Poonam Chhaya CHSL
by VASTU VAIBHAV CREATIONS LLP · Naupada S.O (Thane), Thane 400602Also near Panchpakhadi, Thane West, Charai
What’s in the report? →Possession date of Poonam Chhaya CHSL (MahaRERA PR1330002501631): 30 April 2030, moved from 31 December 2026 (36 months later). It has 59 homes, 3% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002501631, and currently active. Its completion date has moved from December 2026 to April 2030: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for PR1330002501631, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Poonam Chhaya CHSL?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Poonam Chhaya CHSL has moved
31 December 2026
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA16052620987)
Reason the builder gave MahaRERA:
“We launched the project in 02/12/2025. The project is located at a prime location in thane. We misinterpreted and overlooked and gave due date that was falling within an year. Completion of the construction of the project within one year is…” Read the full reason
“We launched the project in 02/12/2025. The project is located at a prime location in thane. We misinterpreted and overlooked and gave due date that was falling within an year. Completion of the construction of the project within one year is not possible. The first year was consumed in completion of the plinth of the project and completion of the other formalities. The project is a redevelopment project. It may be noted that we have not sold any units in the project. The amount received as on 31.03.2026 is from the REHAB allottees, the amount received is against the extra area brought by the…”30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Poonam Chhaya CHSL’s extension records on MahaRERA (PR1330002501631), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Poonam Chhaya CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002501631
- Status
- Registered and active
- Builder
- VASTU VAIBHAV CREATIONS LLP
- Location
- Naupada S.O (Thane), Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 2 Dec 2025
- Completion date at registration
- December 2026
- Latest completion date
- April 2030
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 59
- Sold or booked
- 3%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Poonam Chhaya CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| POONAM CHHAYA CO OPERATIVE HOUSING SOCIETY LIMITED | 100% | 41% | 2.5% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- POONAM CHHAYA CO OPERATIVE HOUSING SOCIETY LIMITED: covers 15 floors
Latest CC order on MahaRERA: dated 27/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Poonam Chhaya CHSL every 1–2 months.
Poonam Chhaya CHSL: buildings, flats and land, as filed on MahaRERA
- Buildings: POONAM CHHAYA CO OPERATIVE HOUSING SOCIETY LIMITED (17 floors, 59 units)
- Car parking: 62 covered
- Land: 1,858 sq m (about 0.5 acres) · sanctioned built-up 6,416 sq m
- Boundaries filed include: OFF Madanlal Dhingra Road
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Poonam Chhaya CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Poonam Chhaya CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Poonam Chhaya CHSL
What is the possession date of Poonam Chhaya CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Poonam Chhaya CHSL in Naupada S.O (Thane), Thane is 30 April 2030 — 36 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Poonam Chhaya CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Poonam Chhaya CHSL's builder has filed on MahaRERA, the official one, is 30 April 2030, already 36 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Poonam Chhaya CHSL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "We launched the project in 02/12/2025. The project is located at a prime location in thane. We misinterpreted and overlooked and gave due date that was falling within an year. Completion of the construction of the project within one year is not possible. The first year was consumed in completion of the plinth of the project and completion of the other formalities. The project is a redevelopment project. It may be noted that we have not sold any units in the project. The amount received as on 31.03.2026 is from the REHAB allottees, the amount received is against the extra area brought by the…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Poonam Chhaya CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Poonam Chhaya CHSL in Naupada S.O (Thane), Thane is PR1330002501631.
Is Poonam Chhaya CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL is registered as PR1330002501631 and its status is "Registered and active".
What is the current construction status of Poonam Chhaya CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on POONAM CHHAYA CO OPERATIVE HOUSING SOCIETY LIMITED is 41% done and internal work 2.5%. GharKundli's full report compares construction progress with the deadline.
Does Poonam Chhaya CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Poonam Chhaya CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL is registered on MahaRERA as PR1330002501631, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Poonam Chhaya CHSL?
Poonam Chhaya CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Poonam Chhaya CHSL?
For a flat in Poonam Chhaya CHSL (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Poonam Chhaya CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Poonam Chhaya CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL is a redevelopment: 29 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Poonam Chhaya CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Poonam Chhaya CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Poonam Chhaya CHSL's possession date changes?
The latest dates are on Poonam Chhaya CHSL's MahaRERA page (PR1330002501631). GharKundli's Kundli Watch sends a free WhatsApp update on Poonam Chhaya CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Poonam Chhaya CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL has one building filed: POONAM CHHAYA CO OPERATIVE HOUSING SOCIETY LIMITED with 17 floors and 59 units.
How much parking does Poonam Chhaya CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 62 covered car parking spaces for Poonam Chhaya CHSL.
How big is the land of Poonam Chhaya CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL stands on 1,858 sq m of land (about 0.5 acres), with 6,416 sq m of sanctioned built-up area.
What are the reviews of Poonam Chhaya CHSL?
Google Maps has reviews of Poonam Chhaya CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Poonam Chhaya CHSL?
Poonam Chhaya CHSL by VASTU VAIBHAV CREATIONS LLP is in Naupada S.O (Thane), Thane, pincode 400602 (near Panchpakhadi, Thane West, Charai), Maharashtra, and is registered on MahaRERA as PR1330002501631, per GharKundli's check of MahaRERA records. Its boundaries filed there include OFF Madanlal Dhingra Road. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Poonam Chhaya CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL has 59 homes in 1 tower registered on MahaRERA, and 3% of them are sold or booked.
When was Poonam Chhaya CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Poonam Chhaya CHSL was registered on MahaRERA on 2 December 2025. GharKundli did not find a title report on the land on file there.
Does Poonam Chhaya CHSL have any legal issues or court cases?
No court cases are listed for Poonam Chhaya CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Poonam Chhaya CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VASTU VAIBHAV CREATIONS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Poonam Chhaya CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Naupada (400602)
- Asavari Co Op HSG Soc LTD
- The Lake Corner
- Platinum Square
- Parvati Niwas
- Rivanta
- Ekatva Crescent
- Pitruchhaya
- Navyug Co.Op.Hsg.Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.