Skip to content
GharKundli

Shubham Shree Balaji Empire

by SHUBHAM HOUSING · Bhayander East, Thane 401105Also near Mira Road East, Navghar Village, GoddevRegistered on MahaRERA as “SHREE BALAJI EMPIRE”

What’s in the report? →

Possession date of Shubham Shree Balaji Empire (MahaRERA P51700054916): 31 December 2030. It has 171 homes, 50% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700054916, and currently active.

Source: MahaRERA website — records for P51700054916, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shubham Shree Balaji Empire?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shubham Shree Balaji Empire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700054916
Status
Registered and active
Builder
SHUBHAM HOUSING
Location
Bhayander East, Thane · 401105
Project type
Others
Registered on
15 Feb 2024
Completion date at registration
December 2030
Homes
171
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shubham Shree Balaji Empire, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE BALAJI EMPIRE BUILDING NO 1, SALE BUILDING PLOT A100%100%33%50%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE BALAJI EMPIRE BUILDING NO 1, SALE BUILDING PLOT A: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubham Shree Balaji Empire every 1–2 months.

Shubham Shree Balaji Empire: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE BALAJI EMPIRE BUILDING NO 1, SALE BUILDING PLOT A (21 floors, 234 units)
  • Land: 5,376 sq m (about 1.3 acres) · sanctioned built-up 13,990 sq m · recreational space 846 sq m
  • Land, as filed: S. NO.30(236)/2PT,3PT,4PT,6PT,7PT,8PT,12PT, S.NO.33(242)/H.NO.1PT, S. NO. 31(235)/9,10PT
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Shubham Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Shubham Shree Balaji Empire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shubham Shree Balaji Empire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shubham Shree Balaji Empire

What is the possession date of Shubham Shree Balaji Empire?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shubham Shree Balaji Empire in Bhayander East, Thane is 31 December 2030.

Is the builder's possession date different from the MahaRERA date for Shubham Shree Balaji Empire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubham Shree Balaji Empire's builder has filed on MahaRERA, the official one, is 31 December 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shubham Shree Balaji Empire?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shubham Shree Balaji Empire in Bhayander East, Thane is P51700054916.

Is Shubham Shree Balaji Empire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire is registered as P51700054916 and its status is "Registered and active".

What is the current construction status of Shubham Shree Balaji Empire? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE BALAJI EMPIRE BUILDING NO 1, SALE BUILDING PLOT A is 100% done and internal work 33%. GharKundli's full report compares construction progress with the deadline.

Does Shubham Shree Balaji Empire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shubham Shree Balaji Empire safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire is registered on MahaRERA as P51700054916, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shubham Shree Balaji Empire?

Shubham Shree Balaji Empire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shubham Shree Balaji Empire?

For a flat in Shubham Shree Balaji Empire (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shubham Shree Balaji Empire received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire is still under construction, with 31 December 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Shubham Shree Balaji Empire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shubham Shree Balaji Empire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shubham Shree Balaji Empire's possession date changes?

The latest dates are on Shubham Shree Balaji Empire's MahaRERA page (P51700054916). GharKundli's Kundli Watch sends a free WhatsApp update on Shubham Shree Balaji Empire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shubham Shree Balaji Empire have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire has one building filed: SHREE BALAJI EMPIRE BUILDING NO 1, SALE BUILDING PLOT A with 21 floors and 234 units.

How big is the land of Shubham Shree Balaji Empire?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire stands on 5,376 sq m of land (about 1.3 acres), with 13,990 sq m of sanctioned built-up area and 846 sq m of recreational open space.

What is the track record of Shubham Shree Balaji Empire's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shubham Shree Balaji Empire?

Google Maps has reviews of Shubham Shree Balaji Empire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shubham Shree Balaji Empire?

Shubham Shree Balaji Empire by SHUBHAM HOUSING is in Bhayander East, Thane, pincode 401105 (near Mira Road East, Navghar Village, Goddev), Maharashtra, and is registered on MahaRERA as P51700054916, per GharKundli's check of MahaRERA records. Its land is filed as S. NO.30(236)/2PT,3PT,4PT,6PT,7PT,8PT,12PT, S.NO.33(242)/H.NO.1PT, S. NO. 31(235)/9,10PT. GharKundli lists all 99 MahaRERA projects in Bhayander East (401105).

How many flats are in Shubham Shree Balaji Empire, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire has 171 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Shubham Shree Balaji Empire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubham Shree Balaji Empire was registered on MahaRERA on 15 February 2024. GharKundli did not find a title report on the land on file there.

Does Shubham Shree Balaji Empire have any legal issues or court cases?

No court cases are listed for Shubham Shree Balaji Empire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shubham Shree Balaji Empire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHUBHAM HOUSING.

All projects with possession due in 2030 in Palghar →

Other projects in Bhayander East (401105)

All 99 projects in Bhayander East (401105) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.