Shubh Shrushti LM
by VINAYAK ENTERPRISES · Katrap, Thane
Registered on MahaRERA under PR1330002600322, and currently active. Its completion date has moved from December 2028 to April 2029, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Shubh Shrushti LM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002600322
- Status
- Registered and active
- Builder
- VINAYAK ENTERPRISES
- Location
- Katrap, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 4 May 2026
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- Delay so far
- 4 months
- Homes
- 108
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Kundli Watch
Shubh Shrushti LM: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Shubh Shrushti LM
Is Shubh Shrushti LM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shubh Shrushti LM is registered as PR1330002600322 and its status is "Registered and active".
Where is Shubh Shrushti LM?
Shubh Shrushti LM by VINAYAK ENTERPRISES is in Katrap, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as PR1330002600322, per GharKundli's check of MahaRERA records.
When is possession of Shubh Shrushti LM due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shubh Shrushti LM in Katrap, Thane is 30 April 2029 — 4 months later than 31 December 2028, the date given at registration.
Does Shubh Shrushti LM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Shubh Shrushti LM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VINAYAK ENTERPRISES, which has 5 other projects registered on MahaRERA.
Other projects in pincode 421503
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.