Shiv-Vista Homes
by Prakash Bhimrao Baviskar · Vasind, Thane 421601
What’s in the report? →Possession date of Shiv-Vista Homes (MahaRERA P51700080407): 30 April 2030. It has 164 homes, 1% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700080407, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700080407, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shiv-Vista Homes?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shiv-Vista Homes has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shiv-Vista Homes’s extension records on MahaRERA (P51700080407), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shiv-Vista Homes
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700080407
- Status
- Registered and active
- Builder
- Prakash Bhimrao Baviskar
- Location
- Vasind, Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 2 Jun 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 164
- Sold or booked
- 1%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shiv-Vista Homes, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 wing A B C | 66% | 11.235% | 1.4% | 0% |
| Building No 2 | 60% | 0% | 0% | 0% |
| Building No 3 | 0% | 0% | 0% | 0% |
| Hospital Building | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1 wing A B C: covers 13 floors
- Building No 2: covers 8 floors
- Building No 3: covers 2 floors
- Hospital Building: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shiv-Vista Homes every 1–2 months.
Shiv-Vista Homes: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1 wing A B C (14 floors, 132 units) · Building No 2 (9 floors, 28 units) · Building No 3 (3 floors, 4 units) · Hospital Building (4 floors, 1 units)
- Car parking: 54 covered, 15 open
- Land: 6,200 sq m (about 1.5 acres) · sanctioned built-up 13,387 sq m · recreational space 648 sq m
- Land, as filed: 118-5-A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shiv-Vista Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shiv-Vista Homes: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shiv-Vista Homes
What is the possession date of Shiv-Vista Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shiv-Vista Homes in Vasind, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shiv-Vista Homes?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shiv-Vista Homes's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shiv-Vista Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shiv-Vista Homes in Vasind, Thane is P51700080407.
Is Shiv-Vista Homes registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes is registered as P51700080407 and its status is "Registered and active".
What is the current construction status of Shiv-Vista Homes? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 11.235% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Shiv-Vista Homes have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shiv-Vista Homes safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes is registered on MahaRERA as P51700080407, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shiv-Vista Homes?
Shiv-Vista Homes is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shiv-Vista Homes?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shiv-Vista Homes: gharkundli.com/tools/property-cost-calculator
Has Shiv-Vista Homes received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shiv-Vista Homes uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shiv-Vista Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shiv-Vista Homes's possession date changes?
The latest dates are on Shiv-Vista Homes's MahaRERA page (P51700080407). GharKundli's Kundli Watch sends a free WhatsApp update on Shiv-Vista Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shiv-Vista Homes have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes has 4 buildings filed: Building No 1 wing A B C with 14 floors and 132 units; Building No 2 with 9 floors and 28 units; Building No 3 with 3 floors and 4 units; Hospital Building with 4 floors and 1 units.
How much parking does Shiv-Vista Homes have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 54 covered and 15 open car parking spaces for Shiv-Vista Homes.
How big is the land of Shiv-Vista Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes stands on 6,200 sq m of land (about 1.5 acres), with 13,387 sq m of sanctioned built-up area and 648 sq m of recreational open space.
What are the reviews of Shiv-Vista Homes?
Google Maps has reviews of Shiv-Vista Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shiv-Vista Homes?
Shiv-Vista Homes by Prakash Bhimrao Baviskar is in Vasind, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700080407, per GharKundli's check of MahaRERA records. Its land is filed as 118-5-A. GharKundli lists all 184 MahaRERA projects in Shahapur (421601).
How many flats are in Shiv-Vista Homes, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes has 164 homes in 4 towers registered on MahaRERA, and 1% of them are sold or booked.
When was Shiv-Vista Homes registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv-Vista Homes was registered on MahaRERA on 2 June 2025. GharKundli did not find a title report on the land on file there.
Does Shiv-Vista Homes have any legal issues or court cases?
No court cases are listed for Shiv-Vista Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shiv-Vista Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Prakash Bhimrao Baviskar.
Check it yourself on MahaRERA
- How to check the possession date of Shiv-Vista Homes
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Shahapur (421601)
- Sai Anand Apartment
- Mirador Utsav Phase 1
- Visava
- Chintamani Habitat (Fortuna Bungalow)
- Chintamani Meadows
- Icon Apartment
- Pitruchhaya Apartment
- Aghav Resideny
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.