SURAJ RAMA HEIGHTS

by SHREE RAMA SHREE CONSTRUCTION PVT LTD · Panchpakhadi, Thane

Possession date of SURAJ RAMA HEIGHTS: 31 December 2025, moved from 30 June 2021 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700007593. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about SURAJ RAMA HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SURAJ RAMA HEIGHTS has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 29 June 2022

    Extended at the builder's request (MahaRERA application EXT51700010361)

    Reason the builder gave MahaRERA:
    “We have been grappled with shortage of labour and a demand slump challenges triggered by the second wave of covid and the resulting lockdown. The past year 2020-21, has been particularly difficult for us i.e. demand for housing collapsed by…” Read the full reason“We have been grappled with shortage of labour and a demand slump challenges triggered by the second wave of covid and the resulting lockdown. The past year 2020-21, has been particularly difficult for us i.e. demand for housing collapsed by 80 percent. Migrant construction workers have not yet returned from their village. Unit sales have slowed down in all segments-i.e low, middle and high income groups in our project. Due to stagnancy in sale of apartments for the past year constant restrictions under state of Maharashtra the pace of construction is slow. The biggest challenge is getting s…”
  3. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51700016868)

    Reason the builder gave MahaRERA:
    “The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. We have been grappled with shortage of labour and a demand slump challenge…” Read the full reason“The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. The project site being situated at rural areas, the biggest challenge is to find skilled labour at a mass scale to assist in completion of work at a reasonable pace. Due to unavailability of skilled labour and labour migration iss…”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700024965)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, I, Mr. Anilkumar Surajnath Singh, hereby declare the following with respect to the project “Suraj Rama Heights” bearing registration number P51700007593 registered under MahaRERA 1. Status of Work Completed: We are pleased t…” Read the full reason“Dear Sir/Ma’am, I, Mr. Anilkumar Surajnath Singh, hereby declare the following with respect to the project “Suraj Rama Heights” bearing registration number P51700007593 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying…”

Source: SURAJ RAMA HEIGHTS’s extension records on MahaRERA (P51700007593), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SURAJ RAMA HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints and 3 court cases, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700007593
Status
Lapsed (registration period ended)
Builder
SHREE RAMA SHREE CONSTRUCTION PVT LTD
Location
Panchpakhadi, Thane · 400602
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2025
Delay so far
54 months
Homes
127
Towers
1
Complaints on MahaRERA
5
Court cases listed
3
Title report on file
Not found

Construction progress of SURAJ RAMA HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SURAJ RAMA HEIGHTS100%100%100%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SURAJ RAMA HEIGHTS every month.

SURAJ RAMA HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: SURAJ RAMA HEIGHTS (23 floors)
  • Land: 3,195 sq m (about 0.8 acres) · sanctioned built-up 4,250 sq m · recreational space 1,065 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SURAJ RAMA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SURAJ RAMA HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SURAJ RAMA HEIGHTS

What is the possession date of SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SURAJ RAMA HEIGHTS in Panchpakhadi, Thane is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SURAJ RAMA HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SURAJ RAMA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SURAJ RAMA HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2022, giving the reason "We have been grappled with shortage of labour and a demand slump challenges triggered by the second wave of covid and the resulting lockdown. The past year 2020-21, has been particularly difficult for us i.e. demand for housing collapsed by 80 percent. Migrant construction workers have not yet returned from their village. Unit sales have slowed down in all segments-i.e low, middle and high income groups in our project. Due to stagnancy in sale of apartments for the past year constant restrictions under state of Maharashtra the pace of construction is slow. The biggest challenge is getting s…"; to 30 December 2023, giving the reason "The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. The project site being situated at rural areas, the biggest challenge is to find skilled labour at a mass scale to assist in completion of work at a reasonable pace. Due to unavailability of skilled labour and labour migration iss…"; to 31 December 2025, giving the reason "Dear Sir/Ma’am, I, Mr. Anilkumar Surajnath Singh, hereby declare the following with respect to the project “Suraj Rama Heights” bearing registration number P51700007593 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying…".

What is the RERA number of SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SURAJ RAMA HEIGHTS in Panchpakhadi, Thane is P51700007593.

Is SURAJ RAMA HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS is registered as P51700007593 and its status is "Lapsed (registration period ended)".

What is the construction status of SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SURAJ RAMA HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SURAJ RAMA HEIGHTS have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SURAJ RAMA HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS is registered on MahaRERA as P51700007593, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SURAJ RAMA HEIGHTS's possession date changes?

The latest dates are on SURAJ RAMA HEIGHTS's MahaRERA page (P51700007593). GharKundli's Kundli Watch sends a free WhatsApp update on SURAJ RAMA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SURAJ RAMA HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS has one building filed: SURAJ RAMA HEIGHTS with 23 floors.

How big is the land of SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS stands on 3,195 sq m of land (about 0.8 acres), with 4,250 sq m of sanctioned built-up area and 1,065 sq m of recreational open space.

Where can I read reviews of SURAJ RAMA HEIGHTS?

Google Maps has reviews of SURAJ RAMA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SURAJ RAMA HEIGHTS?

SURAJ RAMA HEIGHTS by SHREE RAMA SHREE CONSTRUCTION PVT LTD is in Panchpakhadi, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700007593, per GharKundli's check of MahaRERA records.

How many homes are in SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS has 127 homes in 1 tower registered on MahaRERA.

When was SURAJ RAMA HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SURAJ RAMA HEIGHTS was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SURAJ RAMA HEIGHTS?

3 court cases are listed for SURAJ RAMA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SURAJ RAMA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE RAMA SHREE CONSTRUCTION PVT LTD.