by JAK INFRATECH · Bhayandar East, ThaneAlso near Mira Road East, Goddev, Borivali West

Possession date of JAK NAMAHA: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700079398, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about JAK NAMAHA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of JAK NAMAHA has moved

  1. 30 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: JAK NAMAHA’s extension records on MahaRERA (P51700079398), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JAK NAMAHA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700079398
Status
Registered and active
Builder
JAK INFRATECH
Location
Bhayandar East, Thane · 401105
Project type
Residential / Group Housing
Registered on
3 Mar 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
121
Sold or booked
61%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of JAK NAMAHA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING B100%11%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING B: covers FULL CC FROM STILT TO 26TH FLOOR

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JAK NAMAHA every month.

JAK NAMAHA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of JAK NAMAHA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JAK NAMAHA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about JAK NAMAHA

What is the possession date of JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JAK NAMAHA in Bhayandar East, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for JAK NAMAHA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JAK NAMAHA's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JAK NAMAHA in Bhayandar East, Thane is P51700079398.

Is JAK NAMAHA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA is registered as P51700079398 and its status is "Registered and active".

What is the construction status of JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING B is 11% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does JAK NAMAHA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is JAK NAMAHA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA is registered on MahaRERA as P51700079398, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if JAK NAMAHA's possession date changes?

The latest dates are on JAK NAMAHA's MahaRERA page (P51700079398). GharKundli's Kundli Watch sends a free WhatsApp update on JAK NAMAHA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JAK NAMAHA have?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA has one building filed: WING B with 27 floors and 121 units.

How much parking does JAK NAMAHA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 54 covered car parking spaces for JAK NAMAHA.

How big is the land of JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA stands on 1,531 sq m of land (about 0.4 acres), with 9,215 sq m of sanctioned built-up area and 267 sq m of recreational open space.

Where can I read reviews of JAK NAMAHA?

Google Maps has reviews of JAK NAMAHA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is JAK NAMAHA?

JAK NAMAHA by JAK INFRATECH is in Bhayandar East, Thane (pincode 401105), near Mira Road East, Goddev, Borivali West, Maharashtra, and is registered on MahaRERA as P51700079398, per GharKundli's check of MahaRERA records.

How many homes are in JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA has 121 homes in 1 tower registered on MahaRERA, and 61% of them are sold or booked.

When was JAK NAMAHA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAK NAMAHA was registered on MahaRERA on 3 March 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on JAK NAMAHA?

No court cases are listed for JAK NAMAHA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of JAK NAMAHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAK INFRATECH.

All projects with possession due in 2029 in Palghar →

Other projects in pincode 401105

All 99 projects in Bhayander East (401105) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.