Divya Merry Mansion
by Divya Enterprises · Ambernath, Thane 421501Also near Wimco NakaRegistered on MahaRERA as “MERRY MANSION”
What’s in the report? →Possession date of Divya Merry Mansion (MahaRERA PM1330002502661): 18 September 2028. It has 35 homes, 10% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1330002502661, and currently active. Its completion date is now September 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1330002502661, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Divya Merry Mansion?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Divya Merry Mansion has moved
18 May 2028
Completion date given when the project was registered
18 September 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Divya Merry Mansion’s extension records on MahaRERA (PM1330002502661), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Divya Merry Mansion
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1330002502661
- Status
- Registered and active
- Builder
- Divya Enterprises
- Location
- Ambernath, Thane · 421501
- Project type
- Mixed
- Registered on
- 9 Mar 2026
- Completion date at registration
- May 2028
- Latest completion date
- September 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 35
- Sold or booked
- 10%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Divya Merry Mansion, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Merry Mansion | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Merry Mansion: covers 7 floors
Latest CC order on MahaRERA: dated 07/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Divya Merry Mansion every 1–2 months.
Divya Merry Mansion: buildings, flats and land, as filed on MahaRERA
- Buildings: Merry Mansion (7 floors, 44 units)
- Car parking: 13 covered
- Land: 903 sq m (about 0.2 acres) · sanctioned built-up 2,908 sq m
- Boundaries filed include: External Road
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Divya Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2026, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Divya Merry Mansion →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Divya Merry Mansion: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Divya Merry Mansion
What is the possession date of Divya Merry Mansion?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Divya Merry Mansion in Ambernath, Thane is 18 September 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Divya Merry Mansion?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Divya Merry Mansion's builder has filed on MahaRERA, the official one, is 18 September 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Divya Merry Mansion?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Divya Merry Mansion in Ambernath, Thane is PM1330002502661.
Is Divya Merry Mansion registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion is registered as PM1330002502661 and its status is "Registered and active".
What is the current construction status of Divya Merry Mansion? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Merry Mansion is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Divya Merry Mansion have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Divya Merry Mansion safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion is registered on MahaRERA as PM1330002502661, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Divya Merry Mansion?
Divya Merry Mansion is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Divya Merry Mansion?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Divya Merry Mansion: gharkundli.com/tools/property-cost-calculator
Has Divya Merry Mansion received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion is still under construction, with 18 September 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Divya Merry Mansion uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Divya Merry Mansion was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Divya Merry Mansion's possession date changes?
The latest dates are on Divya Merry Mansion's MahaRERA page (PM1330002502661). GharKundli's Kundli Watch sends a free WhatsApp update on Divya Merry Mansion every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Divya Merry Mansion have?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion has one building filed: Merry Mansion with 7 floors and 44 units.
How much parking does Divya Merry Mansion have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for Divya Merry Mansion.
How big is the land of Divya Merry Mansion?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion stands on 903 sq m of land (about 0.2 acres), with 2,908 sq m of sanctioned built-up area.
What is the track record of Divya Merry Mansion's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Enterprises (a group of 2 linked companies) has 2 projects on MahaRERA since 2026, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Divya Merry Mansion?
Google Maps has reviews of Divya Merry Mansion written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Divya Merry Mansion?
Divya Merry Mansion by Divya Enterprises is in Ambernath, Thane, pincode 421501 (near Wimco Naka), Maharashtra, and is registered on MahaRERA as PM1330002502661, per GharKundli's check of MahaRERA records. Its boundaries filed there include External Road. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Divya Merry Mansion, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion has 35 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.
When was Divya Merry Mansion registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Divya Merry Mansion was registered on MahaRERA on 9 March 2026. GharKundli did not find a title report on the land on file there.
Does Divya Merry Mansion have any legal issues or court cases?
No court cases are listed for Divya Merry Mansion on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Divya Merry Mansion?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Divya Enterprises.
Check it yourself on MahaRERA
- How to check the possession date of Divya Merry Mansion
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Ambernath (421501)
- Paritosh Co Operative Housing Society Limited
- New Neelgagan CHS
- Next Crown Landmark
- Mahadev Heights
- Chadha Residency
- Panvelkar Daffodils-Plot No. 11,12,13
- Neelkanth Royale Palms - F Wing Phase II
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.