by PRIYA CONSTRUCTIONS · Chembur, MumbaiAlso near Tilak Nagar, Vikhroli East, Ghatkopar West

Possession date of JADE: 30 June 2027, moved from 30 June 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026869, and currently active. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about JADE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of JADE has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800016759)

    Reason the builder gave MahaRERA:
    “The construction of the project is delayed by one year due to stoppage in de-watering during the construction of basement. Even after receiving permission from the authority we were not allowed to do de-watering because of storm water drain…” Read the full reason“The construction of the project is delayed by one year due to stoppage in de-watering during the construction of basement. Even after receiving permission from the authority we were not allowed to do de-watering because of storm water drainage issue in the surrounding area.The existing storm water drainage is still under repairing stage and at regular intervals we have to stop construction at site due accumulation of ground water.”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA16022619849)

    Reason the builder gave MahaRERA: “As per order of the Hon'ble Chairman (MahaRERA) Dated 09/03/2026 we request you kindly to grant us extension till 10/04/2026”

Source: JADE’s extension records on MahaRERA (P51800026869), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JADE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800026869
Status
Registered and active
Builder
PRIYA CONSTRUCTIONS
Location
Chembur, Mumbai · 400089
Project type
Others
Registered on
31 Oct 2020
Completion date at registration
June 2024
Latest completion date
June 2027
Delay so far
36 months
Homes
173
Sold or booked
49%
Towers
1
Complaints on MahaRERA
8
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found

Construction progress of JADE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Jade100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Jade: covers Upto Plinth

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JADE every month.

JADE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK370 – 474142
2 BHK585 – 61031
Shops146 – 32523
  • Buildings: Jade (20 floors, 196 units)
  • Land: 7,673 sq m (about 1.9 acres) · sanctioned built-up 20,821 sq m · recreational space 2,614 sq m
  • Boundaries filed include: BSES Sub Station, Road and Indira Slum, Eastern Express Highway
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of JADE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JADE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about JADE

What is the possession date of JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JADE in Chembur, Mumbai is 30 June 2027 — 36 months later than 30 June 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for JADE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JADE's builder has filed on MahaRERA, the official one, is 30 June 2027, already 36 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of JADE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "The construction of the project is delayed by one year due to stoppage in de-watering during the construction of basement. Even after receiving permission from the authority we were not allowed to do de-watering because of storm water drainage issue in the surrounding area.The existing storm water drainage is still under repairing stage and at regular intervals we have to stop construction at site due accumulation of ground water."; to 30 June 2027, giving the reason "As per order of the Hon'ble Chairman (MahaRERA) Dated 09/03/2026 we request you kindly to grant us extension till 10/04/2026".

What is the RERA number of JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JADE in Chembur, Mumbai is P51800026869.

Is JADE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE is registered as P51800026869 and its status is "Registered and active".

What is the construction status of JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Jade is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does JADE have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is JADE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE is registered on MahaRERA as P51800026869, its completion date has moved 36 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if JADE's possession date changes?

The latest dates are on JADE's MahaRERA page (P51800026869). GharKundli's Kundli Watch sends a free WhatsApp update on JADE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JADE have?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE has one building filed: Jade with 20 floors and 196 units.

What are the flat sizes (carpet area) in JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for JADE: 1 BHK: 370 to 474 sq ft carpet (142 homes); 2 BHK: 585 to 610 sq ft carpet (31 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE stands on 7,673 sq m of land (about 1.9 acres), with 20,821 sq m of sanctioned built-up area and 2,614 sq m of recreational open space.

Where can I read reviews of JADE?

Google Maps has reviews of JADE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is JADE?

JADE by PRIYA CONSTRUCTIONS is in Chembur, Mumbai (pincode 400089), near Tilak Nagar, Vikhroli East, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800026869, per GharKundli's check of MahaRERA records. Its boundaries filed there include BSES Sub Station, Road and Indira Slum, Eastern Express Highway.

How many homes are in JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE has 173 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.

When was JADE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JADE was registered on MahaRERA on 31 October 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on JADE?

No court cases are listed for JADE on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of JADE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRIYA CONSTRUCTIONS.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400089

All 75 projects in Chembur (400089) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.