Birla Taranya - Retail 1
by Ekamaya Properties Private Limited (Birla) · Ground Floor, Hindalco Industries, Thane 400605Also near Kalwa, Thane East
What’s in the report? →Possession date of Birla Taranya - Retail 1 (MahaRERA PC1331012502738): 31 July 2032. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PC1331012502738, and currently active. Its completion date is now July 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PC1331012502738, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Birla Taranya - Retail 1?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Birla Taranya - Retail 1 has moved
31 March 2032
Completion date given when the project was registered
31 July 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Birla Taranya - Retail 1’s extension records on MahaRERA (PC1331012502738), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Birla Taranya - Retail 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the July 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PC1331012502738
- Status
- Registered and active
- Builder
- Ekamaya Properties Private Limited
- Location
- Ground Floor, Hindalco Industries, Thane · 400605
- Project type
- Commercial
- Registered on
- 12 Mar 2026
- Completion date at registration
- March 2032
- Latest completion date
- July 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Birla Taranya - Retail 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Commercial (Retail) Wing | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Commercial (Retail) Wing: covers 2 Basement + Ground + 1st Floor
Latest CC order on MahaRERA: dated 21/01/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Birla Taranya - Retail 1 every 1–2 months.
Birla Taranya - Retail 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Commercial (Retail) Wing (4 floors, 29 units)
- Car parking: 94 covered
- Land: 59,401 sq m (about 14.7 acres) · sanctioned built-up 6,455 sq m · recreational space 5,564 sq m
- Boundaries filed include: Railway Track
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Birla Estates (a group of 3 linked companies) has 7 projects on MahaRERA since 2024, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Birla Taranya - Retail 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Birla Taranya - Retail 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Birla Taranya - Retail 1
What is the possession date of Birla Taranya - Retail 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Birla Taranya - Retail 1 in Ground Floor, Hindalco Industries, Thane is 31 July 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Birla Taranya - Retail 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Birla Taranya - Retail 1's builder has filed on MahaRERA, the official one, is 31 July 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Birla Taranya - Retail 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Birla Taranya - Retail 1 in Ground Floor, Hindalco Industries, Thane is PC1331012502738.
Is Birla Taranya - Retail 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 is registered as PC1331012502738 and its status is "Registered and active".
What is the current construction status of Birla Taranya - Retail 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Commercial (Retail) Wing is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Birla Taranya - Retail 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Birla Taranya - Retail 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 is registered on MahaRERA as PC1331012502738, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Birla Taranya - Retail 1?
Birla Taranya - Retail 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Birla Taranya - Retail 1?
For a flat in Birla Taranya - Retail 1 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Birla Taranya - Retail 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 is still under construction, with 31 July 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Birla Taranya - Retail 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Birla Taranya - Retail 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Birla Taranya - Retail 1's possession date changes?
The latest dates are on Birla Taranya - Retail 1's MahaRERA page (PC1331012502738). GharKundli's Kundli Watch sends a free WhatsApp update on Birla Taranya - Retail 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Birla Taranya - Retail 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 has one building filed: Commercial (Retail) Wing with 4 floors and 29 units.
How much parking does Birla Taranya - Retail 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 94 covered car parking spaces for Birla Taranya - Retail 1.
How big is the land of Birla Taranya - Retail 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 stands on 59,401 sq m of land (about 14.7 acres), with 6,455 sq m of sanctioned built-up area and 5,564 sq m of recreational open space.
What is the track record of Birla Taranya - Retail 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Estates (a group of 3 linked companies) has 7 projects on MahaRERA since 2024, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Birla Taranya - Retail 1?
Google Maps has reviews of Birla Taranya - Retail 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Birla Taranya - Retail 1?
Birla Taranya - Retail 1 by Ekamaya Properties Private Limited (Birla) is in Ground Floor, Hindalco Industries, Thane, pincode 400605 (near Kalwa, Thane East), Maharashtra, and is registered on MahaRERA as PC1331012502738, per GharKundli's check of MahaRERA records. Its boundaries filed there include Railway Track. GharKundli lists all 58 MahaRERA projects in Kalwa (400605).
How many flats are in Birla Taranya - Retail 1, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 has 0 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Birla Taranya - Retail 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Birla Taranya - Retail 1 was registered on MahaRERA on 12 March 2026. GharKundli did not find a title report on the land on file there.
Does Birla Taranya - Retail 1 have any legal issues or court cases?
1 court case is listed for Birla Taranya - Retail 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Birla Taranya - Retail 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ekamaya Properties Private Limited, the company Birla files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Birla Taranya - Retail 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- Birla Taranya - Phase 1
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Gurukrupa Nityam
- Mauli Krupa
- Urban Reserve Wing B
- Panache
- Lotus
Other projects by Ekamaya Properties Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.