JVMs Emerald
by JVM LIFESPACES · Thane 400601Also near Charai, Majiwada, Naupada
What’s in the report? →Possession: JVMs Emerald (MahaRERA P51700078908) is marked completed on MahaRERA. It has 28 homes, 69% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700078908. Status: Completed.
Source: MahaRERA website — records for P51700078908, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about JVMs Emerald?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on JVMs Emerald
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700078908
- Status
- Completed
- Builder
- JVM LIFESPACES
- Location
- Thane · 400601
- Project type
- Others
- Registered on
- 20 Jan 2025
- Completion date at registration
- December 2027
- Homes
- 28
- Sold or booked
- 69%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of JVMs Emerald, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 | 100% | 100% | 75% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1: covers 8 (G + 7)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on JVMs Emerald every 1–2 months.
JVMs Emerald: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1 (8 floors, 29 units)
- Land: 338 sq m (about 0.1 acres) · sanctioned built-up 1,100 sq m
- Land, as filed: CTS No 16 Tika No 8
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
JVM Spaces (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 15 months); 4 still being built, none past the promised date yet; 1 lapsed. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of JVMs Emerald →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
JVMs Emerald: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about JVMs Emerald
What is the possession date of JVMs Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JVMs Emerald in Thane is 31 December 2027.
Is the builder's possession date different from the MahaRERA date for JVMs Emerald?
Builders and listing sites often quote an earlier "target" date for handover. The completion date JVMs Emerald's builder has filed on MahaRERA, the official one, is 31 December 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of JVMs Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JVMs Emerald in Thane is P51700078908.
Is JVMs Emerald registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald is registered as P51700078908 and its status is "Completed".
What is the current construction status of JVMs Emerald? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald's status on MahaRERA is "Completed". As filed by the builder, slab work on Building No 1 is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does JVMs Emerald have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is JVMs Emerald safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald is registered on MahaRERA as P51700078908, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in JVMs Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in JVMs Emerald?
For a flat in JVMs Emerald (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has JVMs Emerald received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was JVMs Emerald completed?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald is marked completed on MahaRERA, and the completion date filed there is 31 December 2027. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has JVMs Emerald uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for JVMs Emerald was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if JVMs Emerald's possession date changes?
The latest dates are on JVMs Emerald's MahaRERA page (P51700078908). GharKundli's Kundli Watch sends a free WhatsApp update on JVMs Emerald every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does JVMs Emerald have?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald has one building filed: Building No 1 with 8 floors and 29 units.
How big is the land of JVMs Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald stands on 338 sq m of land (about 0.1 acres), with 1,100 sq m of sanctioned built-up area.
What is the track record of JVMs Emerald's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), JVM Spaces (a group of 6 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 15 months); 4 still being built, none past the promised date yet; 1 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of JVMs Emerald?
Google Maps has reviews of JVMs Emerald written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of JVMs Emerald?
JVMs Emerald by JVM LIFESPACES is in Thane, pincode 400601 (near Charai, Majiwada, Naupada), Maharashtra, and is registered on MahaRERA as P51700078908, per GharKundli's check of MahaRERA records. Its land is filed as CTS No 16 Tika No 8. GharKundli lists all 178 MahaRERA projects in Thane (400601).
How many flats are in JVMs Emerald, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald has 28 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.
When was JVMs Emerald registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), JVMs Emerald was registered on MahaRERA on 20 January 2025. GharKundli did not find a title report on the land on file there.
Does JVMs Emerald have any legal issues or court cases?
No court cases are listed for JVMs Emerald on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of JVMs Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JVM LIFESPACES.
Check it yourself on MahaRERA
- How to check the possession date of JVMs Emerald
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane (400601)
- Panache
- Shrikrishna Residency Cooperative Housing Society Limited
- Nav Sulochana Co-operative Housing Society Limited
- Urmila Co-operative Housing Society LTD
- Devshrushti Co-op. Hsg Soc. Ltd
- Phatak Wada
- Raj Tattva Phase 1 Commercial
- Shree Gangadhar CHSL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.