Kalika Heights Phase II
by Sanjay shreenath pandey · Panchpakhadi, Thane
Possession date of Kalika Heights Phase II: 30 October 2027, moved from 31 December 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011655, and currently active. Its completion date has moved from December 2019 to October 2027: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Kalika Heights Phase II?
How the possession date of Kalika Heights Phase II has moved
31 December 2019
Completion date given when the project was registered
31 March 2022
Extended at the builder's request (MahaRERA application EXT51700009504)
Reason the builder gave MahaRERA:
“This is with regards to delay for complete project, Due to Corona-19 pandemic and National wide lockdown imposed by the Government of India to outbreak of Covid-19 pandemic and movement of persons were restricted, therefore, the Developers…” Read the full reason
“This is with regards to delay for complete project, Due to Corona-19 pandemic and National wide lockdown imposed by the Government of India to outbreak of Covid-19 pandemic and movement of persons were restricted, therefore, the Developers could not complete the incomplete work of the above said project within stipulated time prescribed by the authority. The circumstances were beyond the control of the developers. The developers had tried at his level best to complete the project within stipulated time provided by the authority, however, due to the aforesaid reason the project is not comple…”30 September 2023
Extended at the builder's request (MahaRERA application EXT51700012234)
Reason the builder gave MahaRERA: “Due to Lockdown and COVID SECOND WAVE the project was stopped for certain period and there were also facing financial problem by Developer”
30 September 2024
Extended at the builder's request (MahaRERA application EXT51700018730)
Reason the builder gave MahaRERA: “Refer attachment name "Application Letter for extension" in other field.”
30 September 2025
Extended at the builder's request (MahaRERA application EXT51700025278)
Reason the builder gave MahaRERA: “Part Occupancy Certificate Received upto 15 Floors.”
30 June 2027
Extended at the builder's request (MahaRERA application EA04062621232)
Reason the builder gave MahaRERA:
“Poject is complete in all regards OC Part OC is obtained upto 19 (A-1,A-2) Floors. OC for Upper 3 Floors is pending. since the developement on land is part development where a school is also getting developed final joint approvals will be c…” Read the full reason
“Poject is complete in all regards OC Part OC is obtained upto 19 (A-1,A-2) Floors. OC for Upper 3 Floors is pending. since the developement on land is part development where a school is also getting developed final joint approvals will be cleared within a periof of 1 year i.e on or before 30/06/2027”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kalika Heights Phase II’s extension records on MahaRERA (P51700011655), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kalika Heights Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011655
- Status
- Registered and active
- Builder
- Sanjay shreenath pandey
- Location
- Panchpakhadi, Thane · 400061
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- October 2027
- Delay so far
- 90 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 54%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kalika Heights Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kalika Heights Phase II A1 wing | 100% | 100% | 100% | 100% |
| Kalika Heights Phase II Wing A2 | 100% | 100% | 100% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- Kalika Heights Phase II A1 wing: covers 22 floors
- Kalika Heights Phase II Wing A2: covers 22 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalika Heights Phase II every month.
Kalika Heights Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: Kalika Heights Phase II A1 wing (23 floors, 28 units) · Kalika Heights Phase II Wing A2 (23 floors, 28 units)
- Land: 8,839 sq m (about 2.2 acres)
- Boundaries filed include: gayatri madan society, Debinair Society
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kalika Heights Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kalika Heights Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kalika Heights Phase II
What is the possession date of Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalika Heights Phase II in Panchpakhadi, Thane is 30 October 2027 — 90 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Kalika Heights Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalika Heights Phase II's builder has filed on MahaRERA, the official one, is 30 October 2027, already 90 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kalika Heights Phase II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II's builder applied to MahaRERA to extend the completion date 5 times: to 31 March 2022, giving the reason "This is with regards to delay for complete project, Due to Corona-19 pandemic and National wide lockdown imposed by the Government of India to outbreak of Covid-19 pandemic and movement of persons were restricted, therefore, the Developers could not complete the incomplete work of the above said project within stipulated time prescribed by the authority. The circumstances were beyond the control of the developers. The developers had tried at his level best to complete the project within stipulated time provided by the authority, however, due to the aforesaid reason the project is not comple…"; to 30 September 2023, giving the reason "Due to Lockdown and COVID SECOND WAVE the project was stopped for certain period and there were also facing financial problem by Developer"; to 30 September 2024, giving the reason "Refer attachment name "Application Letter for extension" in other field."; to 30 September 2025, giving the reason "Part Occupancy Certificate Received upto 15 Floors."; to 30 June 2027, giving the reason "Poject is complete in all regards OC Part OC is obtained upto 19 (A-1,A-2) Floors. OC for Upper 3 Floors is pending. since the developement on land is part development where a school is also getting developed final joint approvals will be cleared within a periof of 1 year i.e on or before 30/06/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalika Heights Phase II in Panchpakhadi, Thane is P51700011655.
Is Kalika Heights Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II is registered as P51700011655 and its status is "Registered and active".
What is the construction status of Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Kalika Heights Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kalika Heights Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II is registered on MahaRERA as P51700011655, its completion date has moved 90 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kalika Heights Phase II's possession date changes?
The latest dates are on Kalika Heights Phase II's MahaRERA page (P51700011655). GharKundli's Kundli Watch sends a free WhatsApp update on Kalika Heights Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kalika Heights Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II has 2 buildings filed: Kalika Heights Phase II A1 wing with 23 floors and 28 units; Kalika Heights Phase II Wing A2 with 23 floors and 28 units.
How big is the land of Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II stands on 8,839 sq m of land (about 2.2 acres).
Where can I read reviews of Kalika Heights Phase II?
Google Maps has reviews of Kalika Heights Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kalika Heights Phase II?
Kalika Heights Phase II by Sanjay shreenath pandey is in Panchpakhadi, Thane (pincode 400061), Maharashtra, and is registered on MahaRERA as P51700011655, per GharKundli's check of MahaRERA records. Its boundaries filed there include gayatri madan society, Debinair Society.
How many homes are in Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II has 56 homes in 2 towers registered on MahaRERA, and 54% of them are sold or booked.
When was Kalika Heights Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalika Heights Phase II was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Kalika Heights Phase II?
No court cases are listed for Kalika Heights Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Kalika Heights Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sanjay shreenath pandey, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kalika Heights Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Panchpakhadi
- EMPIRE PRESIDENCY
- SHREE KRUPA CO OP HOUSING SOCIETY
- MONICA BY ISHANVI
- MANOHAR MAHAL
- NAND APARTMENT CO-OPERATIVE HOUSING SOCIETY LIMITED
- SURAJ RAMA HEIGHTS
- DEBONAIR CLASSIC
- PRADEEP CO-OPERATIVE HOUSING SOCIETY LTD.
Other projects by Sanjay shreenath pandey
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.