Morya Manas Heights
by K V M and Morya Group · Titwala East, Thane 421605Also near MandaRegistered on MahaRERA as “Manas Heights”
What’s in the report? →Possession date of Morya Manas Heights (MahaRERA P51700054620): 30 April 2028, moved from 31 December 2025 (24 months later). It has 30 homes, 16% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700054620, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700054620, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Morya Manas Heights?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Morya Manas Heights has moved
31 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA29102518189)
Reason the builder gave MahaRERA: “Delay in project completion occurred due to shortage of skilled and unskilled labour in the mofussil area, caused by migration and lack of local workforce availability, which affected construction progress despite best efforts.”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Morya Manas Heights’s extension records on MahaRERA (P51700054620), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Morya Manas Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700054620
- Status
- Registered and active
- Builder
- K V M and Morya Group
- Location
- Titwala East, Thane · 421605
- Project type
- Others
- Registered on
- 2 Feb 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 16%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Morya Manas Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Manas Heights | 100% | 100% | 80% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Manas Heights: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Morya Manas Heights every 1–2 months.
Morya Manas Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Manas Heights (6 floors, 32 units)
- Car parking: 26 covered
- Land: 676 sq m (about 0.2 acres) · sanctioned built-up 1,662 sq m
- Land, as filed: S. No. 188, H. No. 2B, Plot No. 2/3/4/5 Village Titwala, Tal Kalyan 421605
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Morya Manas Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Morya Manas Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Morya Manas Heights
What is the possession date of Morya Manas Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Morya Manas Heights in Titwala East, Thane is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Morya Manas Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Morya Manas Heights's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Morya Manas Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Delay in project completion occurred due to shortage of skilled and unskilled labour in the mofussil area, caused by migration and lack of local workforce availability, which affected construction progress despite best efforts.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Morya Manas Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Morya Manas Heights in Titwala East, Thane is P51700054620.
Is Morya Manas Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights is registered as P51700054620 and its status is "Registered and active".
What is the current construction status of Morya Manas Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Manas Heights is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does Morya Manas Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Morya Manas Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights is registered on MahaRERA as P51700054620, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Morya Manas Heights?
Morya Manas Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Morya Manas Heights?
For a flat in Morya Manas Heights (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Morya Manas Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Morya Manas Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Morya Manas Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Morya Manas Heights's possession date changes?
The latest dates are on Morya Manas Heights's MahaRERA page (P51700054620). GharKundli's Kundli Watch sends a free WhatsApp update on Morya Manas Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Morya Manas Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights has one building filed: Manas Heights with 6 floors and 32 units.
How much parking does Morya Manas Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for Morya Manas Heights.
How big is the land of Morya Manas Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights stands on 676 sq m of land (about 0.2 acres), with 1,662 sq m of sanctioned built-up area.
What are the reviews of Morya Manas Heights?
Google Maps has reviews of Morya Manas Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Morya Manas Heights?
Morya Manas Heights by K V M and Morya Group is in Titwala East, Thane, pincode 421605 (near Manda), Maharashtra, and is registered on MahaRERA as P51700054620, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 188, H. No. 2B, Plot No. 2/3/4/5 Village Titwala, Tal Kalyan 421605. GharKundli lists all 174 MahaRERA projects in Titwala (421605).
How many flats are in Morya Manas Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights has 30 homes in 1 tower registered on MahaRERA, and 16% of them are sold or booked.
When was Morya Manas Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Manas Heights was registered on MahaRERA on 2 February 2024. GharKundli did not find a title report on the land on file there.
Does Morya Manas Heights have any legal issues or court cases?
No court cases are listed for Morya Manas Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Morya Manas Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K V M and Morya Group.
Check it yourself on MahaRERA
- How to check the possession date of Morya Manas Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Titwala (421605)
- Charms City Phase II
- Ganpati Heights
- Marathe Tower
- Pitambare Tower
- Shree Gajanan Plaza
- Sai Vrindavan
- Mangalmurti Heights
- Sarnobat Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.