by CHINNAIAH VENKATESH GOWDA · Tilak Nagar, MumbaiAlso near Chembur, Ghatkopar East, Ghatkopar West

Possession date of Srushti Raj Siddhi: 25 April 2028, moved from 25 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002790, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 17 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Srushti Raj Siddhi?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Srushti Raj Siddhi has moved

  1. 25 December 2022

    Completion date given when the project was registered

  2. 25 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012183)

    Reason the builder gave MahaRERA:
    “We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project…” Read the full reason“We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project under section 6 of Real Estate (Regulation and Development Act, 2016)”
  3. 25 December 2025

    Extended at the builder's request (MahaRERA application EXT51800018122)

    Reason the builder gave MahaRERA: “Delay due to pandemic affects and new guidelines from BMC for pollution control which are resulting in expenses unaccounted for and therefore need more time to mitigate.”
  4. 25 December 2027

    Extended at the builder's request (MahaRERA application EA25122519004)

    Reason the builder gave MahaRERA:
    “Due to materialsourcing difficulty, Labour team deficiency resulting from continuous rain through out the year which restricted construction. The project is 70 percent completed and the balance shall be completed within the proposed timelin…” Read the full reason“Due to materialsourcing difficulty, Labour team deficiency resulting from continuous rain through out the year which restricted construction. The project is 70 percent completed and the balance shall be completed within the proposed timeline”
  5. 25 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Srushti Raj Siddhi’s extension records on MahaRERA (P51800002790), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Srushti Raj Siddhi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 17 complaints, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002790
Status
Registered and active
Builder
CHINNAIAH VENKATESH GOWDA
Location
Tilak Nagar, Mumbai · 400089
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
December 2022
Latest completion date
April 2028
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
133
Sold or booked
91%
Towers
1
Complaints on MahaRERA
17
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Srushti Raj Siddhi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Srushtiraj Siddhi A and B Wing100%53%50%25%

Commencement certificate (CC), as filed on MahaRERA

  • Srushtiraj Siddhi A and B Wing: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Srushti Raj Siddhi every month.

Srushti Raj Siddhi: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK522 – 589115
1 BHK380 – 52418

The builder’s record and reviews

Chinnaiah Venkatesh Gowda has 9 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 30 months late). 32 complaints on MahaRERA across 2 projects.

Read Google reviews of Srushti Raj Siddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Srushti Raj Siddhi: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Srushti Raj Siddhi

What is the possession date of Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Srushti Raj Siddhi in Tilak Nagar, Mumbai is 25 April 2028 — 60 months later than 25 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Srushti Raj Siddhi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Srushti Raj Siddhi's builder has filed on MahaRERA, the official one, is 25 April 2028, already 60 months later than the 25 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Srushti Raj Siddhi extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi's builder applied to MahaRERA to extend the completion date 3 times: to 25 December 2023, giving the reason "We could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project under section 6 of Real Estate (Regulation and Development Act, 2016)"; to 25 December 2025, giving the reason "Delay due to pandemic affects and new guidelines from BMC for pollution control which are resulting in expenses unaccounted for and therefore need more time to mitigate."; to 25 December 2027, giving the reason "Due to materialsourcing difficulty, Labour team deficiency resulting from continuous rain through out the year which restricted construction. The project is 70 percent completed and the balance shall be completed within the proposed timeline". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Srushti Raj Siddhi in Tilak Nagar, Mumbai is P51800002790.

Is Srushti Raj Siddhi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi is registered as P51800002790 and its status is "Registered and active".

What is the construction status of Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Srushtiraj Siddhi A and B Wing is 53% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Srushti Raj Siddhi have complaints on MahaRERA?

17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Srushti Raj Siddhi safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi is registered on MahaRERA as P51800002790, its completion date has moved 60 months since registration and 17 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Srushti Raj Siddhi's possession date changes?

The latest dates are on Srushti Raj Siddhi's MahaRERA page (P51800002790). GharKundli's Kundli Watch sends a free WhatsApp update on Srushti Raj Siddhi every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Srushti Raj Siddhi have?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi has one building filed: Srushtiraj Siddhi A and B Wing with 18 floors and 133 units.

What are the flat sizes (carpet area) in Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Srushti Raj Siddhi: 2 BHK: 522 to 589 sq ft carpet (115 homes); 1 BHK: 380 to 524 sq ft carpet (18 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi stands on 1,201 sq m of land (about 0.3 acres), with 6,066 sq m of sanctioned built-up area.

What is the track record of Srushti Raj Siddhi's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Chinnaiah Venkatesh Gowda has 9 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 30 months late). 32 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Srushti Raj Siddhi?

Google Maps has reviews of Srushti Raj Siddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Srushti Raj Siddhi?

Srushti Raj Siddhi by CHINNAIAH VENKATESH GOWDA is in Tilak Nagar, Mumbai (pincode 400089), near Chembur, Ghatkopar East, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800002790, per GharKundli's check of MahaRERA records.

How many homes are in Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi has 133 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was Srushti Raj Siddhi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Raj Siddhi was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Srushti Raj Siddhi?

No court cases are listed for Srushti Raj Siddhi on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Srushti Raj Siddhi?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHINNAIAH VENKATESH GOWDA, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400089

All 75 projects in Chembur (400089) →

Other projects by CHINNAIAH VENKATESH GOWDA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.