Empire City Building No. 1
by Empire Developers · Pisavli, Thane 421306Also near Katemanivali
What’s in the report? →Possession date of Empire City Building No. 1 (MahaRERA P51700053544): 30 April 2027, moved from 31 December 2025 (12 months later). It has 28 homes, 56% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053544, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700053544, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Empire City Building No. 1?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Empire City Building No. 1 has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA27122519060)
Reason the builder gave MahaRERA:
“. The project has been delayed due to pending finishing works. While the major structural work has been completed, certain finishing activities such as internal finishing, services installation. These works required additional time to ensur…” Read the full reason
“. The project has been delayed due to pending finishing works. While the major structural work has been completed, certain finishing activities such as internal finishing, services installation. These works required additional time to ensure proper execution and quality compliance, which has resulted in an extension of the project timeline. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Empire City Building No. 1’s extension records on MahaRERA (P51700053544), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Empire City Building No. 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053544
- Status
- Registered and active
- Builder
- Empire Developers
- Location
- Pisavli, Thane · 421306
- Project type
- Others
- Registered on
- 10 Nov 2023
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 56%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Empire City Building No. 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Empire City Building No 1 | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- Empire City Building No 1: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Empire City Building No. 1 every 1–2 months.
Empire City Building No. 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Empire City Building No 1 (8 floors, 32 units)
- Land: 1,370 sq m (about 0.3 acres) · sanctioned built-up 1,244 sq m
- Land, as filed: Survey No-36/5/A & Survey No-36/5/B
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Empire City Building No. 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Empire City Building No. 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Empire City Building No. 1
What is the possession date of Empire City Building No. 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Empire City Building No. 1 in Pisavli, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Empire City Building No. 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Empire City Building No. 1's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Empire City Building No. 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason ". The project has been delayed due to pending finishing works. While the major structural work has been completed, certain finishing activities such as internal finishing, services installation. These works required additional time to ensure proper execution and quality compliance, which has resulted in an extension of the project timeline. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Empire City Building No. 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Empire City Building No. 1 in Pisavli, Thane is P51700053544.
Is Empire City Building No. 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 is registered as P51700053544 and its status is "Registered and active".
What is the current construction status of Empire City Building No. 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Empire City Building No 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Empire City Building No. 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Empire City Building No. 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 is registered on MahaRERA as P51700053544, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Empire City Building No. 1?
Empire City Building No. 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Empire City Building No. 1?
For a flat in Empire City Building No. 1 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Empire City Building No. 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Empire City Building No. 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Empire City Building No. 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Empire City Building No. 1's possession date changes?
The latest dates are on Empire City Building No. 1's MahaRERA page (P51700053544). GharKundli's Kundli Watch sends a free WhatsApp update on Empire City Building No. 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Empire City Building No. 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 has one building filed: Empire City Building No 1 with 8 floors and 32 units.
How big is the land of Empire City Building No. 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 stands on 1,370 sq m of land (about 0.3 acres), with 1,244 sq m of sanctioned built-up area.
What are the reviews of Empire City Building No. 1?
Google Maps has reviews of Empire City Building No. 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Empire City Building No. 1?
Empire City Building No. 1 by Empire Developers is in Pisavli, Thane, pincode 421306 (near Katemanivali), Maharashtra, and is registered on MahaRERA as P51700053544, per GharKundli's check of MahaRERA records. Its land is filed as Survey No-36/5/A & Survey No-36/5/B. GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).
How many flats are in Empire City Building No. 1, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 has 28 homes in 1 tower registered on MahaRERA, and 56% of them are sold or booked.
When was Empire City Building No. 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Empire City Building No. 1 was registered on MahaRERA on 10 November 2023. GharKundli did not find a title report on the land on file there.
Does Empire City Building No. 1 have any legal issues or court cases?
No court cases are listed for Empire City Building No. 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Empire City Building No. 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Empire Developers, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Empire City Building No. 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan East (421306)
- Royal Hills
- Hare Krishna Janvi Height
- Krishna Anand
- Sai Dream World Building No 04 Sai Dream Vertex
- Sai Dream World Building No 01 (Sai Dream Signature)
- Davakhar Elegance Phase II
- Nature Vista Building - 1
- Mahadev Heights
Other projects by Empire Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.