Vikas Palazzo

by DURATECH · Mulund West, Mumbai 400080Also near Mulund East, Bhandup West, Off Dmart

What’s in the report? →

Possession date of Vikas Palazzo (MahaRERA P51800001960): 30 March 2028, moved from 31 May 2020 (90 months later). It has 53 homes (4 BHK and Duplex, 2049–9567 sq ft carpet), 80% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800001960, and currently active. Its completion date has moved from May 2020 to March 2028: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800001960, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vikas Palazzo?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vikas Palazzo has moved

  1. 31 May 2020

    Completion date given when the project was registered

  2. 31 May 2021

    Extended at the builder's request (MahaRERA application EXT51800005512)

    Reason the builder gave MahaRERA: “Due to DCPR 2034, there is availability of additional FSI of 1685.53 sq. mtrs. and as a result of which now total proposed FSI will be increased from 12,593.48 sq. mtrs. to 14,279.01 sq. mtrs. (i.e. additional 1685.53 sq. mtrs.).”
  3. 30 May 2023

    Extended at the builder's request (MahaRERA application EXT51800011853)

    Reason the builder gave MahaRERA: “We have received part Occupation Certificates till 38th floor and further to complete the internal unfinished work for 39th and 40th floor we request for extension for the said project for one year i.e 30/05/2023.”
  4. 30 November 2023

    Extended at the builder's request (MahaRERA application EXT51800016483)

    Reason the builder gave MahaRERA:
    “we have completed the project as per architect certificate we have OC till 38th floor but we are in process of getting full OC , hence we require a extension for further 6 months. we have attached possession letters as annexures to the lett…” Read the full reason“we have completed the project as per architect certificate we have OC till 38th floor but we are in process of getting full OC , hence we require a extension for further 6 months. we have attached possession letters as annexures to the letter”
  5. 30 November 2024

    Extended at the builder's request (MahaRERA application EXT51800017842)

    Reason the builder gave MahaRERA: “We have received OC till 38 th floor and we are in process of obtaining the full oc up to 40 floor till that time we request you grant the extension till 30.11.2024”
  6. 30 November 2025

    Extended at the builder's request (MahaRERA application EXT51800024941)

    Reason the builder gave MahaRERA:
    “We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC up…” Read the full reason“We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2025, we have attached the consent letter of all the allottees.”
  7. 30 November 2027

    Extended at the builder's request (MahaRERA application EA13112518322)

    Reason the builder gave MahaRERA:
    “We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC up…” Read the full reason“We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2027, we have attached the consent letter of 80%of the allottees.”
  8. 30 March 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vikas Palazzo’s extension records on MahaRERA (P51800001960), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vikas Palazzo

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001960
Status
Registered and active
Builder
DURATECH
Location
Mulund West, Mumbai · 400080
Project type
Others
Registered on
31 Jul 2017
Completion date at registration
May 2020
Latest completion date
March 2028
Delay so far
90 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
53
Sold or booked
80%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Vikas Palazzo, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VIKAS PALAZZO100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • VIKAS PALAZZO: covers 43 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vikas Palazzo every 1–2 months.

Vikas Palazzo: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
4 BHK2,049 – 3,09046
Other3,090 – 5,0174
Shops1,040 – 2,3243
Duplex2,205 – 9,5673
  • Buildings: VIKAS PALAZZO (43 floors, 56 units)
  • Land: 3,111 sq m (about 0.8 acres) · sanctioned built-up 14,280 sq m · recreational space 622 sq m
  • Boundaries filed include: JAWAHARLAL NEHRU ROAD, WALJI LADHA ROAD, KASTURBA ROAD
  • Land, as filed: 1348A AND 1348B
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Duratech (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 2 past the promised date (typically 40 months late). No complaints on MahaRERA.

Read Google reviews of Vikas Palazzo →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vikas Palazzo: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vikas Palazzo

What is the possession date of Vikas Palazzo?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vikas Palazzo in Mulund West, Mumbai is 30 March 2028 — 90 months later than 31 May 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 90 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vikas Palazzo?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vikas Palazzo's builder has filed on MahaRERA, the official one, is 30 March 2028, already 90 months later than the 31 May 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vikas Palazzo extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo's builder applied to MahaRERA to extend the completion date 6 times: to 31 May 2021, giving the reason "Due to DCPR 2034, there is availability of additional FSI of 1685.53 sq. mtrs. and as a result of which now total proposed FSI will be increased from 12,593.48 sq. mtrs. to 14,279.01 sq. mtrs. (i.e. additional 1685.53 sq. mtrs.)."; to 30 May 2023, giving the reason "We have received part Occupation Certificates till 38th floor and further to complete the internal unfinished work for 39th and 40th floor we request for extension for the said project for one year i.e 30/05/2023."; to 30 November 2023, giving the reason "we have completed the project as per architect certificate we have OC till 38th floor but we are in process of getting full OC , hence we require a extension for further 6 months. we have attached possession letters as annexures to the letter"; to 30 November 2024, giving the reason "We have received OC till 38 th floor and we are in process of obtaining the full oc up to 40 floor till that time we request you grant the extension till 30.11.2024"; to 30 November 2025, giving the reason "We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2025, we have attached the consent letter of all the allottees."; to 30 November 2027, giving the reason "We have completed construction of full building and 100% work is completed as per architect certificate form 2 AND we have uploaded the CPM pert Chart showing 100% work completion and no balance work . , we have also received the part OC upto 38th floor and we are in process for getting the full occupation certificate hence we request you to provide the Extension upto 30/11/2027, we have attached the consent letter of 80%of the allottees.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vikas Palazzo?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vikas Palazzo in Mulund West, Mumbai is P51800001960.

Is Vikas Palazzo registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo is registered as P51800001960 and its status is "Registered and active".

What is the current construction status of Vikas Palazzo? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VIKAS PALAZZO is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vikas Palazzo have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vikas Palazzo safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo is registered on MahaRERA as P51800001960, its completion date has moved 90 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vikas Palazzo?

Vikas Palazzo is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Vikas Palazzo start at 2049 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vikas Palazzo?

For a flat in Vikas Palazzo (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vikas Palazzo received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo is still under construction, with 30 March 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vikas Palazzo uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vikas Palazzo was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vikas Palazzo's possession date changes?

The latest dates are on Vikas Palazzo's MahaRERA page (P51800001960). GharKundli's Kundli Watch sends a free WhatsApp update on Vikas Palazzo every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vikas Palazzo have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo has one building filed: VIKAS PALAZZO with 43 floors and 56 units.

What are the flat sizes (carpet area) in Vikas Palazzo?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vikas Palazzo: 4 BHK: 2049 to 3090 sq ft carpet (46 homes); Other: 3090 to 5017 sq ft carpet (4 homes); Duplex: 2205 to 9567 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Vikas Palazzo?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo stands on 3,111 sq m of land (about 0.8 acres), with 14,280 sq m of sanctioned built-up area and 622 sq m of recreational open space.

What is the track record of Vikas Palazzo's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Duratech (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 still being built, 2 past the promised date (typically 40 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vikas Palazzo?

Google Maps has reviews of Vikas Palazzo written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vikas Palazzo?

Vikas Palazzo by DURATECH is in Mulund West, Mumbai, pincode 400080 (near Mulund East, Bhandup West, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800001960, per GharKundli's check of MahaRERA records. Its boundaries filed there include JAWAHARLAL NEHRU ROAD, WALJI LADHA ROAD, KASTURBA ROAD. Its land is filed as 1348A AND 1348B. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

How many flats are in Vikas Palazzo, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo has 53 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.

When was Vikas Palazzo registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Palazzo was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Does Vikas Palazzo have any legal issues or court cases?

No court cases are listed for Vikas Palazzo on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vikas Palazzo?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DURATECH, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Other projects by DURATECH

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.