ANNAPURNA ARIES
by M/s. DWIVEDI CONSTRUCTION · Miraroad East, ThaneAlso near Mira Road East, Bhayander East, Navghar Village
Possession date of ANNAPURNA ARIES: 8 August 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700079820, and currently active. Its completion date is now August 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANNAPURNA ARIES?
How the possession date of ANNAPURNA ARIES has moved
8 April 2031
Completion date given when the project was registered
8 August 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ANNAPURNA ARIES’s extension records on MahaRERA (P51700079820), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANNAPURNA ARIES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the August 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700079820
- Status
- Registered and active
- Builder
- M/s. DWIVEDI CONSTRUCTION
- Location
- Miraroad East, Thane · 401105
- Project type
- Residential / Group Housing
- Registered on
- 27 Mar 2025
- Completion date at registration
- April 2031
- Latest completion date
- August 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 61
- Sold or booked
- 39%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ANNAPURNA ARIES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANNAPURNA ARISE - B WING | 100% | 15% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ANNAPURNA ARISE - B WING: covers 17 FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANNAPURNA ARIES every month.
ANNAPURNA ARIES: buildings, flats and land, as filed on MahaRERA
- Buildings: ANNAPURNA ARISE - B WING (21 floors, 61 units)
- Car parking: 64 covered, 31 open
- Land: 1,238 sq m (about 0.3 acres) · sanctioned built-up 5,630 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ANNAPURNA ARIES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANNAPURNA ARIES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANNAPURNA ARIES
What is the possession date of ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANNAPURNA ARIES in Miraroad East, Thane is 8 August 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ANNAPURNA ARIES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANNAPURNA ARIES's builder has filed on MahaRERA, the official one, is 8 August 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANNAPURNA ARIES in Miraroad East, Thane is P51700079820.
Is ANNAPURNA ARIES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES is registered as P51700079820 and its status is "Registered and active".
What is the construction status of ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANNAPURNA ARISE - B WING is 15% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ANNAPURNA ARIES have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANNAPURNA ARIES safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES is registered on MahaRERA as P51700079820, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANNAPURNA ARIES's possession date changes?
The latest dates are on ANNAPURNA ARIES's MahaRERA page (P51700079820). GharKundli's Kundli Watch sends a free WhatsApp update on ANNAPURNA ARIES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANNAPURNA ARIES have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES has one building filed: ANNAPURNA ARISE - B WING with 21 floors and 61 units.
How much parking does ANNAPURNA ARIES have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 64 covered and 31 open car parking spaces for ANNAPURNA ARIES.
How big is the land of ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES stands on 1,238 sq m of land (about 0.3 acres), with 5,630 sq m of sanctioned built-up area.
Where can I read reviews of ANNAPURNA ARIES?
Google Maps has reviews of ANNAPURNA ARIES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANNAPURNA ARIES?
ANNAPURNA ARIES by M/s. DWIVEDI CONSTRUCTION is in Miraroad East, Thane (pincode 401105), near Mira Road East, Bhayander East, Navghar Village, Maharashtra, and is registered on MahaRERA as P51700079820, per GharKundli's check of MahaRERA records.
How many homes are in ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES has 61 homes in 1 tower registered on MahaRERA, and 39% of them are sold or booked.
When was ANNAPURNA ARIES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANNAPURNA ARIES was registered on MahaRERA on 27 March 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on ANNAPURNA ARIES?
No court cases are listed for ANNAPURNA ARIES on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ANNAPURNA ARIES?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. DWIVEDI CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of ANNAPURNA ARIES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Palghar →
Other projects in Thane
- EMAAR HEIGHT
- SHANTI HOUSE
- SHANTI SEVEN
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- MAULI KRUPA
- GURUKRUPA NITYAM
- ASAVARI CO OP HSG SOC LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.