Possession date of Dream Pragati (MahaRERA PR1330002500598): 30 April 2029. It has 71 homes, 21% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1330002500598, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1330002500598, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Dream Pragati?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Dream Pragati has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Dream Pragati’s extension records on MahaRERA (PR1330002500598), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dream Pragati

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1330002500598
Status
Registered and active
Builder
Empire Horizons Private Limited
Location
Naupada S.O (Thane), Thane · 400602
Project type
Residential / Group Housing
Registered on
18 Aug 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
71
Sold or booked
21%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Dream Pragati, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PRAGATI COOPERATIVE HOUSING SOCIETY LIMITED (Residential)0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PRAGATI COOPERATIVE HOUSING SOCIETY LIMITED (Residential): covers 17 floors

Latest CC order on MahaRERA: dated 08/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dream Pragati every 1–2 months.

Dream Pragati: buildings, flats and land, as filed on MahaRERA

  • Buildings: PRAGATI COOPERATIVE HOUSING SOCIETY LIMITED (Residential) (17 floors, 71 units)
  • Car parking: 117 covered
  • Land: 1,808 sq m (about 0.4 acres) · sanctioned built-up 6,728 sq m
  • Boundaries filed include: Kacharali Lake, Dharmaveer Marg
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Dream Realtors (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 5 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Dream Pragati →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dream Pragati: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dream Pragati

What is the possession date of Dream Pragati?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Dream Pragati in Naupada S.O (Thane), Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Dream Pragati?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dream Pragati's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Dream Pragati?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Dream Pragati in Naupada S.O (Thane), Thane is PR1330002500598.

Is Dream Pragati registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati is registered as PR1330002500598 and its status is "Registered and active".

What is the current construction status of Dream Pragati? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRAGATI COOPERATIVE HOUSING SOCIETY LIMITED (Residential) is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Dream Pragati have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Dream Pragati safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati is registered on MahaRERA as PR1330002500598, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dream Pragati?

Dream Pragati is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Dream Pragati?

For a flat in Dream Pragati (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Dream Pragati received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Dream Pragati a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati is a redevelopment: 33 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Dream Pragati uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Dream Pragati was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Dream Pragati's possession date changes?

The latest dates are on Dream Pragati's MahaRERA page (PR1330002500598). GharKundli's Kundli Watch sends a free WhatsApp update on Dream Pragati every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dream Pragati have?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati has one building filed: PRAGATI COOPERATIVE HOUSING SOCIETY LIMITED (Residential) with 17 floors and 71 units.

How much parking does Dream Pragati have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 117 covered car parking spaces for Dream Pragati.

How big is the land of Dream Pragati?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati stands on 1,808 sq m of land (about 0.4 acres), with 6,728 sq m of sanctioned built-up area.

What is the track record of Dream Pragati's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Realtors (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 5 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Dream Pragati?

Google Maps has reviews of Dream Pragati written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dream Pragati?

Dream Pragati by Empire Horizons Private Limited (Dream) is in Naupada S.O (Thane), Thane, pincode 400602 (near Panchpakhadi, Thane West, Charai), Maharashtra, and is registered on MahaRERA as PR1330002500598, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kacharali Lake, Dharmaveer Marg. GharKundli lists all 258 MahaRERA projects in Naupada (400602).

How many flats are in Dream Pragati, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati has 71 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.

When was Dream Pragati registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dream Pragati was registered on MahaRERA on 18 August 2025. GharKundli did not find a title report on the land on file there.

Does Dream Pragati have any legal issues or court cases?

No court cases are listed for Dream Pragati on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Dream Pragati?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Empire Horizons Private Limited, the company Dream files this project under.

All projects with possession due in 2029 in Thane →

Other projects in Naupada (400602)

All 258 projects in Naupada (400602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.