Shiv Sarovar Wing B

by MAHESH BHARAT DIVNALE · Belavali, Badlapur West, Thane 421503

What’s in the report? →

Possession date of Shiv Sarovar Wing B (MahaRERA P51700079043): 1 September 2026, and it has already passed. It has 14 homes, 55% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700079043. Status: Lapsed (registration period ended). Its completion date is now September 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700079043, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about Shiv Sarovar Wing B?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shiv Sarovar Wing B has moved

  1. 1 May 2026

    Completion date given when the project was registered

  2. 1 September 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shiv Sarovar Wing B’s extension records on MahaRERA (P51700079043), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shiv Sarovar Wing B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700079043
Status
Lapsed (registration period ended)
Builder
MAHESH BHARAT DIVNALE
Location
Belavali, Badlapur West, Thane · 421503
Project type
Residential / Group Housing
Registered on
31 Jan 2025
Completion date at registration
May 2026
Latest completion date
September 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
14
Sold or booked
55%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Shiv Sarovar Wing B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIV SAROVAR WING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SHIV SAROVAR WING B: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shiv Sarovar Wing B every 1–2 months.

Shiv Sarovar Wing B: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHIV SAROVAR WING B (8 floors, 14 units)
  • Car parking: 1 covered
  • Land: 380 sq m (about 0.1 acres) · sanctioned built-up 651 sq m
  • Land, as filed: SURVEY NO 95, HISSA NO. 1A & 1V
  • Map: Get directions

The builder’s record and reviews

Mahesh Bharat Divnale has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Shiv Sarovar Wing B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shiv Sarovar Wing B: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shiv Sarovar Wing B

What is the possession date of Shiv Sarovar Wing B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shiv Sarovar Wing B in Belavali, Badlapur West, Thane is 1 September 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shiv Sarovar Wing B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shiv Sarovar Wing B's builder has filed on MahaRERA, the official one, is 1 September 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shiv Sarovar Wing B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shiv Sarovar Wing B in Belavali, Badlapur West, Thane is P51700079043.

Is Shiv Sarovar Wing B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B is registered as P51700079043 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shiv Sarovar Wing B? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHIV SAROVAR WING B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shiv Sarovar Wing B have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shiv Sarovar Wing B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B is registered on MahaRERA as P51700079043, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shiv Sarovar Wing B?

Shiv Sarovar Wing B isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shiv Sarovar Wing B?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shiv Sarovar Wing B: gharkundli.com/tools/property-cost-calculator

Has Shiv Sarovar Wing B received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 1 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shiv Sarovar Wing B?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (1 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shiv Sarovar Wing B uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shiv Sarovar Wing B was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Shiv Sarovar Wing B have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SHIV SAROVAR (P51700045969, possession 1 May 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Shiv Sarovar Wing B's possession date changes?

The latest dates are on Shiv Sarovar Wing B's MahaRERA page (P51700079043). GharKundli's Kundli Watch sends a free WhatsApp update on Shiv Sarovar Wing B every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shiv Sarovar Wing B have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B has one building filed: SHIV SAROVAR WING B with 8 floors and 14 units.

How much parking does Shiv Sarovar Wing B have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Shiv Sarovar Wing B.

How big is the land of Shiv Sarovar Wing B?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B stands on 380 sq m of land (about 0.1 acres), with 651 sq m of sanctioned built-up area.

What is the track record of Shiv Sarovar Wing B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Mahesh Bharat Divnale has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shiv Sarovar Wing B?

Google Maps has reviews of Shiv Sarovar Wing B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shiv Sarovar Wing B?

Shiv Sarovar Wing B by MAHESH BHARAT DIVNALE is in Belavali, Badlapur West, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700079043, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 95, HISSA NO. 1A & 1V. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Shiv Sarovar Wing B, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B has 14 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.

When was Shiv Sarovar Wing B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Sarovar Wing B was registered on MahaRERA on 31 January 2025. GharKundli did not find a title report on the land on file there.

Does Shiv Sarovar Wing B have any legal issues or court cases?

No court cases are listed for Shiv Sarovar Wing B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shiv Sarovar Wing B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAHESH BHARAT DIVNALE, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Ambarnath

All 938 projects in Kulgaon (421503) →

Other projects by MAHESH BHARAT DIVNALE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.