Mohan Samah
by V M Constructions · Sarsole,Nerul, ThaneAlso near Nerul Node III
Possession date of Mohan Samah: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053276, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Mohan Samah?
How the possession date of Mohan Samah has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mohan Samah’s extension records on MahaRERA (P51700053276), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mohan Samah
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053276
- Status
- Registered and active
- Builder
- V M Constructions
- Location
- Sarsole,Nerul, Thane · 400706
- Project type
- Others
- Registered on
- 23 Oct 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 63
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Mohan Samah, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Mohan Samah | 50% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Mohan Samah: covers 32 (Basement + Ground Floor + 30 Upper Floor)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mohan Samah every month.
Mohan Samah: buildings, flats and land, as filed on MahaRERA
- Buildings: Mohan Samah (10 floors, 86 units)
- Land: 1,499 sq m (about 0.4 acres) · sanctioned built-up 2,058 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
V M Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Mohan Samah →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mohan Samah: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mohan Samah
What is the possession date of Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mohan Samah in Sarsole,Nerul, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mohan Samah?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mohan Samah's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mohan Samah in Sarsole,Nerul, Thane is P51700053276.
Is Mohan Samah registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah is registered as P51700053276 and its status is "Registered and active".
What is the construction status of Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Mohan Samah is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Mohan Samah have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Mohan Samah safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah is registered on MahaRERA as P51700053276, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mohan Samah's possession date changes?
The latest dates are on Mohan Samah's MahaRERA page (P51700053276). GharKundli's Kundli Watch sends a free WhatsApp update on Mohan Samah every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mohan Samah have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah has one building filed: Mohan Samah with 10 floors and 86 units.
How big is the land of Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah stands on 1,499 sq m of land (about 0.4 acres), with 2,058 sq m of sanctioned built-up area.
What is the track record of Mohan Samah's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), V M Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mohan Samah?
Google Maps has reviews of Mohan Samah written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mohan Samah?
Mohan Samah by V M Constructions is in Sarsole,Nerul, Thane (pincode 400706), near Nerul Node III, Maharashtra, and is registered on MahaRERA as P51700053276, per GharKundli's check of MahaRERA records.
How many homes are in Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah has 63 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was Mohan Samah registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Samah was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Mohan Samah?
1 court case is listed for Mohan Samah on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Mohan Samah?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V M Constructions, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mohan Samah
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Thane
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Other projects by V M Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.