SRUSHTIRAJ TOWER
by CHINNAIAH VENKATESH GOWDA · Tilak Nagar, MumbaiAlso near Chembur, Vikhroli East, Ghatkopar West
Possession date of SRUSHTIRAJ TOWER: 25 April 2027, moved from 22 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800009157, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 15 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SRUSHTIRAJ TOWER?
How the possession date of SRUSHTIRAJ TOWER has moved
22 December 2022
Completion date given when the project was registered
22 December 2023
Extended at the builder's request (MahaRERA application EXT51800012182)
Reason the builder gave MahaRERA:
“We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project…” Read the full reason
“We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project under section 6 of Real Estate (Regulation and Development Act, 2016)”25 December 2025
Extended at the builder's request (MahaRERA application EXT51800018173)
Reason the builder gave MahaRERA: “Delay due to pandemic affects and new guidelines from BMC for pollution control which are resulting in expenses unaccounted for and therefore need more time to mitigate.”
25 December 2026
Extended at the builder's request (MahaRERA application EA25122519003)
Reason the builder gave MahaRERA:
“Material Sourcing became difficult, Labour sourcing and management did not happen properly cause of work stalling due to heavy rains through out the year. The work is 80 percent complete and the balance shall be completed within the coming…” Read the full reason
“Material Sourcing became difficult, Labour sourcing and management did not happen properly cause of work stalling due to heavy rains through out the year. The work is 80 percent complete and the balance shall be completed within the coming year.”25 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SRUSHTIRAJ TOWER’s extension records on MahaRERA (P51800009157), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SRUSHTIRAJ TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 15 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009157
- Status
- Registered and active
- Builder
- CHINNAIAH VENKATESH GOWDA
- Location
- Tilak Nagar, Mumbai · 400089
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 125
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 15
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of SRUSHTIRAJ TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TILAK NAGAR SHANKAR CHHAYA CHS LTD | 100% | 80% | 80% | 20% |
Commencement certificate (CC), as filed on MahaRERA
- TILAK NAGAR SHANKAR CHHAYA CHS LTD: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SRUSHTIRAJ TOWER every month.
SRUSHTIRAJ TOWER: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 421 – 587 | 108 |
| 1 BHK | 410 – 445 | 17 |
- Buildings: TILAK NAGAR SHANKAR CHHAYA CHS LTD (17 floors, 125 units)
- Land: 945 sq m (about 0.2 acres) · sanctioned built-up 3,159 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Chinnaiah Venkatesh Gowda has 9 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 30 months late). 32 complaints on MahaRERA across 2 projects.
Read Google reviews of SRUSHTIRAJ TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SRUSHTIRAJ TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SRUSHTIRAJ TOWER
What is the possession date of SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SRUSHTIRAJ TOWER in Tilak Nagar, Mumbai is 25 April 2027 — 48 months later than 22 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SRUSHTIRAJ TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SRUSHTIRAJ TOWER's builder has filed on MahaRERA, the official one, is 25 April 2027, already 48 months later than the 22 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SRUSHTIRAJ TOWER extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER's builder applied to MahaRERA to extend the completion date 3 times: to 22 December 2023, giving the reason "We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project under section 6 of Real Estate (Regulation and Development Act, 2016)"; to 25 December 2025, giving the reason "Delay due to pandemic affects and new guidelines from BMC for pollution control which are resulting in expenses unaccounted for and therefore need more time to mitigate."; to 25 December 2026, giving the reason "Material Sourcing became difficult, Labour sourcing and management did not happen properly cause of work stalling due to heavy rains through out the year. The work is 80 percent complete and the balance shall be completed within the coming year.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SRUSHTIRAJ TOWER in Tilak Nagar, Mumbai is P51800009157.
Is SRUSHTIRAJ TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER is registered as P51800009157 and its status is "Registered and active".
What is the construction status of SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TILAK NAGAR SHANKAR CHHAYA CHS LTD is 80% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does SRUSHTIRAJ TOWER have complaints on MahaRERA?
15 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SRUSHTIRAJ TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER is registered on MahaRERA as P51800009157, its completion date has moved 48 months since registration and 15 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SRUSHTIRAJ TOWER's possession date changes?
The latest dates are on SRUSHTIRAJ TOWER's MahaRERA page (P51800009157). GharKundli's Kundli Watch sends a free WhatsApp update on SRUSHTIRAJ TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SRUSHTIRAJ TOWER have?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER has one building filed: TILAK NAGAR SHANKAR CHHAYA CHS LTD with 17 floors and 125 units.
What are the flat sizes (carpet area) in SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SRUSHTIRAJ TOWER: 2 BHK: 421 to 587 sq ft carpet (108 homes); 1 BHK: 410 to 445 sq ft carpet (17 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER stands on 945 sq m of land (about 0.2 acres), with 3,159 sq m of sanctioned built-up area.
What is the track record of SRUSHTIRAJ TOWER's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Chinnaiah Venkatesh Gowda has 9 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 30 months late). 32 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SRUSHTIRAJ TOWER?
Google Maps has reviews of SRUSHTIRAJ TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 15 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SRUSHTIRAJ TOWER?
SRUSHTIRAJ TOWER by CHINNAIAH VENKATESH GOWDA is in Tilak Nagar, Mumbai (pincode 400089), near Chembur, Vikhroli East, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800009157, per GharKundli's check of MahaRERA records.
How many homes are in SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER has 125 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was SRUSHTIRAJ TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SRUSHTIRAJ TOWER was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SRUSHTIRAJ TOWER?
No court cases are listed for SRUSHTIRAJ TOWER on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SRUSHTIRAJ TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHINNAIAH VENKATESH GOWDA, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SRUSHTIRAJ TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400089
All 75 projects in Chembur (400089) →Other projects by CHINNAIAH VENKATESH GOWDA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.