What’s in the report? →Possession date of Sai Shrushti Leela (MahaRERA P51700078596): 30 April 2028. It has 328 homes, 43% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700078596, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700078596, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sai Shrushti Leela?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sai Shrushti Leela has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sai Shrushti Leela’s extension records on MahaRERA (P51700078596), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Shrushti Leela
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SAI SHRUSHTI LEELA PHASE IIIPR1330002600117 · possession 30 Apr 2030
- SAI SHRUSHTI LEELA PHASE VPM1330002601558 · possession 31 Dec 2030
- MahaRERA registration
- P51700078596
- Status
- Registered and active
- Builder
- SAI SHRUSHTI ENTERPRISES
- Location
- Padale, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 27 Dec 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 328
- Sold or booked
- 43%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of Sai Shrushti Leela, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 2 | 100% | 100% | 100% | 0% |
| BUILDING 1 | 100% | 100% | 60% | 0% |
| BUILDING 3 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING 2: covers 1 floors
- BUILDING 1: covers 20 floors
- BUILDING 3: covers 20 floors
Latest CC order on MahaRERA: dated 03/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Shrushti Leela every 1–2 months.
Sai Shrushti Leela: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 2 (1 floors, 1 units) · BUILDING 1 (20 floors, 148 units) · BUILDING 3 (20 floors, 180 units)
- Car parking: 81 covered, 51 open
- Land: 4,205 sq m (about 1.0 acres) · sanctioned built-up 18,499 sq m
- Land, as filed: S. NO. 72/1, S. NO. 72/6, Sector-11 of Mouje Padale
- Map: Get directions
The builder’s record and reviews
SAI Shrushti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 15 GharKundli has checked: 9 finished, all within the promised date; 6 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.
Read Google reviews of Sai Shrushti Leela →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Shrushti Leela: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sai Shrushti Leela
What is the possession date of Sai Shrushti Leela?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Shrushti Leela in Padale, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sai Shrushti Leela?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Shrushti Leela's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sai Shrushti Leela?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Shrushti Leela in Padale, Thane is P51700078596.
Is Sai Shrushti Leela registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela is registered as P51700078596 and its status is "Registered and active".
What is the current construction status of Sai Shrushti Leela? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Sai Shrushti Leela have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sai Shrushti Leela safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela is registered on MahaRERA as P51700078596, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sai Shrushti Leela?
Sai Shrushti Leela is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sai Shrushti Leela?
For a flat in Sai Shrushti Leela (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sai Shrushti Leela received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sai Shrushti Leela uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Shrushti Leela was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Sai Shrushti Leela have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: SAI SHRUSHTI LEELA PHASE III (PR1330002600117, possession 30 Apr 2030); SAI SHRUSHTI LEELA PHASE V (PM1330002601558, possession 31 Dec 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Sai Shrushti Leela's possession date changes?
The latest dates are on Sai Shrushti Leela's MahaRERA page (P51700078596). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Shrushti Leela every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Shrushti Leela have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela has 3 buildings filed: BUILDING 2 with 1 floors and 1 units; BUILDING 1 with 20 floors and 148 units; BUILDING 3 with 20 floors and 180 units.
How much parking does Sai Shrushti Leela have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 81 covered and 51 open car parking spaces for Sai Shrushti Leela.
How big is the land of Sai Shrushti Leela?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela stands on 4,205 sq m of land (about 1.0 acres), with 18,499 sq m of sanctioned built-up area.
What is the track record of Sai Shrushti Leela's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI Shrushti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 15 GharKundli has checked: 9 finished, all within the promised date; 6 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sai Shrushti Leela?
Google Maps has reviews of Sai Shrushti Leela written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sai Shrushti Leela?
Sai Shrushti Leela by SAI SHRUSHTI ENTERPRISES is in Padale, Thane, pincode 421204 (near Manpada, Vishnunagar), Maharashtra, and is registered on MahaRERA as P51700078596, per GharKundli's check of MahaRERA records. Its land is filed as S. NO. 72/1, S. NO. 72/6, Sector-11 of Mouje Padale. GharKundli lists all 252 MahaRERA projects in Manpada (421204).
How many flats are in Sai Shrushti Leela, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela has 328 homes in 3 towers registered on MahaRERA, and 43% of them are sold or booked.
When was Sai Shrushti Leela registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sai Shrushti Leela was registered on MahaRERA on 27 December 2024. GharKundli did not find a title report on the land on file there.
Does Sai Shrushti Leela have any legal issues or court cases?
1 court case is listed for Sai Shrushti Leela on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Sai Shrushti Leela?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI SHRUSHTI ENTERPRISES, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sai Shrushti Leela
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Manpada (421204)
- Shanti Luxuria
- Palava Fresca J-K
- Chanakya C wing
- Chanakya A wing
- Yesu Anand Heights
- Arista Skyline
- Runwal Gardens Phase 4 Bldg No. 33-34
- Shree Krishna Heights
Other projects by SAI SHRUSHTI ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.