved

  1. 30 September 2026

    Completion date given when the project was registered

  2. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shree Krupa Co Op Housing Society’s extension records on MahaRERA (P51700051756), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Krupa Co Op Housing Society

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700051756
Status
Registered and active
Builder
SHARDA VASTU NIRMITEE PVT. LTD.
Location
Panchpakhadi, Thane · 400602
Project type
Others
Registered on
27 Jun 2023
Completion date at registration
September 2026
Latest completion date
January 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
26
Sold or booked
59%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Shree Krupa Co Op Housing Society, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE KRUPA CO OP HOUSING SOCIETY100%100%95%75%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE KRUPA CO OP HOUSING SOCIETY: covers STILT+1ST TO 11TH & 12TH PART & RECREATIONAL FLOOR

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Krupa Co Op Housing Society every 1–2 months.

Shree Krupa Co Op Housing Society: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE KRUPA CO OP HOUSING SOCIETY (14 floors, 37 units)
  • Car parking: 36 covered
  • Land: 789 sq m (about 0.2 acres) · sanctioned built-up 3,421 sq m
  • Land, as filed: FINAL PLOT NO 226, SUB PLOT NO 19 TOWN PLANNING SCHEME NO 1
  • Map: Get directions

The builder’s record and reviews

Sharda Vastu Nirmitee has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 7 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Shree Krupa Co Op Housing Society →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Krupa Co Op Housing Society: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shree Krupa Co Op Housing Society

What is the possession date of Shree Krupa Co Op Housing Society?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Krupa Co Op Housing Society in Panchpakhadi, Thane is 30 January 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shree Krupa Co Op Housing Society?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Krupa Co Op Housing Society's builder has filed on MahaRERA, the official one, is 30 January 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shree Krupa Co Op Housing Society?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Krupa Co Op Housing Society in Panchpakhadi, Thane is P51700051756.

Is Shree Krupa Co Op Housing Society registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society is registered as P51700051756 and its status is "Registered and active".

What is the current construction status of Shree Krupa Co Op Housing Society? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE KRUPA CO OP HOUSING SOCIETY is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Shree Krupa Co Op Housing Society have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Krupa Co Op Housing Society safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society is registered on MahaRERA as P51700051756, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shree Krupa Co Op Housing Society?

Shree Krupa Co Op Housing Society is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shree Krupa Co Op Housing Society?

For a flat in Shree Krupa Co Op Housing Society (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shree Krupa Co Op Housing Society received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shree Krupa Co Op Housing Society a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society is a redevelopment: 15 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Shree Krupa Co Op Housing Society uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Krupa Co Op Housing Society was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shree Krupa Co Op Housing Society's possession date changes?

The latest dates are on Shree Krupa Co Op Housing Society's MahaRERA page (P51700051756). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Krupa Co Op Housing Society every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Krupa Co Op Housing Society have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society has one building filed: SHREE KRUPA CO OP HOUSING SOCIETY with 14 floors and 37 units.

How much parking does Shree Krupa Co Op Housing Society have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for Shree Krupa Co Op Housing Society.

How big is the land of Shree Krupa Co Op Housing Society?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society stands on 789 sq m of land (about 0.2 acres), with 3,421 sq m of sanctioned built-up area.

What is the track record of Shree Krupa Co Op Housing Society's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sharda Vastu Nirmitee has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 7 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shree Krupa Co Op Housing Society?

Google Maps has reviews of Shree Krupa Co Op Housing Society written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shree Krupa Co Op Housing Society?

Shree Krupa Co Op Housing Society by SHARDA VASTU NIRMITEE PVT. LTD. is in Panchpakhadi, Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700051756, per GharKundli's check of MahaRERA records. Its land is filed as FINAL PLOT NO 226, SUB PLOT NO 19 TOWN PLANNING SCHEME NO 1. GharKundli lists all 258 MahaRERA projects in Naupada (400602).

How many flats are in Shree Krupa Co Op Housing Society, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society has 26 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.

When was Shree Krupa Co Op Housing Society registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krupa Co Op Housing Society was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.

Does Shree Krupa Co Op Housing Society have any legal issues or court cases?

1 court case is listed for Shree Krupa Co Op Housing Society on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Shree Krupa Co Op Housing Society?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHARDA VASTU NIRMITEE PVT. LTD., which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Naupada (400602)

All 258 projects in Naupada (400602) →

Other projects by SHARDA VASTU NIRMITEE PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.