Satej Premises Co-operative Society Limited
by Ojass Govind Infra LLP · Panchpakhadi, Thane
Possession date of Satej Premises Co-operative Society Limited: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1330002501164, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Satej Premises Co-operative Society Limited?
How the possession date of Satej Premises Co-operative Society Limited has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Satej Premises Co-operative Society Limited’s extension records on MahaRERA (PM1330002501164), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Satej Premises Co-operative Society Limited
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1330002501164
- Status
- Registered and active
- Builder
- Ojass Govind Infra LLP
- Location
- Panchpakhadi, Thane · 400602
- Project type
- Mixed
- Registered on
- 9 Oct 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 35
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Satej Premises Co-operative Society Limited, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Satej Premises Co-Operative Society Limited | 100% | 26.66% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Satej Premises Co-Operative Society Limited: covers 15 floors
Latest CC order on MahaRERA: dated 09/05/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Satej Premises Co-operative Society Limited every month.
Satej Premises Co-operative Society Limited: buildings, flats and land, as filed on MahaRERA
- Buildings: Satej Premises Co-Operative Society Limited (15 floors, 52 units)
- Car parking: 36 covered
- Land: 945 sq m (about 0.2 acres) · sanctioned built-up 3,503 sq m
The builder’s record and reviews
Ojass Govind Infra (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 15 GharKundli has checked: 7 finished, all within the promised date; 8 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Satej Premises Co-operative Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Satej Premises Co-operative Society Limited: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Satej Premises Co-operative Society Limited
What is the possession date of Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Satej Premises Co-operative Society Limited in Panchpakhadi, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Satej Premises Co-operative Society Limited?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Satej Premises Co-operative Society Limited's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Satej Premises Co-operative Society Limited in Panchpakhadi, Thane is PM1330002501164.
Is Satej Premises Co-operative Society Limited registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited is registered as PM1330002501164 and its status is "Registered and active".
What is the construction status of Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Satej Premises Co-Operative Society Limited is 26.66% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Satej Premises Co-operative Society Limited have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Satej Premises Co-operative Society Limited safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited is registered on MahaRERA as PM1330002501164, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Satej Premises Co-operative Society Limited's possession date changes?
The latest dates are on Satej Premises Co-operative Society Limited's MahaRERA page (PM1330002501164). GharKundli's Kundli Watch sends a free WhatsApp update on Satej Premises Co-operative Society Limited every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Satej Premises Co-operative Society Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited has one building filed: Satej Premises Co-Operative Society Limited with 15 floors and 52 units.
How much parking does Satej Premises Co-operative Society Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for Satej Premises Co-operative Society Limited.
How big is the land of Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited stands on 945 sq m of land (about 0.2 acres), with 3,503 sq m of sanctioned built-up area.
What is the track record of Satej Premises Co-operative Society Limited's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojass Govind Infra (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 15 GharKundli has checked: 7 finished, all within the promised date; 8 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Satej Premises Co-operative Society Limited?
Google Maps has reviews of Satej Premises Co-operative Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Satej Premises Co-operative Society Limited?
Satej Premises Co-operative Society Limited by Ojass Govind Infra LLP is in Panchpakhadi, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as PM1330002501164, per GharKundli's check of MahaRERA records.
How many homes are in Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited has 35 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was Satej Premises Co-operative Society Limited registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Satej Premises Co-operative Society Limited was registered on MahaRERA on 9 October 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on Satej Premises Co-operative Society Limited?
No court cases are listed for Satej Premises Co-operative Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Satej Premises Co-operative Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ojass Govind Infra LLP, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Satej Premises Co-operative Society Limited
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Thane
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- Centurion
- Panache
- Mahavir Breeze Phase 1
- LOTUS
Other projects by Ojass Govind Infra LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.