VEDANT PARK Wing D of the Phase II

by KAILAS RAVIKANT KABADI · KHativali, Thane

Registered on MahaRERA under P51700078741, and currently active. Its completion date has moved from March 2029 to July 2029, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on VEDANT PARK Wing D of the Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700078741
Status
Registered and active
Builder
KAILAS RAVIKANT KABADI
Location
KHativali, Thane · 421601
Project type
Residential / Group Housing
Registered on
8 Jan 2025
Completion date at registration
March 2029
Latest completion date
July 2029
Delay so far
4 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

VEDANT PARK Wing D of the Phase II: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about VEDANT PARK Wing D of the Phase II

Is VEDANT PARK Wing D of the Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VEDANT PARK Wing D of the Phase II is registered as P51700078741 and its status is "Registered and active".

Where is VEDANT PARK Wing D of the Phase II?

VEDANT PARK Wing D of the Phase II by KAILAS RAVIKANT KABADI is in KHativali, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700078741, per GharKundli's check of MahaRERA records.

When is possession of VEDANT PARK Wing D of the Phase II due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VEDANT PARK Wing D of the Phase II in KHativali, Thane is 31 July 2029 — 4 months later than 31 March 2029, the date given at registration.

Does VEDANT PARK Wing D of the Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of VEDANT PARK Wing D of the Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KAILAS RAVIKANT KABADI.

Other projects in pincode 421601

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.