OM SAI HEIGHTS

by OM SAI DEVELOPERS · Airoli, Thane

Registered on MahaRERA under PR1330002600071, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on OM SAI HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1330002600071
Status
Registered and active
Builder
OM SAI DEVELOPERS
Location
Airoli, Thane · 400708
Project type
Residential / Group Housing
Registered on
10 Apr 2026
Completion date at registration
December 2029
Latest completion date
April 2030
Delay so far
4 months
Homes
28
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
31

Kundli Watch

OM SAI HEIGHTS: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about OM SAI HEIGHTS

Is OM SAI HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), OM SAI HEIGHTS is registered as PR1330002600071 and its status is "Registered and active".

Where is OM SAI HEIGHTS?

OM SAI HEIGHTS by OM SAI DEVELOPERS is in Airoli, Thane (pincode 400708), Maharashtra, and is registered on MahaRERA as PR1330002600071, per GharKundli's check of MahaRERA records.

When is possession of OM SAI HEIGHTS due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for OM SAI HEIGHTS in Airoli, Thane is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.

Does OM SAI HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of OM SAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OM SAI DEVELOPERS, which has 31 other projects registered on MahaRERA.

Other projects in pincode 400708

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.