Olivia Tower - A

by LODHA DEVELOPERS LIMITED · Khoni, Thane 421204Also near Manpada, Vishnunagar

What’s in the report? →

Possession date of Olivia Tower - A (MahaRERA P51700052470): 30 October 2027. It has 85 homes, 53% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700052470, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700052470, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Olivia Tower - A?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Olivia Tower - A has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Olivia Tower - A’s extension records on MahaRERA (P51700052470), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Olivia Tower - A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700052470
Status
Registered and active
Builder
LODHA DEVELOPERS LIMITED
Location
Khoni, Thane · 421204
Project type
Residential / Group Housing
Registered on
8 Sep 2023
Completion date at registration
June 2027
Latest completion date
October 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
85
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Olivia Tower - A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A Cluster 4 Point 02 Sector D100%95%24%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A Cluster 4 Point 02 Sector D: covers 23 floors

Latest CC order on MahaRERA: dated 30/12/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Olivia Tower - A every 1–2 months.

Olivia Tower - A: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A Cluster 4 Point 02 Sector D (23 floors, 91 units)
  • Car parking: 33 covered
  • Land: 2,280 sq m (about 0.6 acres) · sanctioned built-up 9,376 sq m
  • Land, as filed: 64/1A Part
  • Map: Get directions

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Olivia Tower - A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Olivia Tower - A: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Olivia Tower - A

What is the possession date of Olivia Tower - A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Olivia Tower - A in Khoni, Thane is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Olivia Tower - A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Olivia Tower - A's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Olivia Tower - A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Olivia Tower - A in Khoni, Thane is P51700052470.

Is Olivia Tower - A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A is registered as P51700052470 and its status is "Registered and active".

What is the current construction status of Olivia Tower - A? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A Cluster 4 Point 02 Sector D is 95% done and internal work 24%. GharKundli's full report compares construction progress with the deadline.

Does Olivia Tower - A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Olivia Tower - A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A is registered on MahaRERA as P51700052470, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Olivia Tower - A?

Olivia Tower - A is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Olivia Tower - A?

For a flat in Olivia Tower - A (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Olivia Tower - A received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Olivia Tower - A uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Olivia Tower - A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Olivia Tower - A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Olivia Tower -B (P51700052243, possession 31 Mar 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Olivia Tower - A's possession date changes?

The latest dates are on Olivia Tower - A's MahaRERA page (P51700052470). GharKundli's Kundli Watch sends a free WhatsApp update on Olivia Tower - A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Olivia Tower - A have?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A has one building filed: Wing A Cluster 4 Point 02 Sector D with 23 floors and 91 units.

How much parking does Olivia Tower - A have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for Olivia Tower - A.

How big is the land of Olivia Tower - A?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A stands on 2,280 sq m of land (about 0.6 acres), with 9,376 sq m of sanctioned built-up area.

What is the track record of Olivia Tower - A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Olivia Tower - A?

Google Maps has reviews of Olivia Tower - A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Olivia Tower - A?

Olivia Tower - A by LODHA DEVELOPERS LIMITED is in Khoni, Thane, pincode 421204 (near Manpada, Vishnunagar), Maharashtra, and is registered on MahaRERA as P51700052470, per GharKundli's check of MahaRERA records. Its land is filed as 64/1A Part. GharKundli lists all 252 MahaRERA projects in Manpada (421204).

How many flats are in Olivia Tower - A, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A has 85 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was Olivia Tower - A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Olivia Tower - A was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.

Does Olivia Tower - A have any legal issues or court cases?

No court cases are listed for Olivia Tower - A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Olivia Tower - A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LODHA DEVELOPERS LIMITED, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Manpada (421204)

All 252 projects in Manpada (421204) →

Other projects by LODHA DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.