RUNWAL RESERVE
by RUNWAL DEVELOPERS PVT LTD · Lower Parel, MumbaiAlso near Worli, Kalanagar, Bandra East, Delisle Road
Possession: RUNWAL RESERVE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900000383. Status: Completed. 60 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RUNWAL RESERVE?
How the possession date of RUNWAL RESERVE has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT51900000931)
Reason the builder gave MahaRERA:
“We have registered our project “Runwal Reserve” (“hereinafter referred to as the said Project”) on the RERA Website bearing Registration No.51900000383 on 15th July 2017. The “Revised Proposed Date of Completion” while registering the said…” Read the full reason
“We have registered our project “Runwal Reserve” (“hereinafter referred to as the said Project”) on the RERA Website bearing Registration No.51900000383 on 15th July 2017. The “Revised Proposed Date of Completion” while registering the said Project was mentioned on RERA Website as 31/12/2018 . We submit that we acted diligently and have completed the major construction work of the Building and obtained the Part Occupation Certificate dated 7th November 2017 in respect of all flats that are sold upto 24th floors within the Date of Completion as disclosed on the RERA Website. We have not sold…”
Source: RUNWAL RESERVE’s extension records on MahaRERA (P51900000383), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUNWAL RESERVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 60 complaints, and how it ended
- Construction pace against the December 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900000383
- Status
- Completed
- Builder
- RUNWAL DEVELOPERS PVT LTD
- Location
- Lower Parel, Mumbai · 400018
- Project type
- Residential / Group Housing
- Registered on
- 15 Jul 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2019
- Delay so far
- 12 months
- Homes
- 90
- Towers
- 1
- Complaints on MahaRERA
- 60
- Court cases listed
- 0
- Appeals at the tribunal
- 7
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of RUNWAL RESERVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RUNWAL RESERVE | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUNWAL RESERVE every month.
RUNWAL RESERVE: buildings, flats and land, as filed on MahaRERA
- Buildings: RUNWAL RESERVE (36 floors)
- Land: 7,394 sq m (about 1.8 acres) · sanctioned built-up 11,381 sq m · recreational space 3,824 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RUNWAL RESERVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUNWAL RESERVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUNWAL RESERVE
What is the possession date of RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RUNWAL RESERVE in Lower Parel, Mumbai is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RUNWAL RESERVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUNWAL RESERVE's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RUNWAL RESERVE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "We have registered our project “Runwal Reserve” (“hereinafter referred to as the said Project”) on the RERA Website bearing Registration No.51900000383 on 15th July 2017. The “Revised Proposed Date of Completion” while registering the said Project was mentioned on RERA Website as 31/12/2018 . We submit that we acted diligently and have completed the major construction work of the Building and obtained the Part Occupation Certificate dated 7th November 2017 in respect of all flats that are sold upto 24th floors within the Date of Completion as disclosed on the RERA Website. We have not sold…".
What is the RERA number of RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RUNWAL RESERVE in Lower Parel, Mumbai is P51900000383.
Is RUNWAL RESERVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE is registered as P51900000383 and its status is "Completed".
What is the construction status of RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE's status on MahaRERA is "Completed". As filed by the builder, slab work on RUNWAL RESERVE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does RUNWAL RESERVE have complaints on MahaRERA?
60 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUNWAL RESERVE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE is registered on MahaRERA as P51900000383, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 60 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RUNWAL RESERVE's possession date changes?
The latest dates are on RUNWAL RESERVE's MahaRERA page (P51900000383). GharKundli's Kundli Watch sends a free WhatsApp update on RUNWAL RESERVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUNWAL RESERVE have?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE has one building filed: RUNWAL RESERVE with 36 floors.
How big is the land of RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE stands on 7,394 sq m of land (about 1.8 acres), with 11,381 sq m of sanctioned built-up area and 3,824 sq m of recreational open space.
Where can I read reviews of RUNWAL RESERVE?
Google Maps has reviews of RUNWAL RESERVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 60 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUNWAL RESERVE?
RUNWAL RESERVE by RUNWAL DEVELOPERS PVT LTD is in Lower Parel, Mumbai (pincode 400018), near Worli, Kalanagar, Bandra East, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900000383, per GharKundli's check of MahaRERA records.
How many homes are in RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE has 90 homes in 1 tower registered on MahaRERA.
When was RUNWAL RESERVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RUNWAL RESERVE was registered on MahaRERA on 15 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RUNWAL RESERVE?
No court cases are listed for RUNWAL RESERVE on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RUNWAL RESERVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RUNWAL DEVELOPERS PVT LTD, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RUNWAL RESERVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Lower Parel
- PLUS ART
- Siddharth Enclave
- Raheja Imperia II
- Sumer Samaq Prime
- 7 Mahalaxmi - Tower 3
- Birla Niyaara Phase-1
- SILA TOWER
- Anant Serene Villas II
Other projects by RUNWAL DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.