Gami Erica
by Lal Gebi Infra Co. · Shahbaz- Belapur, ThaneAlso near CBD Belapur, C.B.D. Belapur, Agroli Belapur
Possession date of Gami Erica: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700052930, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Gami Erica?
How the possession date of Gami Erica has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA10022619783)
Reason the builder gave MahaRERA:
“The project has been delayed due to the non-receipt of the Occupancy Certificate (OC). The application for the Occupancy Certificate has already been duly submitted and approval is still pending owing to administrative delays at their end.…” Read the full reason
“The project has been delayed due to the non-receipt of the Occupancy Certificate (OC). The application for the Occupancy Certificate has already been duly submitted and approval is still pending owing to administrative delays at their end. As the flat in question has already been sold, its registration is required to be completed. However, in the absence of the Occupancy Certificate, the registration process cannot be carried out. In view of the above circumstances, which are beyond our control, we are constrained to seek an extension of time for registration of the said flat until the Occu…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Gami Erica’s extension records on MahaRERA (P51700052930), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gami Erica
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700052930
- Status
- Registered and active
- Builder
- Lal Gebi Infra Co.
- Location
- Shahbaz- Belapur, Thane · 400614
- Project type
- Others
- Registered on
- 5 Oct 2023
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 70
- Sold or booked
- 88%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Gami Erica, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Gami Erica | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Gami Erica: covers 8 (G + 7)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gami Erica every month.
Gami Erica: buildings, flats and land, as filed on MahaRERA
- Buildings: Gami Erica (8 floors, 76 units)
- Car parking: 80 covered
- Land: 1,235 sq m (about 0.3 acres) · sanctioned built-up 3,972 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Gami Erica →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gami Erica: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Gami Erica
What is the possession date of Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gami Erica in Shahbaz- Belapur, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Gami Erica?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gami Erica's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gami Erica extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project has been delayed due to the non-receipt of the Occupancy Certificate (OC). The application for the Occupancy Certificate has already been duly submitted and approval is still pending owing to administrative delays at their end. As the flat in question has already been sold, its registration is required to be completed. However, in the absence of the Occupancy Certificate, the registration process cannot be carried out. In view of the above circumstances, which are beyond our control, we are constrained to seek an extension of time for registration of the said flat until the Occu…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gami Erica in Shahbaz- Belapur, Thane is P51700052930.
Is Gami Erica registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica is registered as P51700052930 and its status is "Registered and active".
What is the construction status of Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Gami Erica is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Gami Erica have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Gami Erica safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica is registered on MahaRERA as P51700052930, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Gami Erica's possession date changes?
The latest dates are on Gami Erica's MahaRERA page (P51700052930). GharKundli's Kundli Watch sends a free WhatsApp update on Gami Erica every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gami Erica have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica has one building filed: Gami Erica with 8 floors and 76 units.
How much parking does Gami Erica have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 80 covered car parking spaces for Gami Erica.
How big is the land of Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica stands on 1,235 sq m of land (about 0.3 acres), with 3,972 sq m of sanctioned built-up area.
Where can I read reviews of Gami Erica?
Google Maps has reviews of Gami Erica written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Gami Erica?
Gami Erica by Lal Gebi Infra Co. is in Shahbaz- Belapur, Thane (pincode 400614), near CBD Belapur, C.B.D. Belapur, Agroli Belapur, Maharashtra, and is registered on MahaRERA as P51700052930, per GharKundli's check of MahaRERA records.
How many homes are in Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica has 70 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.
When was Gami Erica registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami Erica was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Gami Erica?
1 court case is listed for Gami Erica on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Gami Erica?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lal Gebi Infra Co..
Check it yourself on MahaRERA
- How to check the possession date of Gami Erica
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.